Professional Documents
Culture Documents
FOR
OF
AT
FIGURES
ENCLOSURES
Page | 1
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
1. EXECUTIVE SUMMARY
M/s Hindalco Industries Ltd. (HIL) intends to produce 0.3 MTPA Bauxite as ROM
from Lakharshi Bauxite Mine over an area of 237.632 Ha. located at village(s)
Lakharshi, Rogapadar, Lalingpadar, Bhandapai, Kangatumba, Chiliguda &
Kalagaon, Tehsil-Kashipur, Dist-Rayagada, Odisha.
Mining Plan (under Rule 22 of Mineral Concession Rules, 1960) along with
Progressive Mine Closure Plan (under Rule 23B of MCDR, 1988) have been
prepared & approved by Indian Bureau of Mines, Ministry of Mines, Govt. of
India vide letter no MPM/OTFM 07-ORI/BHU/2012-13, dated 27.09.2012. The
copy of the approved letter is attached as Enclosure – 1.
Prospecting license has been approved by State Govt. vide letter no. II(BX) (SM)
13/01-3352/SM, Bhubaneswar dated 07.05.2004. The copy of the same is
attached as Enclosure – 2.
This Pre-feasibility Report along with Form-I and proposed Term of Reference
(TOR) are prepared for the prior environmental clearance from Ministry of
Environment, Forest and climate change.
Page | 2
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
2. INTRODUCTION OF THE PROJECT / BACKGROUND
INFORMATION
2(i) Identification of project and project proponent. In case of
mining project, a copy of mining lease/letter of intent
should be given.
The total mining lease are of Lakharshi Bauxite mine is 237.632 Hectare. Out of
total mining lease area, 117.572Ha area is DLC forest land, for which Diversion
proposal has been submitted to CCF (Nodal) vide letter no nil, dated 17.02.2012
(State serial no. 543, dated 26.06.2012) and copy of the same is attached as
Enclosure – 3.
Prospecting license has been approved by State Govt. vide letter no. II(BX) (SM)
13/10-3352/SM, Bhubaneswar dated 07.05.2004.
The Applicant, M/s Hindalco Industries Ltd is a registered public limited company
involved in mining, beneficiation, refining and smelting of minerals, particularly
bauxite. The registered office of Hindalco is at Century Bhavan, 3rd floor, Dr
Annie Besant Road, Worli, Mumbai-400030 and Orissa based office is at J-6,
Jaydev Vihar, Bhubaneswar-751013, Orissa.
Page | 3
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
This project on the basis of its merit comes under schedule no. 1(a) of Category
A projects eligible for screening, scoping & env. appraisal by MoEF, New Delhi.
General Geology
Applied area forms a segment of the east-central part of the Eastern Ghat hill
ranges. Rocks belonging to the khondalite and charnockite suites constitute the
major rock types of the area. In general, Khondalite forms high hills and peaks
where as charnockite is invariably confined to the valleys and slopes of hills. Both
the groups of rocks occur as concordant bands. It is a common feature to
observe islands of khondalite within charnockite rocks.
The geological succession tentatively worked out for the area is presented
below:
Page | 4
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Local Geology
As revealed from the local geological set up, the stratigraphy of the applied area
has been enumerated as follows:
The plateau top is covered with thin humus of 0.15 m to 0.3 m thickness. The
adjoining slopes and valleys are covered by screed and alluvium respectively.
Bauxite bearing area is mostly covered with humus and lateritic capping of
variable thickness. Soil patches are widely scattered and mostly occupy the
valleys.
Page | 5
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Laterite/Bauxite
Most of the plateau top exhibits laterites of varying thickness ranging from 3m to
5m. The laterite horizon is followed below by a transitional zone into moderately
good grade bauxite. In general, there is a gradual improvement in grade of
bauxite in depth which usually grades into a zone containing admixture of
bauxite and kaolinite which ultimately passes into altered khondalitic bedrock.
Laterite is usually brown, dark brown and brick red in colour. Both massive and
cavernous varieties are available, which are, at places, pisolitic in nature. Bauxite
is of pale pink, light brown to brick red colour and is either semi-massive or
cavernous. Gibbsite usually occurs as saccharoidal crystals and at places forms
district bands. In vesicular type of bauxite, crystalline gibbsite occurs as coatings
in the cavities. Goethite, limonite and clay occur in varying amounts. The
aluminous laterite boulders of the plateau contain gibbsite.
Bauxite (Al2O3 2H2O) is the mineral form of aluminium, occurring naturally in the
earth’s crust. It appears as a medium soft to hard rock, has a cellular, porous of
fine grained compact structure. It is formed by the weathering of sedimentary
rocks. Bauxite is normally found in a layer on the top of the plateau below a thin
layer of overburden.
