Category/Group: Construction-CNS, Environmental-ENV, Contracting & Management-MGT, Structures & Geotech-STG, Utilities-UTL, Safety is included in all areas
Quality Impact
Environmental
Safety Impact
Stakeholder
Cost Impact
Mitigation Team Preventative
Risk Score
Probability
Sensitivity
Mitigation Efforts (General) Response Plan
Schedule
Leaders Actions
Impact
Impact
Impact
Prepare submittal schedule/log for monitoring/tracking. Identify critical
MGT-01 Timely/accurate submission of submittals (shop drawings/sublet requests). 2 1 4 1 1 1 1 8 Contractor
submittals. Include in CPM.
MGT-04 Delivery/procurement/ fabrication processes - appropriate timing. 3 1 3 1 1 1 1 9 Contractor Include in CPM, proactive communication
MGT-05
MGT-06
MGT-07
MGT-08
District __________________ Project ________________ Risk Workshop
Category/Group: Construction-CNS, Environmental-ENV, Contracting & Management-MGT, Structures & Geotech-STG, Utilities-UTL, Safety is included in all areas
Quality Impact
Environmental
Safety Impact
Stakeholder
Cost Impact
Mitigation Team Preventative
Risk Score
Probability
Sensitivity
Mitigation Efforts (General) Response Plan
Schedule
Leaders Actions
Impact
Impact
Impact
ENV-01 Installing and maintaining E&S controls 1 1 1 1 1 2 2 2 Contractor/VDOT C-107 for communication. Visual daily reviews.
ENV-02 Time of year restrictions - Bats - April 15 1 1 1 1 1 1 1 1 Contractor/VDOT Clear prior to April 15, 2016
MOT-02 School bus hours of work 5 2 2 2 1 1 3 15 Contractor/VDOT Re-occuring coordinationwith staeholders. Proactive notifications.
MOT-03
MOT-04
RW-01 Contractor right of entry 1 1 1 1 1 1 1 1 Contractor/VDOT Ensure contractor has rights of entry.
RW-02
District __________________ Project ________________ Risk Workshop
Category/Group: Construction-CNS, Environmental-ENV, Contracting & Management-MGT, Structures & Geotech-STG, Utilities-UTL, Safety is included in all areas
Quality Impact
Environmental
Safety Impact
Stakeholder
Cost Impact
Mitigation Team Preventative
Risk Score
Probability
Sensitivity
Mitigation Efforts (General) Response Plan
Schedule
Leaders Actions
Impact
Impact
Impact
Discuss at preconstruction meeting and establish time frames. VDOT
UTL-01 Encountering unknown offsite storm drainage or otherwise 4 1 2 1 1 1 5 20 VDOT/Contractor will call: staff at local Public Works, Expect input immediatetly to 24
hours.
Probability
Safety Impact
Schedule
Impact
Cost Impact
Quality Impact
Environmental
Impact
Stakeholder
Sensitivity
Impact
Risk Score
Leaders
Mitigation Team
Mitigation Efforts (General)
Actions
Preventative
Response Plan