You are on page 1of 35

SIMHADRI STAGE-II -2X500MW FD F

FAN COMMG FLOW DIAGRAM

MOTOR NO LOAD TRIAL-8 HRS + OPN LOGS +CHECKLISTS FILLED +DOR CHECK

POWER SUPPLY ELECTRICAL


C & I READINESS
READINESS READINESS LUB OIL FLUSHING

3.3KV SWGR 3UAA/UAB MOTOR CHECKS P&I CHECKS


P&I CHECKS
COMMG +TESTS

11KV SWGR 3UA/UB P&I CHECKS TANT INSP +OIL FILLING


DDCMIS CHECKOUT
COMMG + P/P TRIAL+HT

11 KV STN SB/SC POWER+CONTROL LUB OIL P/PS MOTOR


CABLE CHECKS CER/CCR CHECK CHECK NO LOAD TRIAL
COMMG

LOCAL & REMOTE LUB OIL LINES ACID


ST#1 CHARGED /FROM BREAKER CHECKS CLEANING
SA CHARGED INSTRUMENTATION

CABLING:FIELD -JB, JB- APPROVED PRO FROM


DC SUPPLY READINESS SWITCH GEAR CHECKS PANEL CC -OS + CHEMICALS A

MOTOR + CABLE +INSTRUMENT ERECTION COMPLETION LUB OIL ERECTION


ERECTIO & FQA LOGS MADE COMPLETION

CABLE ERECTED+ PIPE LINE +INSTUME


MOTOR ERECTED SAFETY READINESS
TAGGING OVER ERECTION

CABLE TRESTLE FOUNDATION DECK PROPER APPROACH


CASTED LUB OIL SKID ERECT
ERECTED +HAND RAILS +FIRE
FIGHTING SY. AV

LIE/LIR ERECTION FD FAN HANDLING ERECTION


FD FAN COMMISSIONING PROGRAMME

FD FAN TRIAL RUN -8 HRS +OPN LOGS + CHECK LISTS FILLED

FAN-MOTOR ALIGNMENT P&I CHECKS

FAN + INSTRUMENT ERECTION PROPER APPROACH


LUB OIL FLUSHING COMPLETION + ERECT. -FQA LOGS +HAND RAILS

BLADE PITCH ERECTION


P&I CHECKS BLADEPITCH COMMG
COMPLETION

TANT INSP +OIL FILLING DISCHARGE GATE


BVDC MCC BVDC COMMG COMMG
+ P/P TRIAL+HT

LUB OIL P/PS MOTOR DISCHERGE GATE


BMCC COMMG ERECTION COMPLETION
CHECK NO LOAD TRIAL

LUB OIL LINES ACID


CLEANING DUCT AIR LEAK APPROVED PRO. FROM
CC-OS

APPROVED PRO FROM


CC -OS + CHEMICALS AV

LUB OIL ERECTION ECW LINES COMPLETION +


COMPLETION FLUSHING + HT

PIPE LINE +INSTUMENT


ERECTION

LUB OIL SKID ERECTION


P&I CHECKS

DUCT READINESS

GATE

GATE INSULATION CHECK OUT


OMPLETION

ROVED PRO. FROM SUPPORT CHECKOUT+ DUCT


AIR LEAK TEST

DUCT INSTRUMENTATION CHECK


OUT

SUCTION / DISCHARGE DUCT + C&I


INSTRU.ERECTION COMPLETION
SIMHADRI STAGE-II -2X500MW ID FAN
COMMG FLOW DIAGRAM
AC CHECK OUT ID

MOTOR NO LOAD TRIAL-8 HRS + OPN LOGS +CHECKLISTS FILLED +DOR CHECK

POWER SUPPLY ELECTRICAL


READINESS READINESS
C & I READINESS
LUB OIL FLUSHING
VFD+ESP/ID FAN EMCC MOTOR CHECKS
COMMD +TESTS

ESPT#3A/B,3C/D & ESP# P&I CHECKS P&I CHECKS


P&I CHECKS
3A/B ,C/D COMMGD

11KV SWGR 3UA/UB VFD + BREAKER TANT INSP +OIL FILLING


CHECKS DDCMIS CHECKOUT
COMMG + P/P TRIAL+HT

11 KV STN SB/SC POWER+CONTROL LUB OIL P/PS MOTOR


CABLE CHECKS CER/CCR CHECK CHECK NO LOAD TRIAL
COMMG

LOCAL & REMOTE LUB OIL LINES ACID


ST#1 CHARGED /FROM BREAKER CHECKS CLEANING
SA CHARGED INSTRUMENTATION

CABLING:FIELD -JB, JB- APPROVED PRO FROM


DC SUPPLY CC -OS + CHEMICALS A
SWITCH GEAR CHECKS PANEL
(24V+220V)READINESS