Page | 6
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Khondalite
The lower reaches of the slopes surrounding the plateau expose khondalite. The
khondalite are often altered and the foliation NNE-SSW to N-S directions with
mostly sub-vertical dip. They are at places tightly folded into steep northerly
plunging isoclinal folds. The khondalite is mainly composed of quartz, feldspar,
garnet and sillimanite.
Grade
Sl. Sample Location Depth (m) LoI% SiO2% Fe2O3% Al2O3% TiO2%
No.
1 LR-1 CH-1 3.0-4.0 22.91 0.58 30.70 43.77 1.30
2 LR-2 CH-1 4.0-5.0 20.34 2.29 38.50 37.06 1.70
3 LR-3 CH-1 5.0-6.0 18.91 2.44 40.70 36.02 1.70
4 LR-4 CH-1 6.0-7.0 25.99 2.69 18.50 50.29 1.70
5 LR-5 CH-1 8.0-9.0 22.53 1.26 31.10 42.23 2.20
6 LR-6 CH-2 3.0-4.0 21.10 1.21 36.10 39.75 1.60
7 LR-7 CH-2 4.0-5.0 19.09 0.63 40.70 36.02 3.30
8 LR-8 CH-2 5.0-6.0 18.59 2.16 41.60 35.40 2.00
9 LR-9 CH-2 8.0-9.0 22.10 2.08 28.40 45.26 1.00
10 LR-10 CH-3 3.0-4.0 20.04 2.62 32.20 42.91 2.30
11 LR-11 CH-3 4.0-5.0 20.33 1.01 37.40 39.13 1.70
12 LR-12 CH-3 6.0-7.0 22.25 0.46 31.20 43.47 2.00
13 LR-13 CH-3 7.0-8.0 17.02 0.25 47.20 33.53 1.60
14 LR-14 CH-3 8.0-9.0 20.50 1.53 35.00 40.35 1.90
15 LR-15 CH-4 4.0-5.0 19.58 2.45 37.30 38.55 1.90
16 LR-16 CH-4 5.0-6.0 23.24 2.31 25.00 46.57 2.50
17 LR-17 CH-4 8.0-9.0 24.25 2.48 22.50 48.03 2.60
18 LR-18 CH-5 3.0-4.0 23.08 2.48 24.80 45.88 2.20
19 LR-19 CH-5 8.0-9.0 25.87 2.41 19.00 50.09 2.30
20 LR-20 CH-6 6.0-7.0 16.64 1.53 37.80 40.99 2.60
21 LR-21 CH-7 5.0-6.0 15.87 1.28 33.80 39.88 2.80
Page | 7
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Sl. Sample Location Depth (m) LoI% SiO2% Fe2O3% Al2O3% TiO2%
No.
22 LR-22 CH-8 8.0-9.0 20.80 2.10 33.30 39.75 1.70
23 LR-23 CH-9 5.0-6.0 20.82 2.30 36.90 37.78 2.00
24 LR-24 CH-9 6.0-7.0 28.23 2.14 13.90 53.41 1.90
25 LR-25 CH-9 8.0-9.0 20.33 1.20 39.10 36.64 2.40
26 LR-26 CH-10 0.0-1.0 23.75 1.92 29.60 41.90 2.20
27 LR-27 CH-11 5.0-6.0 25.43 2.92 23.30 46.17 1.70
28 LR-28 CH-11 8.0-9.0 21.60 2.52 33.40 40.23 1.70
29 LR-29 CH-12 3.0-4.0 23.75 2.74 25.60 45.43 1.80
30 LR-30 CH-12 5.0-6.0 21.75 2.83 30.40 41.71 1.90
31 LR-31 CH-12 8.0-9.0 24.75 1.23 25.60 45.75 2.60
32 LR-32 CH-13 4.0-5.0 22.92 2.03 24.60 46.06 4.00
33 LR-33 CH-13 5.0-6.0 23.31 1.37 28.80 43.99 2.40
34 LR-34 CH-13 8.0-9.0 22.76 2.97 28.40 44.21 1.20
35 LR-35 CH-14 6.0-7.0 21.34 2.32 30.80 42.66 1.50
36 LR-36 CH-15 6.0-7.0 21.73 2.43 32.50 42.68 1.30
37 LR-37 CH-16 4.0-5.0 23.78 2.00 29.14 41.95 2.12
38 LR-38 CH-16 8.0-9.0 23.95 2.62 24.82 45.48 1.88
39 LR-39 CH-17 3.0-4.0 21.83 2.93 29.68 42.27 1.93
40 LR-40 CH-17 7.0-8.0 25.93 2.16 19.00 50.16 2.18
-- Mean --- --- 21.97 1.97 30.71 42.58 2.03
The chemical analysis data of 21 samples collected from the seven pits are as
follows:
Page | 8
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Sl. Sample No From To LOI% SiO2% Fe2O3% Al2O3% TiO2%
No. In meters
17 LRP-6/2 2.96 4.00 25.99 2.69 18.33 50.29 1.70
18 LRP-6/3 4.00 5.00 23.02 0.58 30.20 43.77 1.30
19 LRP-7/1 0.28 2.60 17.15 18.85 30.67 31.62 1.32
20 LRP-7/2 2.60 4.60 21.23 2.81 31.11 41.81 2.43
21 LRP-7/3 4.60 6.00 26.12 2.88 19.48 49.21 1.48
--- Average --- --- 21.66 7.60 26.80 41.35 1.66
Mean grade of pits samples obtained by using the formula i.e. Mean grade = Σ
weight percentage x thickness of analysis / Σ thickness of analysis is as follows:
Page | 9
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
MINEABLE RESERVE OF BAUXITE
Cross Length of Volume of Quantity of
Category Section Sectional influence Bauxite Bauxite
Considered area (@2 t/m3)
(m2) (m) (m3) (t)
AB 1900 132 250800 501600
CD 2300 212 487600 975200
EF 1175 370 434750 869500
GH 1410 376 530160 1060320
IJ 2390 258 616620 1233240
KL 230 330 75900 151800
Proved MN 320 328 104960 209920
OP 270 338 91260 182520
QR 260 442 114920 229840
ST 345 260 89700 179400
UV 600 212 127200 254400
WX 225 252 56700 113400
YZ 170 240 40800 81600
Total --- --- --- 3,021,370 6,042,740
2 (iii) Need for the project and its importance to the country and
or region.
