Professional Documents
Culture Documents
Design Considerations in
Cable-Stayed Roof Structures
by Lawrence A. Kloiber, P.E., David E. Eckmann, AIA, S.E., P.E., Thomas R. Meyer, S.E., and Stephanie J. Hautzinger, AIA, S.E.
able-supported roof struc- major factor in the load-carrying capacity sisting of one or more groups of wires,
Lawrence A. Kloiber is vice presi- David E. Eckmann AIA, S.E., Thomas R. Meyer S.E. is a Stephanie J. Hautzinger AIA,
dent of engineering at LeJeune P.E. is a principal and the di- structural engineer and associ- S.E. is a project engineer and
Steel Co., Minneapolis. He is rector of structural engineering ate with OWP/P, Chicago. associate with OWP/P,
AISC’s 2004 T.R. Higgins Award at OWP/P, architectural-engi- Chicago.
winner. neering firm in Chicago.
References
Several books provide guidelines and
commentary for cable-stayed structural
design. However, governing building
codes do not address specific design cri-
teria for cable-supported structures. As
such, the American Society of Civil Engi-
neers (ASCE) developed useful stan-
dards through their publication ASCE
19-96, Structural Applications of Steel Ca-
bles for Buildings. The ASCE 19-96 publi-
cation offers recommendations for design Triple-tube jet grouting beneath the mast foundations will minimize long-term settlements.
drawings and specifications, design con-
siderations, material properties, fittings,
protective coatings, and fabrication and the erected structure, as well as ranges of sion of OWP/P, was structural designer
erection of cable structures. acceptable final cable tensions at a de- and structural engineer of record for the
ASCE 19-96 indicates that tempera- fined ambient temperature. project.
ture effects on cables, vibrations, deflec- The design documents also should The Ratner Center is the first asym-
tions, and erection analysis must be provide parameters for the erection se- metrically supported cable-stayed build-
evaluated for cable structures. The ASCE quence. While it is the erection engi- ing with multiple levels of splaying
standard also states the minimum break- neer ’s responsibility to establish the cables in Chicago, and possibly the
ing strength of cables shall always be at erection sequence, the design engineer is world. The structural solution allows
least twice the maximum cable design most familiar with the final structure, large-volume spaces (more than 20,000
loads, including the envelope of loading and can provide valuable information sq. ft) to be enclosed with structural steel
combinations of cable self-weight, struc- regarding issues of load flow and struc- members that are only 33” deep.
ture dead load, cable prestress forces, and tural stability. The design engineer
live-load and environmental-load combi- should be aware that the erection se- Structural Overview
nations. Cables also should maintain a quence might require cable forces not The structural system for the gymna-
minimum tensile force under all loading analyzed originally for the completed sium and natatorium space is a masted
conditions to minimize visible cable sag structure. When cables initially are ten- cable-stayed roof system of composite
and potential for induced cable vibra- sioned, frequently they are not ten- masts that are sloped, tapered, and stabi-
tions. Maintaining minimum cable ten- sioned to defined design tensions. lized by 15 cables (nine fore-stay cables
sions is critical to achieving the stiffness Unless all cables are tensioned simulta- and six back-stay cables), which in turn
necessary to stabilize the axial compres- neously, the magnitude of cable tensions support S-shaped roof girders.
sive masts and other structural compo- will change as subsequent cables are The structural system allows column-
nents. Cable-supported structures are tensioned. As a result, some cables ini- free spaces of 160’ by 125’ in the gymna-
generally lighter structures and must be tially are over-tensioned and others sium, and 130’ by 200’ in the natatorium.
designed to account for the dynamic ef- under-tensioned to achieve the correct Both spaces have a similar system of pri-
fects of individual cables and the overall final tensions. mary masts spaced at 75’ on center,
structure. which are opposed at the other end of the
The construction documents for cable- Case Study: Ratner Center structure by smaller masts located at 25’
stayed roof structures typically provide The University of Chicago is in the on center. Each primary mast supports
information not shown on projects with midst of its largest capital development three curved roof girders, with the mast
more conventional structures: they de- program in its history, and is investing located on axis with the center girder.
