Professional Documents
Culture Documents
Bachelor of Architecture
(2021-2022)
Submitted by
BISCUITWALA
KHUSHI
Guided by
Ar. Vishwanath K.R.
CABLE-NET:
ICE SKATING RINK (OLYMPIC PARK MUNICH) - 1983
ELEVATIONS
STRUCTURAL DETAILS
CABLE JOINERY DETAILS
GUIDED BY:
AR.VISHWANATH SHAH
CASESTUDY-
HOWARH BRIDGE,KOLKATA
LOCATION
KOLKATA, WEST BENGAL, INDIA
CONSTRUCTION COMPLETED
1943
ESTIMATED INVESTMENT -
RS.25Million.
THE HOWRAH BRIDGE IS
LOCATED BETWEEN THE TWIN
CITIES OF HOWRAH AND
KOLKATA IN WEST BENGAL,
INDIA.
CONSTRUCTION TECHNIQUE:
MATERIAL
THE HOWRAH BRIDGE DOES NOT HAVE NUTS AND BOLTS, BUT WAS FORMED BY
RIVETING THE WHOLE STRUCTURE. IT REQUIRED 26,500 TONS OF STEEL, OUT OF WHICH
23,000 TONS OF HIGH-TENSILE ALLOY STEEL, KNOWN AS TISCROM, WERE SUPPLIED BY
TATA STEEL.
THE MAIN TOWER WAS CONSTRUCTED WITH SINGLE MONOLITH CAISSONS OF
DIMENSIONS 55.31 X 24.8 M WITH 21 SHAFTS, EACH 6.25 M2. THE FABRICATION WAS DONE
BY BRAITHWAITE, BURN & JESSOP CONSTRUCTION COMPANY AT FOUR DIFFERENT
SHOPS IN KOLKATA.THE TWO ANCHORAGE CAISSONS WERE EACH 16.4 M BY 8.2 M, WITH
TWO WELLS 4.9 M SQUARE. THE CAISSONS WERE SO DESIGNED THAT THE WORKING
CHAMBERS WITHIN THE SHAFTS COULD BE TEMPORARILY ENCLOSED BY STEEL
DIAPHRAGMS TO ALLOW WORK UNDER COMPRESSED AIR IF REQUIRED. THE CAISSON
AT KOLKATA SIDE WAS SET AT 31.41 M AND THAT AT HOWRAH SIDE AT 26.53 M BELOW
GROUND LEVEL.
COST
THE ENTIRE PROJECT COST 25 MILLION (£2,463,887). THE PROJECT WAS A PIONEER IN
BRIDGE CONSTRUCTION, PARTICULARLY IN INDIA, BUT THE GOVERNMENT DID NOT
HAVE A FORMAL OPENING OF THE BRIDGE DUE TO FEARS OF ATTACKS BY JAPANESE
PLANES FIGHTING THE ALLIED POWERS. JAPAN HAD ATTACKED THE UNITED STATES AT
PEARL HARBOUR ON DECEMBER 7, 1941. THE FIRST VEHICLE TO USE THE BRIDGE WAS A
SOLITARY TRAM.
DESIGN
THE DESIGN OF THE SECOND HOOGHLY BRIDGE DIFFERS SLIGHTLY FROM OTHER
BRIDGES, WHICH ARE OF LIVE LOAD COMPOSITE CONSTRUCTION. THE DIFFERENCE IS IN
THE DEAD LOAD DESIGN CONCEPT ADOPTED FOR THIS BRIDGE AND CONCRETING OF
THE SIDE SPANS DONE WITH SUPPORT PROVIDED BY THE INTERMEDIATE TRESTLE. THE
DECK IS DESIGNED WITH A GRID STRUCTURE OF GIRDERS. ONE SET OF GIRDERS ARE AT
THE END AND ANOTHER SET IN THE MIDDLE, WHICH ARE BRACED BY GIRDERS SPACED
ON AN AVERAGE AT 4.2 METRES (14 FT) CENTRE TO CENTRE.
STRUCTURAL DETAILS OF HOWRAH BRIDGE:
• THE ORIGINAL CONCEPT WAS TO MAKE THE CENTRAL SUSPENDED SPAN AS HOG
• BACKED.
• THERE WAS NO STANDARD CODE AVAILABLE FOR THE DESIGN OF BRIDGES.
• HIGH-STRENGTH STEEL WAS SELECTED FOR REDUCING THE WEIGHT OF STEEL WORK.
