QMS-F-15
Capillary tube assy (3P355507-1A) Rev.Date-00/01-10-13
Receiving of Raw Material Receiving of Raw Material
Cu 6.35*0.7,6.4*0.8 mm(C1220TS-O) Capill OD 3.2*ID-1.8 mm(C1220T-OL)
IQC IQC
Reject
Not OK Not OK
OK Ok
Cutting Cutting
PQC PQC
Reject
Not OK Not OK
OK Ok
De Burring De Burring
Air Blowing
Air Blowing
PQC PQC
Reject
Not Ok
OK Not ok Ok
Expanding
Beading
Ok
Not Ok PQC
PQC Reject
Not Ok
OK
Blockage
Not Ok Testing
Reject
Expanding
Ok
Bending
To (A)
PQC
PROCESS FLOW DIAGRAM Doc.No.QMS-F-15
Capillary tube assy (3P355507-1A ) Rev.Date-00/01-10-13 TO
(A) TO
(B)
Brazing
Final Fitment
(Reducer+Capill)
Contamination testing
PQC 25mg/m²
Reject
Ok Not ok Not OK
OK
Blockage Testing
N2 Blowing & End
Reject Capping /Packing
Not OK
OK
Leakage Test
OK
OQC
O
Gauging Reject
Not OK
Ok
PQC Not OK
OK
To (B)
LEGEND:
IQC : INCOMING QUALTIY CONTROL
PQC: PROCESS QUALTIY CONTROL
OQC: OUTGOING QUALTIY CONTROL
IQC IQC
Reject
Not OK Not OK
OK Ok
Cutting Cutting
PQC PQC
Reject
Not OK Not OK
OK Ok
De Burring De Burring
Air Blowing
Air Blowing
PQC PQC
Reject Not ok
Not Ok
OK Ok
Bending Expanding
Gauging
PQC
Bending
Ok
Cleaning & N2 Blowing
PQC
PROCESS FLOW DIAGRAM Doc.No.QMS-F-15
Auxiliary inlet pipe assy (3P357458-1) Rev.Date-00/10-09-13
To(A)
TO (A) TO (B)
Dimple
Final Fitment
PQC
Not ok
Ok PQC
Reject
Brazing
Ok No
(Reducer+Capill+Distributor+Cu Not OK
tube OK
D)
OK
Gauging
LEGEND: To (B)
IQC : INCOMING QUALTIY CONTROL
PQC: PROCESS QUALTIY CONTROL
OQC: OUTGOING QUALTIY CONTROL
IQC IQC
Reject
Not OK Not OK
OK Ok
Cutting Cutting
PQC PQC
Reject
Not OK Not OK
OK Ok
De Burring De Burring
Air Blowing
Air Blowing
PQC PQC
Reject
Not Ok
OK Not ok Ok
Reducing
Beading
Ok
Not Ok PQC
PQC Reject
Not Ok
OK
Blockage
Not Ok Testing
Reject
Ok
Bending
Not Ok PQC
Reject
PROCESS FLOW DIAGRAM Doc.No.QMS-F-15
Capillary TubeCleaning
Assy &(4PN16086-1)
N2 Blowing Rev.Date-00/10-09-13
PQC
TO (A) TO (B)
Brazing
Final Fitment
(Reducer+Capill)
Contamination testing
PQC 25mg/m²
Reject
Ok Not ok Not OK
OK
Blockage Testing
N2 Blowing & End
Reject Capping /Packing
Not OK
OK
Leakage Test
OK
OQC
O
Gauging Reject
Not OK
Ok
PQC Not OK
OK
Ok To (B)
LEGEND:
IQC : INCOMING QUALTIY CONTROL
PQC: PROCESS QUALTIY CONTROL
OQC: OUTGOING QUALTIY CONTROL