Bauxite mined @300,000 tonne/annum from the applied lease area will be
utilized for captive purpose by the applicant in their smelter plant at Hindalco in
district Sambalpur, Orissa after refining the bauxite in to alumina in their plant at
Renukot, Muri and Belgaum.
In addition to these, aluminium is one of the most important and widely used
metals in the transport, construction, packaging and electrical sectors. In
transport sector aluminium is used in cars (engine blocks, cylinder heads,
transmission housings and body panels), trucks and buses (sheet and plate for
bodies), in railway stock and in aircraft. In the construction sector aluminium is
used in sheet products for roofing and wall cladding, in extrusions for windows
and doors and in castings for builders’ hardware. In the packaging sector
aluminium is used in the form of alloy sheet for beverage can bodies and tops,
as foil for household and commercial wrap, in manufactured packaging products
Page | 10
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
such as cartons for fruit juice and packaging for pharmaceuticals. In the
electrical sector aluminium is used in the form of wire, normally reinforced with
steel to form cables.
2 (iv) Demand-Supply Gap
Mineable reserve of bauxite is estimated to be 6,042,740 t. Therefore, life of the
mine will be approximately 20 years @ 300,000 t/annum.
2 (v) Imports vs. Indigenous production
It is a mining project where bauxite will be produced for the refinery plants.
2 (vi) Export Possibility
There is no export possibility since bauxite mined out from the applied lease area
will be exclusively used in the refinery and then in smelter plant.
2 (vii) Domestic / export Markets
Average grade of Bauxite in Lakharshi Mine is 44.31% Al2O3 which will be mined
out@300,000 t/annum from the applied lease area for captive purpose by the
applicant in their smelter plant at Hindalco in district Sambalpur, Orissa after
refining the bauxite in to alumina in their refinery plant at Renukot, Muri and
Belgaum. There is no question of exporting the bauxite as per the terms &
conditions of State Govt. issued to the Applicant.
2 (viii) Employment Generation (Direct and Indirect) due to the
project
Due to mine activities in the M.L area, there will be approximate engagement of
60 persons in the mining & other auxiliary activities which are incidental to
mining operation, who may be employed directly or indirectly. This includes
management, technical, supervisory, other highly-skilled & skilled category, some
more persons may be associated with this project to carry out some other
developmental jobs as per need-base from time to time. Ancillary income such as
shopping, supply of food items, tailoring, hoteling etc. are extra.
Page | 11
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
3. PROJECT DESCRIPTION
This is a mining project. Bauxite mined out from the project will be transporting
to the refinery plants at Renukoot, Muri and Belgaum for alumina which will be
sent to smelter plant at Hirakud in district Sambalpur, Orissa for alumina.
The applied Lakharshi M.L area over 237.632 hectares decided for grant by the
State Govt. is located in villages Lakharshi, Rogapadar, Chiliguda, Kangatumba,
Bhandapai, Kalagaon, Lalingpadar in Tehsil/ PS: Kashipur of Rayagada district,
Orissa forms a part of the Survey of India toposheet No.65M/3 and is bounded
by the latitudes 190 24’ 39.568” to 190 25’ 57.08” N and longitudes 830 07’
38.636” to 830 09’ 07.605” E. The plateau of applied M.L. area partly belongs to
East Coast bauxite deposits which reservoirs about 56% of the total bauxite
resource in the country.
The details of the land use pattern is given in Section - 4(ii). There is no
environmentally fragile area such as sanctuary or biosphere reserve with the 10
Page | 12
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
km radius of the applied area. Extent, engaged or rare species are not found in
the applied area.