MOTOR + CABLE +INSTRUMENT ERECTION COMPLETION


ERECTIO & FQA LOGS MADE

CABLE ERECTED+ MOTOR ERECTED SAFETY READINESS


TAGGING OVER

CABLE TRESTLE FOUNDATION DECK PROPER APPROACH


ERECTED CASTED +HAND RAILS +FIRE
FIGHTING SY. AV

LIE/LIR ERECTION ECW LINES COMPLETION +


FLUSHING + HT

ID FAN HANDLING ERECTION


ID FAN HANDLING ERECTION
ID FAN COMMISSIONING PROGRAMME

ID FAN TRIAL RUN -8 HRS +OPN LOGS + CHECK LISTS FILLED

FAN-MOTOR ALIGNMENT P&I CHECKS

FAN + INSTRUMENT ERECTION PROPER APPROACH


LUB OIL FLUSHING COMPLETION + ERECT. -FQA LOGS +HAND RAILS

IGV ERECTION
P&I CHECKS IGV COMMG
COMPLETION

TANT INSP +OIL FILLING ESP-ID FAN EMERGENCY SUCTION+DISCHARGE GATES


ESP/ID FAN MCC MCC COMMG COMMG
+ P/P TRIAL+HT

LUB OIL P/PS MOTOR ESP/ID FAN EMCC+ SUCTION+DISCHERGE GATE


CHECK NO LOAD TRIAL BMCC ERECTION COMPLETION

LUB OIL LINES ACID


CLEANING DUCT AIR LEAK APPROVED PRO. FROM
CC-OS

APPROVED PRO FROM


CC -OS + CHEMICALS AV

LUB OIL ERECTION ECW LINES COMPLETION +


COMPLETION FLUSHING + HT

PIPE LINE +INSTUMENT


ERECTION

LUB OIL SKID ERECTION


P&I CHECKS CHIMNEY
READINESS

LIFT + CHIMNEY CHECKOUT

CHIMNEY + LIFT ERECTION

DUCT READINESS

SCHARGE GATES

SCHERGE GATE INSULATION CHECK OUT


OMPLETION

ROVED PRO. FROM SUPPORT CHECKOUT+ DUCT


AIR LEAK TEST

DUCT INSTRUMENTATION CHECK


OUT

SUCTION / DISCHARGE DUCT + C&I


INSTRU.ERECTION COMPLETION
SIMHADRI STAGE-II -2X500MW CC C
PUMP COMMG FLOW DIAGRAM
C

CC PUMP

ELECTRICAL
READINESS

MOTOR CHECKS
+TESTS

P&I CHECKS

POWER+CONTROL
CABLE CHECKS

BREAKER CHECKS

SWITCH GEAR CHECKS DC SUPPLY READI

MOTOR +PUMP ERECTION COMPLETION

ECW LINES COMPLETION +


ID FAN HANDLING ERECTION MOTOR +PUMP +INSTRUMENT ERECTION FLUSHING + HT

CABLE ERECTED+ PRESSURE PARTS HT SAFETY READINESS


TAGGING OVER

CABLE TRESTLE PRESSUREPARTS ERECTION PROPER APPROACH +HAND RAILS +FIRE


ERECTED FIGHTING SY. AV

LIE/LIR ERECTION
CC PUMP COMMISSIONING PROGRAMME

CC PUMP TRIAL RUN -8 HRS +OPN LOGS + CHECK LISTS FILLED

PUMP READINESS P&I CHECKS

HP/LP PURGE LINE


POWER SUPPLY C & I READINESS EMERGENCY CW READINESS READINESS
READINESS

3.3KV SWGR 3UAA/UAB DDCMIS CHECKOUT


COMMG HP/LP LINE PURGING

11KV SWGR 3UA/UB


COMMG CER/CCR CHECK
INSTRUMENT+FILTER
CHECKOUT

11 KV STN SB/SC P&I CHECKS


LOCAL & REMOTE
COMMG INSTRUMENTATION HP/LP PURGE LINE HT+
STEAM BLOWING

ST#1 CHARGED /FROM CABLING:FIELD -JB, JB-


SA CHARGED PANEL HP/LP PURGE LINE ER
COMPLETION
BOOSTER PUMP CHECKS+LINES
DC SUPPLY READINESS FLUSHING
TANK INSPECTION
+FLUSHING

BOOSTER PUMP -MOTOR ECW OVERHEAD TANK


BOOSTER PUMP ERECTION +INSTRUM ERECTION
ALIGNMENT

ECW LINES COMPLETION +


FLUSHING + HT
SUCTION +DISCHARGE LINES + MOTOR +CABLE TESTS +NO
BMCC COMMG
INSTRUMENT ERECTION COMPLETION LOAD TRIAL
DINESS