WITH THE ADOPTION OF A CANTILEVER BRIDGE, UNHINDERED NAVIGATION
PROVISION WAS ATTAINED.
STRUCTURAL FEATURES:
• CENTRAL SPAN 1500 FT BETWEEN CENTRES OF MAIN TOWERS.
• ANCHOR ARM 325FT EACH
• CANTILEVER ARM 468FT EACH.
• SUSPENDED SPAN 564FT.
• MAIN TOWERS ARE 280FT HIGH ABOVE THE MONOLITHS AND 76 FT APART AT THE TOP.
• BRIDGE DECK WIDTH 71 FT WITH TWO FOOTPATHS OF 15 FT EITHER SIDE.
• ALL MEMBERS OF THE SUPER STRUCTURE COMPRISE BUILT UP RIVETED SECTIONS
WITH A COMBINATION OF HIGH TENSILE AND MILD STEEL.
• BETWEEN TOWERS BRIDGE DECK HANGS FROM PANEL POINTS IN THE LOWER
CHORD OF THE MAIN TRUSSES WITH A SERIES OF HUNGERS (39 PAIRS)
• ROAD WAY BEYOND THE TOWER IS SUPPORTED ON GROUND LEAVING ANCHOR ARM
FREE FROM DECK LOADS.
• BRIDGE DECK COMPRISES 71 FT CARRIAGE WAY AND 15 FT FOOTWAY PROJECTING
EITHER SIDE OF THE TRUSSES AND BRACED BY A LONGITUDINAL FASCIA GIRDER.
MORE ABOUT THE BRIDGE
• THE DECK SYSTEM CONSISTS OF CROSS GIRDERS HUNG BETWEEN PAIRS OF
HUNGERS WITH PINNED CONNECTION.
• SIX ROWS OF LONGITUDINAL STRINGER GIRDERS SPAN BETWEEN CROSS GIRDER.
• FLOOR JOISTS SUPPORTED TRANSVERSELY ON TOP OF STRINGERS.
• THEY SUPPORT A CONTINUOUS PRESSED STEEL TROUGHING SYSTEM.
• OVER WHICH DECK CONCRETE IS LAID OUT
DETAILS OF SUPERSTRUCTURE:
• THE LENGTH OF THE ANCHOR SPANS IS 99 M. THE TRUSS FORMATION FOR THE
CANTILEVER ARM AND ANCHORAGE ARM IS A K-TYPE, AND THAT FOR THE
SUSPENDED SPAN IS AN. ADOPTION OF A K-TYPE TRUSS HELPED IN THE REDUCTION
OF THE SLENDERNESS EFFECT OF THE LARGE VERTICAL LOADS.
PIER FOUNDATION
• THE ANALYSIS SHOWED THAT THE MAXIMUM LOAD THAT MAY COME ON THE
FOUNDATION FROM THE SUPERSTRUCTURE IS 30,000 TONS DOWNWARD
COMPRESSION AT THE MAIN PIER LOCATIONS AND 13,500 TONS UPWARD TENSION
AT THE ANCHORAGE POINTS. THE TWO PIERS AND TWO ANCHORAGES AT EACH
END WILL TAKE HALF OF THE ABOVE LOAD EACH.
ANALYSIS
TENSION
COMPRESSION
TENSION
COMPRESSION
N truss
TENSION
COMPRESSION
DECK GRILLAGE SYSTEM EXPANSION JOINT
THANK YOU....
Subject – BMCT-V
Bachelor of Architecture
(2021-2022)
Submitted by
Jadav Saloni. R.
Batch – I, Roll no.-19
Guided by
Ar. Vishwanath K.R.
Introduction:
What IsTensile Structure?
Tension roofs or canopies are those in which every part of the structure
is loaded only in tension, with no requirement to resist compression or bending
forces.
• Area: 9000 m²
• Year: 2010
• Client:United Nations
• City:New York
• Country:United States
Architectural Design Criteria :
These symmetrical curved parallel arch designs form an incredibly functional tensioned membrane
canopy that can span long distances such as a sports arena or smaller areas such as an entryway.
Depending on the spans, a barrel vault system can be a very cost-effective way to incorporate tensile
membrane on a project due to the repetitive nature of the design and efficiencies of materials.
Stayed Structure.