Rate of Production
Height and width of the benches will be kept at 3m & 6m respectively. In case
the ore-body elongates to some more depth the height may increases by 1 or 2
mtrs & it is maximum up to 6 mtrs height. The individual bench faces will be kept
nearly vertical (750 - 85°) whereas the overall quarry slope angle (the angle
between the line joining the toe of bottom bench and the crest of the top bench
with the horizontal) is proposed to be maintained at less than 45° with the
horizontal.
To keep the ultimate pit slope safe & stable and to mine out the optimum
amount of bauxite from the quarries, height & width of the benches will be kept
at 3m each at the time of abandonment. The aforesaid benching will form
ultimate pit slope angle at around 450 with the horizontal.
Page | 13
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Ultimate extent of the quarries will be confined to the area of 106.0 hectares up
to 6m depth from surface level.
The major factors like topography, estimated reserve & grade, thickness and
nature of overburden as well as bauxite, capital available and production target
have become the basis to adopt opencast trench mining method on one shift
basis with the deployment of earth moving machineries like ripper dozer, blast
hole drill, toothed double roll crusher (150 TPH) and screen. In addition to these,
it is proposed to carryout concurrent reclamation to comply with the
environmental and legal constraints.
Page | 14
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Mining unit operations likely to be carried out for development and
productions are
Removal of 2.7m thick sub-soil (overburden between 0.3m thick top soil
and bauxite strata) zone and dumping by shovel & tippers.
Drilling & blasting of the strata which can not be dislodged by the ripper
dozer
Transporting of the R.O.M. bauxite from mine to crusher site by the use of
20 tonne capacity tippers.
Page | 15
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Top Soil
Transport
Railway Siding
(Tikiri)
Page | 16
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
This is mining project, so raw material is not required. Here the bauxite
produced from the mine is the raw material, which will be used for the
production of Alumina by refinery plants.
Page | 17
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Drinking water source in the region are the tube wells and dug wells. For
the mine employed people, drinking water will be made available by
putting a Tube well in the lease area. Some of the perennial water sources
are available nearby to the lease area, which will meet the requirement of
the mines up to certain extent. 20 KLD water will be required for domestic
and non-domestic use in the mine. There is no possibility of puncture of
ground water table during the life of the mine since the mine working will
be confined to only 6m depth from surface level.
Electricity will be made available for office & quarters in the M.L. area in
directly by installing the DG or some other energy generator. There is no
proposal to use electricity for mining / mechanization or mineral
processing. To support the activities illumination within the lease area
shall be met by installing 50 KVA DG-set.
Rate of generation
An area of 106.0 hectares will be under mining during the life of the mine.
Page | 18
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Selection of dumping site mostly depends upon the factors like topography,
drainage, land use, mineral inventory, pit configuration, mine waste
characteristics, its volume of generation and economy in transportation. Keeping
in view the above physical as well as techno-economic factors, the
overburden/waste generated from the opencast mine will be in the bauxite zone
during initial two (2) years on the relatively flat plateau top near the opening
within the ultimate pit limit temporarily for ease and economy in back filing
instead of dumping on the plateau slopes degrading the additional non-forest
barren land outside the ultimate pit limit.
Page | 19
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Waste dump will be terraced and overall slope will be maintained at 270
with the horizontal. Retaining wall will be constructed around the dump
toe to arrest the wash-off material during rain. Garland drain shall be
developed around the lower slopes of the waste dump. Settling tanks will
be constructed at the corner of the garland drain and de-silted at regular
intervals.
Backfilling
It is proposed to back-fill the mined out area from one end of the opening
in the direction of progress of mining to restore the possible extent of
mined out area (as per the availability of waste) to a shape nearer to the
original topography. The void which will remain as such due to lack of
waste at the end of mining will be rehabilitated by way of soil conditioning
and plantation as well as water reservoir. Thus, the back filling in plan
period will be commenced con-currently from 2nd year of date of opening
of the mine and onwards as per the given table.
Page | 20
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Management of Dump
Waste of 90,018 m3 generated from the mine in 1st year will be dumped
temporarily. There will be automatic compaction of waste materials due to
the movement of loaded trucks.
The back filling in plan period will be commenced concurrently from 2nd
year of date of opening of the mine and onwards.
Retaining wall will be constructed around the waste dump at the eastern
side to check the wash-offs of the waste dump. In addition to these, a
garland drain with settling tank is proposed to be developed to the east of
check dam to receive effluent water of the waste dump, to settle down
the washed out solids and to release clean water to the natural drainage
system.