CABLE ERECTED+
ROACH +HAND RAILS +FIRE BOOSTER PUMP MOTOR ERECTION
TAGGING OVER
. AV

CABLE TRESTLE
FOUNDATION
SAFETY READINESS ERECTED

PROPER APPROACH +HAND RAILS +FIRE LIE/LIR ERECTION


FIGHTING SY. AV
PROPER APPROACH +HAND RAILS +FIRE LIE/LIR ERECTION
FIGHTING SY. AV
P&I CHECKS

HP/LP PURGE LINE


READINESS

HP/LP LINE PURGING

INSTRUMENT+FILTER
CHECKOUT

HP/LP PURGE LINE HT+


STEAM BLOWING

HP/LP PURGE LINE ERECTION


COMPLETION

TANK INSPECTION
+FLUSHING

ECW OVERHEAD TANK


+INSTRUM ERECTION

BMCC COMMG

CABLE ERECTED+
TAGGING OVER

CABLE TRESTLE
ERECTED

LIE/LIR ERECTION
LIE/LIR ERECTION
DC SCA
SIMHADRI STAGE-II -2X500MW DC SCANNER
AIR FAN COMMG FLOW DIAGRAM

MOTOR NO LOAD TRIAL-4 HRS + OPN LOGS +CHECKLISTS FILLED +DOR CHECK FAN-MOTOR

POWER SUPPLY ELECTRICAL FAN ERECTION CO


C & I READINESS
READINESS READINESS

MOTOR CHECKS
LOCAL STARTER PANEL P&I CHECKS
+TESTS SUCTION FITER ER

STARTER PANEL P&I CHECKS DDCMIS CHECKOUT


SUCTION + DISCH
ERECTION COMPL
POWER+CONTROL
220 DCDB CABLE CHECKS CER/CCR CHECK

LOCAL & REMOTE


220 V CHARGER COMMG STARTER PANEL CHECK INSTRUMENTATION

CABLING:FIELD -JB, JB-


220 BATTERY BANK BATTERY BANK CHECK PANEL

MOTOR + CABLE +INSTRUMENT ERECTION COMPLETION


ERECTIO N- FQA LOGS MADE

CABLE ERECTED+ MOTOR DECOUPLED SAFETY READINESS


TAGGING OVER

CABLE TRESTLE DC SCANNER AIR FAN PROPER APPROACH


ERECTED SKID ERECTION +HAND RAILS +FIRE
FIGHTING SY. AV

LIE/LIR ERECTION LOCAL DC STARTE PANEL


ERECTED
DC SCANNER AIR FAN COMMISSIONING PROGRAMME

SCANNER AIR FAN TRIAL RUN -4 HRS +OPN LOGS + CHECK LISTS FILLED

FAN-MOTOR ALIGNMENT P&I CHECKS

FAN ERECTION COMPLETION

SUCTION FITER ERECTION DISCHARGE DAMPER COMMD EMERGENCY DAMPER COMMD

SUCTION + DISCHARGE DUCT+C&I DISCHARGE DAMPER ERECTION 24V SV + IAC CHECK OUT
ERECTION COMPLETION
S FILLED

P&I CHECKS LINES FLUSHING FROM FD FAN

Y DAMPER COMMD

CHECK OUT EMERGENCY DAMPER ERECTION