PLAN SHOWING MINIMAL ANCHORAGE POINTS
The Porte Cochere may be relocated to another location on the UN campus or to any other site of
the UN’s choosing. With this as a starting point, the design developed to have minimal anchorage
points and to be modular in nature, using prefabricated steel trusses allowing for quick installation
whic h minimizes the impa ct of construction crews on site.
TYPE FABRIC OF STRUCTURE :
The structure uses two fabrics, a Teflon coated glass fabric as the main fabric and a silicone coated
glass fabric for greater translucency in the arches.
Functionally the canopy provides shelter for the motorcades as they load and unload delegates,
requiring ventilation for the idling cars inside. The open facades and linear vents that run the
entire length of the trusses allow fresh air to flow freely throughout the enclosure.
ROOF PLAN OF PORTE COCHERE, UN.
JOINERY DETAILS OF United Nations Porte Cochere :
TRUSS ASSEMBLY
3-D TENSILE STRUCTURE
JOINERY DETAILS OF United Nations Porte Cochere :
DIAGRAM OF OPRABLE
CURTAINS
STRUCTURAL PLACEMENTS OF INTERMEDIATE MEMBERS :
VIEWS OF PORTE COCHERE, UN.
BACHELOR OF ARCHITECTURE
B.ARCH-III SEM-V
(2021-22)
SUBJECT: BMCT
CASESTUDY OF
MUNICH OLYMPIC STADIUM, GERMANY
SUBMITTED BY:
Jagtap Priyanka-20(Batch-1)
GUIDED BY:
Ar. Vishwanath KR
MUNICH OLYMPIC STADIUM, GERMANY
INTRODUCTION
The Munich Olympic stadium is located in Munich, Germany, which is designed and built to host the
Olympic Games in Munich 1972. The architects in charge, Frei Otto and Gunther Behnisch both won the
design competition for the 1972 Olympic Games by proposing an undulating. continuous translucent
roof covering almost 80000 square metres of the landscape.
Designing a structure emulating the motto of the games: "The Happy Games" was their aim. Otto and
Behnisch created a structure mimicking the elevation of the Swiss Alps with a continuous translucent
roof which is suspended looking like the clouds covering all over the spaces between the main stadium,
pools and gym.
The stadium consist of four separate sub-areas (Olympic Games. Olympic Village. Press Room Olympic
City and the Olympic Park), Telecommunications tower and a stadium.
Architect : Frei Otto and Gunther Behnisch
Location : Munich, Germany
Years of Construction : 1968 - 1972
Collaborators : Otl Aicher
Client : Olympia-Baugesellschaft mbh
Stadium type : Public
Type of enclosure : Fully enclosed structure
Climatic zone : Temperate - cold winters and
mild summer
Volume : 427,300 m3
Swimming Pool volume : 222,000 m3
Total Roof Area : 74,800 m2
Capacity : 69,250 visitors,57,450 seats and
11,800 standing places, 100
places for disabled Persons
Dimensions : 260 m length axis and 250 m
diagonal axis
Field : 105 x 68 m
Internal area : Automatic irrigation system and
field heating, 400 m round track
with 8 tracks, long jump and
triple jump complex, high jump,
pole vault, discus, hammer and
javelin throw, shotput.
Lighting system : 1875 LUX
Cable Net & Membrane Structure
For long-span tensile membrane roofing applications typically found in
stadiums or large spaces, 3D cable net or cable grid structures are an
efficient solution for lightweight tensile architecture
SURFACE CONSTRUCTION
CANOPY TENSILE STRUCTURE (ROOF)
2. Outstanding Translucency
In daylight, the membrane's translucency offers soft diffused naturally
lit spaces reducing interior lighting costs. At night, the artificial
lighting creates an ambient exterior luminescence.
4.Cost Benefits
Lightweight structures can be a more cost effective solution than
traditional building materials offering building owners reduced costs.
Materials, such as photo-catalytic membranes, can help prevent
temperature rise as well as reduce maintenance costs due to their
self-cleaning properties.
6. Earthquake Resistant
Lightweight tensile membrane structures bear less building load than
traditional roofing materials and the membrane's elasticity offers
further earthquake resistance.
SKELETAL CONSTRUCTION
STEEL MASTS
The masts support the main cables maintained in tension by providing the necessary hanging roof
surfaces support. The masts are responsible structural elements transmit loads to the strong hand.
and do so in an inclined manner. The junction between the various cables that make up the structural mesh
is materialized by a knot of steel casting with a system using bolted anchors and tensioned. Earth anchor
foundations were needed to support the masts.