Page | 21
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Mining
Transportation
Inside Project
Area
Crusher
Transportation
Outside Project
Railway Siding Area
Dispatch Point
Page | 22
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
4. SITE ANALYSIS
4 (i) Connectivity
Applied Lakharshi M.L area over 237.632 hectares is accessible from Rayagada,
the district Head Quarter covering a distance of 75 km via Kashipur by an all
weather proof road. The nearest Rail head is at Tikiri at a distance of 35 km from
the village Lakharshi. A railway siding is also on the process of development by
Railway at Tikiri for transportation of road materials. The nearest airport
Visakhapatanam is at a distance of 280 km from this place.
The surface of the plateau is almost flat and has very gentle slope. One saucer
shaped depression is marked on the central part of the plateau, which is filled by
thick humus and clay. The southern margin of the plateau exhibit scarp faces.
Out of 237.632 hectares applied area, 120.06 hectares is non forest area &
117.572 Ha is DLC forest land.
Page | 23
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
The area under study forms a part of the Eastern Ghat hill ranges. The top
surface of the plateau is flat to gentle slope in nature. The average elevation of
the plateau is more than 1000m above MSL. One saucer shaped depression is
marked at the central part of the plateau, which is filled by thick humus and clay.
The southern margin of the plateau exhibit scarp faces of about 12m heights.
Most part of the plateau tops are covered by lateritic boulders. Highest and
lowest altitudes are noted at 1055m and 825m above mean sea level
respectively. The maximum altitude difference is noted to be 230m. 15 km radius
topographical map is presented in Figure No. 1 (Page No. 26).
Total 237.632
Page | 24
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Reserve Forest
Dhanda R.F Adjacent, E
Kalanga R.F 0.562Km, E
Rastugurha R.F 3.164Km, SE
Kalibhata R.F 4.007Km, NW
Mandibishi R.F 3.304Km, ESE
Sunger R.F 5.273Km, NW
Ranikota R.F 5.343Km, SE
Kandabindha R.F 6.186Km, SW
Bijaynagar R.F 6.327Km, ENE
Ladakhman R.F 8.155Km, NW
Bhasangamali R.F 6.116Km, SSE
Bartibali R.F 9.491Km, ESE
Durpai R.F. 11.810Km, E
Mohangiri R.F. 9.350Km, NE
Melaghara R.F. 8.366Km, NNE
Porhabandh R.F 11.107Km, SSW
Ajaynagar R.F. 10.334Km, ENE
Amapada R.F. 11.740Km, N
Renga R.F. 11.951Km, S
Leliguma R.F. 12.303Km, S
Utanga R.F. 12.724Km, SE
Alanda R.F. 14.412Km, E
There is no national park, wild life sanctuary, eco-sensitive areas water bodies,
CRZ etc. within 15 km radius of the applied lease area. This area does not fall
within notified industrial area.
Page | 25
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Page | 26
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
The lease area can be approached from Rayagada (the district Head Quarter)
through 75 km long well maintained road via Kashipur. Important towns like
Bhubaneswar, State Capital (400 km) in Orissa and Visakhapatna in Andhra
Predesh and potential AirPort (240 km) are well connected. Nearest Rail Head is
at Tikiri (35 km).
Drinking water will be made available by putting a deep tube-well in the M.L.
area. Water for industrial use will be obtained from the nearby perennial sources.
The country rock constituting the parent rock for bauxite comprises “Khondalitic”
suite of rocks belonging to the Eastern Ghat Group. The latter consists of highly
deformed, high grade metamorphic rocks of Precambrian age. The “Khondalitic”
suite represents a migmatised meta-sedimentary formation having been
felspathised to different degrees to yield rocks of wide range of variability in
composition. A purely quartz-sillimanite schist grades through quartz-felspathic
gneiss, porphyroblastic gneiss etc to granite gneiss and (or) granitoid bodies.
The suite, on the whole, is garnetiferous. The felspar present is mainly albite.
Plateau top is covered with thin humus of 30 cm thickness. This adjoining slopes
and valleys are covered by the screw and alluvium respectively. However, soil
samples will be collected and analyzed from various points as per Terms of
Reference (TOR) once it is issued by the Ministry of Environment & Forest
(MoEF), Govt. of India.
Page | 27
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
The annual mean maximum temperature in the region varies from 24.3 0C
(December) to 34.2 0C (May) while annual mean minimum temperature
varied from 10.8 0C (December & January) to 22.0 0C (May).
Relative Humidity
The annual relative humidity at 8.30 hours varies from 59% (March) to 87%
(July & August) while at 17.30 hours annual relative humidity varied from
40% (March) to 84% (July & August).
Rainfall
The annual mean rainfall observed was 1550.8 mm. About 77.65% of total
rainfall was observed during the months of June to September.
Wind Direction
Page | 28
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Page | 29
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
5. PLANNING BRIEF
A 7.5 m wide peripheral barrier is proposed to be left on the edge of the plateau
for the purpose of equipment safety, avoiding discharge of the silts into the
valleys directly, and hiding the mining activities from the surrounding adjacent
areas.
There is a proposal to start production and exhaust bauxite from one side of the
deposit. A concrete proposal is incorporated in the mining plan for reclamation
of mined area from 3rd year onwards.