AC SCAN
SIMHADRI STAGE-II -2X500MW AC
SCANNER AIR FAN COMMG FLOW
DIAGRAM

MOTOR NO LOAD TRIAL-4 HRS + OPN LOGS +CHECKLISTS FILLED +DOR CHECK FAN-MOTOR

POWER SUPPLY ELECTRICAL FAN ERECTION CO


C & I READINESS
READINESS READINESS

MOTOR CHECKS
BMCC P&I CHECKS
+TESTS SUCTION FITER ER

UNIT SERVECE SWGR P&I CHECKS DDCMIS CHECKOUT


SUCTION + DISCH
ERECTION COMPL
11KV SWGR UA/UB POWER+CONTROL
COMMG +UST CABLE CHECKS CER/CCR CHECK

11 KV STN SB/SC COMMG LOCAL & REMOTE


BMCC MODULE CHECK INSTRUMENTATION
+UA/UB COMMG

ST#1 CHARGED /FROM CABLING:FIELD -JB, JB-


SA CHARGED DC SUPPLY READINESS PANEL

MOTOR + CABLE +INSTRUMENT ERECTION COMPLETION


ERECTIO N- FQA LOGS MADE

CABLE ERECTED+ MOTOR DECOUPLED SAFETY READINESS


TAGGING OVER

CABLE TRESTLE DC SCANNER AIR FAN PROPER APPROACH


ERECTED SKID ERECTION +HAND RAILS +FIRE
FIGHTING SY. AV

LIE/LIR ERECTION LOCAL DC STARTE PANEL


ERECTED
AC SCANNER AIR FAN COMMISSIONING PROGRAMME

SCANNER AIR FAN TRIAL RUN -4 HRS +OPN LOGS + CHECK LISTS FILLED

FAN-MOTOR ALIGNMENT P&I CHECKS

FAN ERECTION COMPLETION

SUCTION FITER ERECTION DISCHARGE DAMPER COMMD EMERGENCY DAMPER COMMD

SUCTION + DISCHARGE DUCT+C&I DISCHARGE DAMPER ERECTION 24V SV + IAC CHECK OUT
ERECTION COMPLETION
S FILLED

P&I CHECKS PIPE LINE FLUSHING FROM FD FAN

Y DAMPER COMMD

CHECK OUT EMERGENCY DAMPER ERECTION


SIMHADRI STAGE-II -2X500MW
BOILER HT COMMG FLOW DIAGRAM

B O I L E R

AVAILABILITY OF CC APPR
BOILER ERECTION COMPLETION PROCEDURE

PUMPS R
 AIR CO
 SYSTEM CONNECTED WITH HT ERECTED AS PER  BOILE
DRAWING
 3 NOS PRESSURISING
 HP WELDS & NDT TEST COMPLETED AND STRESS (26/16/12 l/m)25/40 HP
RELIEVED
 FQA CHECKS OVER & LOGS AVAILABLE
 HANGERS SET/LOCKED AS PER RECOMMENDATIONS
 AS PER EXPANSION DRAWING , CLEARANCES CONSUMABLES
CHECKED AND LOGGED FOR THERMAL MOVEMENT  DM WATE STAGE-I/I
OF SYSTEM  HYDRAZINE STAGE-I
 ALL RADIOGRAPHS AND STRESS RELIEVING CHARTS  AMMONIA