TENSILE STRUCTURE
DESIGN PROCESS Design of supporting framework:
• fabric
• arches
• Masts
• Anchorages
• cables
• weldments
Masts were erected and Fabric was sewn to the Main coble was
drilled into the base main cable and supporting attached
with cables(fahing wire) was to the base and
screws as cable joints added to the edges of the secondary cables tied to
Because of the precision in the calculations of the structural system and the
fabric the masts and the base
membrane, these elements were manufactured off-site construction. The
high precision allowed easy assembly for one the most innovative and
complex structural systems that have been worked only with the premise
of stress.
GRAVITATIONAL LOAD
LATERAL LOAD
MATERIALS
CABLES EDGE STRAPS TENDONS KNOTS AND CAST ACRYLIC MASTS STEEL
LACES CLOSED PARALLEL CORDS STEEL CLAMPS (PLEXIGLAS) TUBES
COVER GLASS
Bachelor of Architecture
(2021-2022)
Submitted by
MAHARAJWALA
TWINKLE
Guided by
Ar. Vishwanath K.R.
MILLENIUM DOME,
GREENWICH
INTRODUCTION
•Architect-Richard Rogers
•Structural Engineer-Buro Happold
Period of construction-1996-2000
Project cost-758 million pounds
Building Category-Exhibition and assembly
LAYOUT
Diameter-320 meters
Central height-48 m
Enclosed area-80,000 sqm (20 acres)
Capacity-40,000 ppl
ELEMENTS USED :
UPPER
HANGER
CABLE RING
CIRCUMFERENTIAL
CACLE LOWER TIE
DOWN
CATENARY CABLE STRINGERS
DETAILING OF MASTS
•Flame resistant
•Unaffected by UV light
•Water proof and dirt resistant
SUBMITED BY:-
baldaniya sagar n. [05]
BATCH - s01
TOPIC:-
tensile stucture
SUBMITED TO:-
AR. VISHWANATH
DENVER UNION STATION
INFORMATION
Architect: Skidmore, Owings & Merrill
Stucture: Long span tensile structure
Function / usaage: Central transportation hub
Material: Steel and PTEE fabric canopy
Project Timeline: 2010-2014 (rebuilt)
Location: Denver Colorado U.S.A
DESCRIPTION
The primary structural system consists of 11 steel 'arch trusses' spanning
nearly 55 meters from a single large-diameter pin connection atop 5.5 meter
tall arched column supports.
Each truss is supported about 6 meter above the ground by a series of steel
'kick stands,' which support vertical loads and horizontal thrust.
Each 'kick stand' is rigidly connected to the foundation with heavy anchor bolts.
The arch-trusses and cantilevered trusses support a tensioned ptfe fabric.
DENVER UNION STATION
Roof details:
The structural system resist large uplifting wind forces because of void in
tensile mass fabric ,and foundation is design to take care of possible uplifting
Opening the canopy towards sky also provides view of the denver historic
station
Fiber membranes with a high degree of strength, together with layers of
waterproof coatings, giving protection against ultraviolet rays, fungus, fire, and
allowing greater or less translucency and reflectivity.
DENVER UNION STATION
STRUCTURE SPECIFICATION
Length: 159 meters
Breadth: 55 meters
Area: 8,745 sq.m
Height: 21 meter at the head–
end platform and 6.7
meter at the center
Weight: 720 tons
DENVER UNION STATION
PHOTOS
DENVER UNION STATION
REFRENCES
SOM | Denver Union Station – Structural Engineering
Denver Union Station // Skidmore, Owings & Merrill (SOM) - Architizer Journal
Denver Union Station / SOM | ArchDaily
Denver union station , case study by A JAY KUSHWAHA_ PILLAI HOC COA - issuu
DENVER INTERNATIONAL AIRPORT- TENSILE STRUCTURE
RUSHALI GURNANI-16
BUILDING MATERIALS AND CONSTRUCTION TECHNOLOGY -V
INTRODUCTION :
• THE MASSIVE 1200X240 FOOT FACILITY FEATURES STRIKING “MOUNTAIN RANGE CANOPY” THAT
UTILIZES BIRDAIR’S INNOVATIVE STEEL CABLE SYSTEMS AND DURABLE PTFE TEFLON-COATED
FABRIC MEMBRANE.