Page | 30
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Total = Management & supervisory (10) + Skilled (24) + Semi Skilled (18) + un-
skilled (8) = 60.
5.(iii) Land use planning (breakup along with green belt etc).
21.834 Ha land at the end of plan period and 106.00 ha at the end of life
of mine will be utilized for excavation. At the end of mining plan period of
first 5 years, 33.823 ha land will be utilized for mining, dumping,
processing etc. But at the end of life of mine, 116.6 ha will be utilized for
mining and allied activities. The detail of land utilization pattern is given
below.
Page | 31
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Sl. Type of land use As at the end of As at the end of
No plan period life of mine (ha)
. (ha)
Total 237.632 237.632
Surface Plan, Conceptual Plan & Env Management Plan are given in
Figure No. 2, 3 & 4 respectively.
Page | 32
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
CH/16 F/2
1000
CH/14 F/1
800 N
G/2 F
0
800 N P/1 95
LR
45
0
10
90
40 0
1010350
3
10 5 85 600 N
H 2
10 20
10 15
10 10 5
10 0
D
1 0 00
600 N CH/13 1095
9 0
D/1 D/2
99 5
98 0
98 5
97 0
D/3 E
97 5
96 0
96 5
95 0
95 5
9440
9935
0
93 5
92 0 C/1 400 N
92 5
91 600 E 800 E
200 E 400 E
400 N
H/1 CH/1
5
104 LR
P/2 C
200 N
200 N
CH/15
B/1 A
00
H/2 P/7
00 LR
A/1 CH/4
CH/2
P/6
LR
200 S
200 S
1045
/3 B
L RP CH/10 1040
H/3 CH/5
CH/6
CH/3
M
40
1050
10
30 400 S
10 20
400 S /5
RP
10
10
CH/11 L 10
10
00
0
99
0
98 0
97 0
96 0
L/4
CH/7 95
94
0
P/4
0
0
93
90
LR
0
92
1055 91
0
L/3
CH/8 600 S
600 S
H/4 1050
L/2
1040
CH/9 1030
1020
1010
1000
990
L/1
980
5
104
970 800 S
960 00
800 S 950 800 W 600 W 400 W 200 W
940
930
K L
H/5
J
1000 S 1000 S
1000 W
I/1
1200 S
1200 S
I 1600 W
1400 W 1200 W
SURFACE PLAN
INDEX
MODIFICATION OF APPROVED MINING PLAN
M . L . AREA PROPOSED LAKHARSHI BAUXITE MINE
DLC FOREST
234 CONTOUR
NON-FOREST HILLY AREA
NALA AGRICULTURAL FIELD M/s. HINDALCO INDUSTRIES LTD.
TRIAL PITS
Page | 33
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
K A15 1000 N
G/1 F/3
A19
1000 N M
O
A 3rd 5YEARS F/2 A14
4th 5YEARS
D Q F/1
A13
L A7
N A8
G/2 N A12 800 N
A20 F
800 N A9 A10 A11
P R
35
10 30
S 10 25
H 10 20
10 15 A5 600 N
10 10
10 05 D A6
A21 10
00 D/1
10 5
600 N C
99 0
99 5 D/2
98 0
98 5 D/3 E
97 0
97 5
96
0
96 5
95 0
95 5
94 0
94 5
93 0 A4
93
5 C/1
92
0
92 5 400 N
91
200 E 400 E 600 E 800 E
400 N
H/1 F
A22
C
A3
200 N
200 N A2
A1
E S1
H/2 A
00
00 B/1
H U
A/1
200 S
INDEX
S B13
B B12
200 S M . L . AREA
B11
RS
H/3
B14 4th 5YEA 234
CONTOUR
1st 5YEARS V
G 2nd 5YEARS J
B15 NALA
T
M
30
10 20 B9 400 S DLC FOREST
10
B16 10
10
400 S BACKFILLING & PLANTATION B17 10
00
0 NON-FOREST HILLY AREA
99
0
98 0
L/4
B18 97 0
96 0
B8
95
0
94
0
0
93
90
0
92
0
91
S2 B19 L/3
600 S
B20 B7 200 W 00
600 S
H/4 L/2
1040
B211030
1020
Y I
1010
B22 1000 L/1
990 B6
CONCEPTUAL PLAN
980
B23 970
Z
960 800 S
400 W
ULTIMATE LANDUSE PARTEEN
800 S 950
800 W 600 W
940
B24 930
K
B4
L B5 ULTIMATE PIT LIMIT MODIFICATION OF APPROVED MINING PLAN
B25
H/5
PERIPHERAL BARRIER
PROPOSED LAKHARSHI BAUXITE MINE
J RECLAMATION OF MINED OUT AREA
W B3 (Backfilling & plantation)