OF PRESSURE PARTS SYSTEM ACCEPTED AND
SIGNED BY BOILER INSPECTOR
 ALL SAFETY VALVES WITH SHOP INSTALLED
HYDROSTATIC PLUG ARE INSTALLED
 CC PUMPS VOLUTES ARE BLANKED
 ALL BUCKSTAYS ARE COMPLETED ALONG WITH
CORNERS CONNECTIONS AND FREE TO EXPAND
 ALL FIN WELDING ARE COMPLETED.
 ALL ATTACHMENT WELDING COMPLETED
 ISOLATING VALVES/BLANKS ARE PROVIDED TO ALL
THE OTHER BRANCHING SYSTEM LIKE SOOT BLOWER
SYSTEM TAPPING, SH/RH SPRAY CONNECTION,
PRESSURE GAUGES ETC.,
 ALL NECESSARY VALVES INCLUDING DRAIN AND VENT
VALVES ARE INSTALLED
 CHECK THE ENTIRE BOILER TO MAKE CERTAIN THAT
ALL TEMPORARY TIES TO STRUCTURAL STEEL ARE
REMOVED
 ALL THE JOINTS OF TEMPORARY LINES(LIKE NEAR
DRAIN HEADER FOR PRESSURIZING PUMP
CONNECTION) ARE TO BE WELDED WITH HP
WELDERS AND ADEQUATELY SUPPORTED
 RADIOGRAPHIC PLUGS ARE WELDED AND
INSTRUMENT TAPPINGS ARE CLOSED
 READINESS OF STAIR-CASES, HAND RAILS,
PLATFORMS, APPROACHES ETC., SHOULD BE
ENSURED
WELDERS AND ADEQUATELY SUPPORTED
 RADIOGRAPHIC PLUGS ARE WELDED AND
INSTRUMENT TAPPINGS ARE CLOSED
 READINESS OF STAIR-CASES, HAND RAILS,
PLATFORMS, APPROACHES ETC., SHOULD BE
ENSURED
BOILER HYDRAULIC TEST

E R H Y D R A U L I C T E S T

AVAILABILITY OF CC APPROVED STATUTORY REREQUIREMENTS


PROCEDURE

PUMPS REQUIRED PR.GAUSES REQUIRED SAFETY REQUIREMEN


 AIR COMPRESSOR  3 NOS PR.GAUGES  24 V LAMPS ONL
 BOILER FILL PUMP  RANGE FOR AIR TEST 0-4 KSC  ENTRY TO BE RESTRICTE
 3 NOS PRESSURISING PUMPS  RANGE FOR ST-I 0-600 KSC  DELIVERY LINE OF PRESSURIZING PUMPS
(26/16/12 l/m)25/40 HP  RANGE FOR ST-II (RH)0-200 KSC SHOULD BE HIGH PRESSURE SEAMLESS PIPE
TO WITHSTAND THE REQUIRED HIGH
PRESSUR

CONSUMABLES REQUIRED
 DM WATE STAGE-I/II-------700 M3
 HYDRAZINE STAGE-I/II—500/300L
 AMMONIA—150/100 L
SAFETY REQUIREMENT
 24 V LAMPS ONLY
 ENTRY TO BE RESTRICTED
OF PRESSURIZING PUMPS
PRESSURE SEAMLESS PIPE
HE REQUIRED HIGH
PRESSURE
SIMHADRI STAGE-II -2X500MW ESP
COMMG FLOW DIAGRAM