• THE MEMBRANE IS STRETCHED BETWEEN 34 MASTS (105 TO 125 FEET IN HEIGHT) LINED UP 60
FEET ON-CENTER AND PLACED IN TWO ROWS 150 FEET APART.
• THE MASTS ARE ANCHORED TO THE FRAMING OF ROOF SURFACES ALONG THE EAST AND WEST
SIDES OF THE TERMINAL.
• STEEL CABLE 7x7: STEEL CABLE CARRY HIGH FLEXIBILITY AND CORROSION RESISTANT. IT
IS GREAT FOR TENSIONING AND HAS HIGH DURABILITY. IT HAS LONG LIFE SPAN AS WELL AS
ABRASION RESISTANCE.
- IN ORDER TO COMBAT FLUTTER OF THE ROOF DUE TO THE DYNAMIC EFFECT OF THE
WIND, DOUBLE CABLE SYSTEM IS INTEGRATED.
- THE CELESTORY WINDOWS ALONG THE EAST AND WEST OF THE WALLS OF THE FREAT HALL ARE
FRAMED BY CABLE-SUPPORTED STRUCTURES.
• Along with the building, Foster's studio designed the majority of fixtures for Renault including the warehouse
storage units and a range of office furniture.
• Glass-topped tables, which were developed for the studio's own offices, were modified for the distribution
facility's offices, restaurant and reception. The tables were developed by Italian furniture manufacturer Tecno
and placed on sale in 1986 – they are still in production.
• This expansive horizontal span is
combined with an internal clear height
of 7.5 metres, allowing the Centre to
accommodate a range of uses from
industrial warehouse racking to its
subdivision into office floors.
• Enveloped by a continuous PVC
membrane roof, pierced by glass
panels at each mast, allowing ample
natural light and ventilation, the
building is also stepped at one end,
narrowing to a single, open bay that
forms a porch alongside a double-
height gallery.
STRUCTURAL DETAILS
Subject – BMCT-V
Bachelor of Architecture
(2021-2022)
Submitted by
MANANI ABHAY
Guided by
Ar. Vishwanath K.R.
ASHFORD DESIGNER RETAIL OUTLET
• Architect • Structural Engineer
Roger Strik Harbour + Partners Buro Happold
ABHAY MANANI - 36
OVERVIEW
The distinctive tent structure is
festive in spirit, unites the centre and
announces itself proudly within the
30-acre site. It is undulating in form,
rising to high points whose vertical
masts act as counterpoints to the
horizontal nature of the
development and local topology. It
wraps around the edge of the leaf-
shaped plan and joins the northern
end of the site.
ABHAY MANANI - 36
DESIGN
• The defining element of the design is
the light-weight tensile fabric roof,
supported from 22 bright orange steel
masts and attached to the ground by
tension cables attached to circular
concrete pads anchors.
ABHAY MANANI - 36
DESIGN
• The roof, the longest continuous tent structure in the world and covering
an area of 30 square kilometres, shelters the ring of single storey units
below. The units themselves, glazed on the inner face and clad in solid blue
panels to the rear, are highly flexible insulated ‘boxes’. Each unit is air-
conditioned with bright yellow external air handling units located on the
rear of the units.
ABHAY MANANI - 36
CONSTRUCTION METHODOLOGY
• The roof is the longest continuous
tent form in the world and required
detailed study to establish how it
was to be built in relation to other
trades involved in the project, as
well as ensuring its temporary
structural stability for the duration FABRIC ROOF
of the construction programme.
ABHAY MANANI - 36
CONSTRUCTION METHODOLOGY
• The site remediation strategy formed an important element of the construction programme, and provided a significant challenge for the contractor in
terms of soil grading, washing and batching prior to the construction of the continuous landscaped berm. To avoid the cost and environmental impact of
removing large quantities of material from the site, significant amounts of soil were re-used. Repetitive cladding details and modular design of the
environmental systems also significantly reduced the overall cost of the project
• The structural model for the roof was established by Buro Happold Engineers working in collaboration with Richard Rogers Partnership. Detailed discussions
also influenced the type of cables specified and the nature of the connection details, as well as the specification for the tent-like roof material.
ABHAY MANANI - 36
PHOTOS
ABHAY MANANI - 36
REFRENCES
• Ashford Designer Retail Outlet – Retail – Projects – Rogers Stirk Harbour + Partners | RSHP (rsh-p.com)
• Tensinet
ABHAY MANANI - 36