1000 S
1000 S X 1000 W REHABILITATION OF MINED OUT AREA M/s. HINDALCO INDUSTRIES LTD.
( plantation)
B27 5 YEARLY LIMIT
B2 SAFETY ZONE
I/1
B1 PERIPHERAL ROAD WITH WATCH TOWER
1200 S 1200 S
I 1400 W 1200 W
1600 W
Page | 34
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
A16
F/4
A15 1000 N
G/1 F/3
A19
1000 N
F/2
A14
F/1
A13
A7
N A8
G/2 A12 800 N
A20 F
45
10
40
10 35
10 30
S 10 25
H 10 20
A5 600 N
10 15
10 10 D
A21 10 05
10
A6 D/1
00
10 5
600 N 99 0
99 5 D/2
98 0 E
98 5 D/3
97 0
97 5
96 0
96 5
95 0
95 5
94 0
94 5
93 0 A4
93
5 C/1
92
92 5
0 400 N
91 600 E 800 E
200 E 400 E
H/1
A22 RS
C
A3
200 N
200 N
A2
A1
S1
PRO
POS
BS A
H/2
00
ED
BACKFILLING
B/1
QU
00
ARR
Y
A/1
EX
PL
CO
M
200 S
ENVIRONMENTAL PROTECTION MEASURES
B13 E
B12 IC
200 S
B
FF MONITORING POLLUTION CONTROL SAFETY MEASURES
O
B11
1040 REST SHED
H/3 3rd YEAR
B14 AIR MONITORING STATION
BLASTING SHED
4th YEAR
B15 FIRST AID CENTER +
M
40
10 50
WATER SAMPLING STATION
10
30 5th YEAR
1 0 20 B9 400 S
10
10
400 S
B16 10
DUMP B17 10
00 RETAINING WALL
9 90
9 80 L/4
B18 9 70
9 60
B8 GARLAND DRAIN
NOISE / DUST FALL MONITORING
9 50
B19 9 40 STATION
9 00
9 30
TOPSOIL SETTLING TANK
9 20
1055
9 10
L/3
600 S
S2 200 W 00
600 S
B20 B7
10 50
H/4 L/2
10 40 400 W
B22 B21103020
10
10 10
10 00 L/1
PROPOSAL PLATE - VII
990 B6
ENVIRONMENT MANAGEMENT PLAN
980
970 PROPOSED QUARRY
10 45 B23 960 800 S
950 800 W 600 W
800 S WASTE DUMP
940
B24 930
K
B4
L
B5 INDEX TOPSOIL MODIFICATION OF APPROVED MINING PLAN
B25
H/5
BACKFILLING AREA
PROPOSED LAKHARSHI BAUXITE MINE
M . L . AREA
J
B3 OFFICE COMPLEX
234
CONTOUR
1000 S
1000 S 1000 W
NALA
ROM STOCK PILE M/s. HINDALCO INDUSTRIES LTD.
MAGAZINE
B27 CRUSHER SITE
DLC FOREST
B2 MAGAZINE
I/1 NON-FOREST HILLY AREA
B1 PERIPHERAL ROAD WITH WATCH TOWER
1200 S
1200 S
1400 W 1200 W
I 1600 W
Page | 35
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Tribal Issues : However, the infrastructure demand of the locality has been
assessed as follows :
5.(v) Amenities/Facilities.
Helmets, safety shoes, ear plugs, spectacles, globes, pads etc will be provides to
the labour to save their body parts while working. Rest shed will be provided to
take rest in lunch period. Vocational training will be provided to the labours by
trained executive to work safety in the mine & processing plant. First-aid as well
as medical facilities will be made available in the mine or to take care of the
health. In addition to these, following amenities / facilities will be provided to the
local communities:
Page | 36
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
6. PROPOSED INFRASTRUCTURE
There is a proposal to commission a 150 TPH capacity crushing unit for sizing of
run-off mine bauxite in to required sizes.
Office, rest shed-cum-fast-aid centre etc will be made available in the lease
area for day to day mine operation. Since the lease area is near the tahasil
town Kashipur, the infrastructural facilities in respect of road, market,
telephone, power etc. are well developed.
Electricity will be made available for office & quarters in the M.L. area. There is
no proposal to use electricity for mining / mechanization or mineral processing.
Accommodation or Housing
As far as experience is concerned, local people will work in the mine staying in
their own villages. Migrated people from distance will be accommodated at
Kashipur. Accommodation or housing will be provided to the essential workers
near the Q.L. area.
The rest shed will be provided near quarry site as per the mines rule, 56. Toilet,
Fast-Aid and lunch facilities will be attached with the rest-shed.
Magazine
Page | 37
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Blasting Shed
Portable steel blasting shed of one end open type will be provided at this mine
site for giving protection to the blasters during blasting. The blasting sheds will
be shifted depending upon the shifting of the blasting locations.