E L E C T R O S T A T I C P R E C I

ESP INSULATION COMPLETION ESP ELECTRICAL SUPPLY READINESS

AIR LEAK TEST COMPLETION CHARGING OF EP


PANELS

ESP AIR LEAK TEST

APPROVED PROCEDURE
FROM CC-OS
CHARGING OF ACP ESP AC SYSTEM +
#A/B/C/D CR READY
ESP ERECTION FOR AIR LEAK TEST

CHARGING OF ACP
#A/B/C/D
MEASURING
APPROACHES
INSTRUMENTS ERECTED
FOR CHECKING
TEST ERECTED CHARGING OF ESP
BOARD A/B/C/D

COLLECTING/EMITTING
FAN & MOTOR REQUIRED FOR AIR CHARGING OF LOAD TRIAL
LEAKTEST ERECTED. ESPT#A/B/C/D

COLLECTING/EMITTING
11KV SWGR 3UA/UB RAPPERS MOTORS NO
ESP CASING,HOPPERS.INTERNALS COMMG
,INLET/OUTLET FUNNELS ERECTION
COMPLETION & DUCT /HOPPER OUT COLLECTING/EMITTIN
LETS DUMMIED & ESP NOT 11 KV STN SB/SC
COMMG RAPPERS MOTORS + C
INSULATED.

ST#1 CHARGED /FROM COLLECTING/EMITTIN


SA CHARGED RAPPERS ERECTION C

SCRREN COLLECTING /
EMITTING /GD RAPPERS MOTOR
ERECTION COMPLETION
SCRREN COLLECTING /
EMITTING /GD RAPPERS MOTOR
ERECTION COMPLETION

COLLECTING/EMITT
SCREEN RAPPER E
COMPLETION
P R E C I P I T A T O R R E A D I N E S S

OPACITY SYSTEM HOPPERS KNIFE GATES


COMMISSIONED COMMISSIONING

OPACITY SYSTEM HOPPERS KNIFE GATES


ERECTION COMPLETION ERECTION COMPLETION

ESP A U X I LI R I ES READINESS
INLET/OUT LET GATES
COMMISSIONING

P AC SYSTEM +
READY
INLET/OUT LET GATES
ERECTION COMPLETION

FLUEDISING
BLOWERS
COMMISSIONING
HOPPER LEVEL TRANSMITTER
INTERLOCK WITH FIELD CHECKING
FLUEDISING
COLLECTING/EMITTING RAPPERS BLOWERS ERECTION
LOAD TRIAL COMPLETION HOPPER LEVEL TRANSMITTER
COMMISSIONING

COLLECTING/EMITTING/GD SCREEN FLUEDISING PADS


RAPPERS MOTORS NO LOAD TRIAL ERECTION HOPPER LEVEL TRANSMITTERS
COMPLETION ERECTION COMPLETION

COLLECTING/EMITTING/GD SCREEN
RAPPERS MOTORS + CABLES TESTS HOPPERS HEATERS
COMMISSIONING +INTERLOCK INSULATOR HEATERS
CHECKING COMMISSIONING
COLLECTING/EMITTING /GD SCREEN
RAPPERS ERECTION COMPLETION
HOPPERS HEATERS ERECTION Shaft/SUPPORT insulator
COMPLETION heater ERECTION COMPLETION
OLLECTING / CONTROL +POWER
GD RAPPERS MOTOR CABLE LAYING
OMPLETION
OLLECTING / CONTROL +POWER
GD RAPPERS MOTOR CABLE LAYING
OMPLETION POWER +CONTROL CABLE POWER +CONTROL CABLE
ERECTION ERECTION

