You are on page 1of 2

ABSTRACT OF QUANTITY

Name of work :- Estimate for foundation work for Tranformar at Back side of
Trivani guest house premises of THDCIL Colony Rishikesh
S.no. Description No. L. B. H. Total Unit

Earth work in excavation by mechanical means


(Hydraulic excavator) / manual means in
foundation trenches or drains (not exceeding
1.5 m in width or 10 sqm on plan), including
1 dressing of sides andramming of bottoms, lift up
to 1.5 m, including getting out the excavated soil
and disposal of surplus excavated soil as
directed, within a lead of 50 m All kinds of soil
For plinths No 1 1*1 1.74 1.74 0.45 1.36
For plinths No 2 1*1 1.74 1.74 0.45 1.36
For Partition Wall 1*1 4.35 0.3 0.4 0.52
Total 3.25 Cum
Providing and laying in position cement concrete
of specified grade excluding
the cost of centering and shuttering - All work up
to plinth level : 1:4:8 (1 Cement : 4 coarse sand
2 (zone-III) : 8 graded stone
aggregate 40 mm nominal size)
P.C.C For foundation of plinths No 1 1*1 1.74 1.74 0.10 0.30
P.C.C For foundation of plinths No 2 1*1 1.74 1.74 0.10 0.30
P.C.C for Wall 1*1 4.35 0.1 0.10 0.04
Total 0.65 Cum

Providing and laying up to floor five level


reinforced cement concrete in kerbs, steps and
the like excluding the cost of centering,
shuttering, finishing and reinforcement with
3 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) : 3
graded stone aggregate 20 mm nominal size).
For Raft foundationof plinths No 1 1*1 1.72 1.72 0.15 0.44
For Raft foundation of plinths No 2 1*1 1.72 1.72 0.15 0.44
For foundation Top of plinths No 1 1*1 1.72 1.72 0.20 0.59
For foundation Top of plinths No 2 1*1 1.72 1.72 0.20 0.59
Total 2.07 Cum
Providing and laying in position cement concrete
of specified grade excluding
the cost of centering and shuttering - All work up
to plinth level : 1:1½:3 (1 Cement: 1½ coarse
4
sand (zone-III) : 3 graded stone
aggregate 20 mm nominal size).
For plinths No 1 1*1 1.72 1.72 1.15 3.40
For plinths No 2 1*1 1.72 1.72 1.15 3.40
Total 6.80 Cum
Brick work with common burnt clay F.P.S. (non
modular) bricks of class designation 7.5 in
superstructure above plinth level up to floor V
level in all shapes and sizes in : 6.4.2 Cement
5 mortar 1:6 (1 cement : 6 coarse sand)
For plinths No 1 1*1 1.72 0.23 1 0.40
1*1 1.49 0.23 1 0.34
For plinths No 2 1*1 1.72 0.23 1 0.40
1*1 1.49 0.23 1 0.34
For Partition Wall 1*1 4.35 0.23 3.1 3.10
Total 4.58 Cum
1.5% of ITEM No 3
6
Twisted steel/deformed TMT bars Fe-500D 1*2 (2.07*1.50*78.50/100) 2.44 Quintal
12 mm cement plaster of mix :
1:4 (1 cement: 4 fine sand)
For plinths No 1 sides 1*4 1.72 1.02 7.02
For plinths No 2 sides 1*4 1.72 1.02 7.02
7 Plinth 1 plaster at Top 1*1 1.72 1.72 2.96
Plinth 2 plaster at Top 1*1 1.72 1.72 2.96
For Partition Wall face 1*2 4.35 2.8 24.36
Wall side 1*2 0.25 2.8 1.40
Wall Top 1*1 4.35 0.25 1.09
Total 46.80 Sqm

You might also like