At the end of life of mine total lease area will be under plantation as mentioned
below:
Page | 38
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Health: - Mobile health units will be provided at the villages to transfer the
suffered/injured to the nearest PHC/CHC by the Applicant, M/s HINDALCO
Industries Limited and free medicine will be available to the patients. An MBBS
doctor with other paramedical staff will be provided along with the MHU during
the course of regular & specialized health camps by Applicant. MHU will be
provided by the Applicant for emergency on full time basis to serve all the
villages. Further need base heath care program will be organized independently
or in convergence with Govt/ NGO under the request of local people.
Entertainment: - Film show will be arranged fortnightly for the employees and
villages. Sport facilities will be provided for the outdoor games like football,
volleyball, hockey, cricket etc.
Financial help will be provided to decorate the place where the cultural program
/ festivals are enjoyed by the local people.
Others (water and light):- Financial add as well as awareness will be developed
in the region to consume wholesome drinking water. Area will be lighted in the
night through generator/ fixed power.
The lease area can be approached from Rayagada (the district Head Quarter)
through 75 km long well maintained road via Kashipur. Important towns like
Page | 39
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Drinking water will be made available by putting a deep tube-well in the M.L.
area. Water for industrial use will be obtained from the nearby perennial sources.
In a day about, 4 KLD of potable clean & wholesome drinking water will be
provided to the staff at the mine for drinking & domestic use. In addition to
these, 16 KLD of water will be utilized for non-domestic purpose which includes
use of water for mine operation (washing of machines etc), water spraying for
dust suppression / prevention and watering the plantation site for live & growth
of the saplings.
Lease area is consisting of plateau top and slopes. Sewerage system will be
developed at the hill top from the offices & other sheds which will be developed
for the needy persons (mostly security guards) who will reside on the plateau top
for essential services.
Page | 40
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
This is a mining project. Solid waste such as laterite, khondalite etc will be
generated during mine which will be back-filled in the mined out area since 3rd
year onwards. Plantation will be carried out on the back-filled area after
spreading of topsoil, bio-fertilizers/manures (ref : Para-6.0)
Quality
Types of wastes are laterite, clay, lateritised khondalite and free khondalite.
These are not toxic in nature.
Management
Retaining wall & garland drain will be developed around the waste dump to
arrest the washed off waste materials while there is rain.
Page | 41
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Year of Waste available Topsoil available Total Area to be
Modification from (m3) from (m3) (m3) backfilled
of Approved Quarry Dump Quarry Stack at 5m thick
(E=
Mining Plan (A) (B) (C) (D) filling (m2)
A+B+C+D)
(F=E/5)
3rd 121,500 45,018 13,500 5,002 185,020 37,004
4th 135,000 --- 15,000 --- 150,000 30,000
5th 135,000 --- 15,000 --- 150,000 30,000
Total 499,500 90,018 55,500 10,002 655,020 131,004
Electricity will be made available for office & quarters in the M.L. area thru’
50KVA DG or by any other means once activity starts at the hill top. There is no
proposal to use electricity for mining / mechanization or mineral processing
except the mine & road lighting.
Page | 42
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
There is no human settlement in the applied lease area which is entirely located
in Govt. land. Therefore, rehabilitated and resettlement proposal have ourselves
not required. Non-outlined un-irrigated privately owned land over 2.404 hectares
exists in the applied M.L area. Policy of the State Govt. will be adopted in respect
of their land once planned for use in mining & allied activities.
There is no forest in the applied M.L area. Most likely the date of construction of
site services and / or opening of the mine after the construction work may be six
(6) months or one year from the date of obtaining the surface right possession.
Approval of mining plan, Environmental Clearance, execution of mining lease
deed with State Govt. and surface right possession from the Collector will be a
job of approx. two (2) years.
Page | 43
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Estimates project cost is worked out to be Rs.19.2 crores and Production target
of bauxite is Rs.300,000 t/annum. Operating cost is worked to be Rs.800/tonne
while purchasing cost of bauxite is Rs.1200/tonne. Therefore, this project will be
economically viable for mining of bauxite for captive use in the Applicant’s
alumina and aluminum plants.
Page | 44
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
Due to mine activities in the M.L area, there will be approximate engagement of
60 persons in the mining & other auxiliary activities which are incidental to
mining operation, who may be employed directly or indirectly. In addition to
these 60 persons, who includes management, technical, supervisory, other
highly-skilled & skilled category, some more persons may be associated with this
project to carry out some other developmental jobs as per need-base from time
to time. Ancillary income such as shopping, supply of food items, tailoring,
hoteling etc. are extra. Medical, transport, communication facilities including the
Purchase facilities and cultural improvement will be developed. Moreover the
general awareness and lifestyle of the area people will be improved.
Page | 45
Lakharshi Bauxite Project Hindalco Industries Ltd
Rayagada, Orissa Mining Lessee
Pre-feasibility Report
ENCLOSURES
Page | 46
Enclosure - 1
Annexure-1.6
Enclosure- 2
Enclosure - 3