COLLECTING/EMITTING/GD HOPPERS HEATERS Shaft/SUPPORT insulator heater


SCREEN RAPPER ERECTION +THERMOSTART ERECTION ERECTION
COMPLETION
FIELD CHARGED + TUNING

ASH EVACUATION SYSTEM FLUE GAS ALLOWED


READY

ESP SAFETY KEY CHECKING


SAFETY READINESS COMPLETION

DIFFERENT CHECKS/TESTS PROPER APPROACH ESP SAFETY KEY ERECTION


COMPLETION +HAND RAILS +FIRE COMPLETION
FIGHTING SY. AV

LET GATES DUMMY LOAD TEST


NING

T LET GATES VARIOUS INTERLOCKS


COMPLETION

GD TEST
ITTER
D CHECKING

FIELDS INTERNAL INSPECTION

HOPPERS INTERNAL
INSPECTION
SIMHADRI STAGE-II -2X500MW ECW
(SG) COMMG FLOW DIAGRAM
ECW PUMP TRIAL

P&I CHECKS
ECW

ECW MOTOR NO LOAD TRIAL +TS+CHECKLISTS +OPN LOGS

DISHCHARGE
ELECTRICAL POWER SUPPLY C&I READINESS VALVE COMMG
READINESS READINESS

MOTOR P& I UNIT SERVICE P&I CHECKS TVDC COMMG


CHECKS SWGR COMMG

MOTOR CHECKS UST#3A/B OR DDCMIS CHECKS


+TESTS EMERG SWGR

POWER + CER/CCR CHECKS


CONTROL CABLE 11KV SWGR
CHECKS +TESTS 3UA/UB COMMG

BREAKER ST#1 CHARGED INSTRUMENT


CHECKS /FROM SA CALIBRATION
CHARGED

DC SUPPLY PUMP MOTOR ALIGNMENT


SWGR CHECKS

MOTOR ERECTION COMPLETION +FQA -ERECTION LOGS PUMP ERECTION COMPLETION +FQA -EREC

MOTOR + C&I
INSTRU. ERECTION POWER+CONTROL LOCAL PANEL SAFETY READINESS PUMP + C& I
CABLING +TAGGING ERECTION INSTRU. ERECTION

CIVIL FOUNDATION CABLE TRESTLE PROPER APPROACH


ERECTION FIREFIGHTING SY.
+PLATFORMS + HOUSEKEEPING
+HANDRAILS
LIE/LIR ERECTION

NORMAL MAKE UP ECW OVERHEAD


LINES + VALVES TANK +INSRUMENT
ERECTION +HT ERECTION
+FLUSHING
NORMAL MAKE UP ECW OVERHEAD
LINES + VALVES TANK +INSRUMENT
ERECTION +HT ERECTION
+FLUSHING

EMERGENCY MAKE
UP LINES + VALVES
ERECTION +HT
PUMP TRIAL +OPN LOGS + TS + CHECKLIST

ECW P U M P READINESS

DISHCHARGE SUCTION DP CV COMMG MO DP ISO INDIVIDUAL EQUPT CW CV


VALVE COMMG VALVE COMMG
VALVE COMMG COMMG

TVDC COMMG TVDC COMMG IA+DC SV TVDC COMMG IA+DC SV


COMMG COMMG

R ALIGNMENT

ON COMPLETION +FQA -ERECTION LOGS

PUMP + C& I PIPE LINE INSTRUT.


INSTRU. ERECTION ERECTION
+ORIFICES FIXING
NAOH DOSING
SYSTEM ERECTION
LINES HT
+FLUSHING

CW OVERHEAD SUCTION
+DISCHARGE PHE ERECTION
NK +INSRUMENT
ECTION +RECIR. +VALVES
LUSHING ERECTION EXCEPT
CV
CW OVERHEAD SUCTION
+DISCHARGE PHE ERECTION
NK +INSRUMENT
ECTION +RECIR. +VALVES
LUSHING ERECTION EXCEPT
CV

You might also like