fine specific coordinates and parameters more than $500 million in new facilities The cables splay outward from the mast,
of the cable structure, including diameter and renovations. The new Gerald Ratner and support roof girders located 25’ to ei-
and required cross-sectional area of the Athletics Center is a $51-million state-of- ther side of the central girder. The cables
cables, which can vary depending on size the-art athletics facility with 150,000 sq. ft are connected to the primary mast at
and shape of wires used in the cables. of fitness and sports area. The project in- three distinct elevations: top of the mast,
The documents and specifications should cludes a competition gymnasium and an approximately 25’ below the mast top,
indicate any requirements for wire coat- Olympic-sized natatorium. and at approximately 50’ below the mast
ings, unique material properties, and Cesar Pelli & Associates teamed with top. Each level has three forestay cables
specific testing procedures. They also OWP/P to design the facility. OWP/P that reach to one of the three supported
should identify acceptable tolerances for served as the architect of record for the roof girders. Each level also has two
the final geometry of key coordinates of project, and OWP/P Structures, a divi- backstay cables, each reaching to a tie-
down connection located 25’ on either balanced. Thus, the girders located at that the slight rotation of the mast
side of the mast. The backstay cables the exterior walls on each side of the under loading conditions does not in-
transfer load to steel tension columns, structure must be supported by the mast duce moments at the mast’s base. Addi-
which in turn anchor to massive concrete and cable system, and not the perimeter tionally, the W33 that is in line with the
foundations resisting the overturning columns located below the end girders. mast and carries axial horizontal thrust
forces from the weight of the roof. The columns at the exterior sidewalls of to the roof truss located behind the
Smaller secondary masts opposite the the spaces offer no vertical support to masts is detailed as a collar that passes
primary masts are located at each girder the roof structure, and are connected to load around the mast, minimizing
line. A single cable from the top of this the roof only with vertically slotted con- bending in the mast. Each mast in the
mast supports a portion of the roof nections. The sidewall columns prima- gymnasium transfers more than 1700
girder. Two back cables in a bow configu- rily are vertical beams, which resist kips of vertical load from the roof
ration help resist the flattening tendency wind loads from the 50’-tall exterior through the cables to the foundation.
of the arched roof. The result is a series of walls. However, the perimeter columns Since the large-volume gymnasium
roof girders supported at four points by are also components of the lateral sys- and natatorium spaces could not be in-
cables, effectively reducing the girder tem, and so the vertically slotted con- terrupted with interior columns or a tie-
span and allowing the girders to be only nections can transfer horizontal loads down system, a thin layer of concrete
33”-deep wide-flange sections. from the roof diaphragm. The roof is es- topping was added to the long-span roof
The asymmetry of the gymnasium sentially a curved floating plane sus- deck to provide sufficient dead load to
and natatorium structure is a result of site pended only by the cable system. It offset uplift forces from gusting winds.
constraints and architectural design pref- moves approximately 3.5” up and down The roof deck is a 7½”-deep, long-span
erences. The asymmetry results in an un- at mid-span under the envelope of load- deck with 2½” of lightweight concrete
balanced horizontal thrust delivered to a ing conditions across the 160’ span of topping. It spans 25’ between the W33
truss located in the roof plane behind the the gymnasium, and 3” up and down roof girders. The deck acts as a lateral di-
primary masts through axial load in the across 130’ span of the natatorium. aphragm in the direction perpendicular
curved roof girders. The horizontal truss The masts are inclined at 10 degrees to the span of the W33s, transferring load
transfers load to the building’s vertical from vertical for aesthetic reasons and to high-strength diagonal bracing rods at
braced frames, essentially making the lat- to maximize effectiveness in the asym- each end of the gymnasium and natato-
eral system a component of the gravity metrical structure. To maintain the mast rium spaces.
system. as a predominantly axially-loaded
With each of the primary masts sup- member, the base of the mast is mod- Composite Masts
porting three separate roof girders, the eled and detailed literally as a “pinned” The 10-story-tall masts are composed
load supported by each mast must be base in the direction of the span, such of three 18”-diameter steel hollow struc-
tion helped determine brace forces. It for the unusually shaped roof. Wind-tun- portioned conventional shallow founda-
also was compared to required brace nel and water-flume tests were per- tion at the masts. However, due to the
forces to determine k-values for each formed to provide design parameters for magnitude of the mast’s sustained loads,
mast segment. Ultimately, axial capaci- the cable-stayed structure. An accurate the soft clay could experience long-term
ties and moment capacities of each seg- measure of the drift and wind-loading settlement of undesirable magnitude if
ment were calculated to evaluate actual patterns allowed designers to further op- not addressed in the design. Since the
maximum loads to ensure satisfactory timize the building design. It also identi- foundations for the other elements, like
design of each mast. fied heavily loaded areas that are not the secondary masts, resist substantially
intuitive or addressed by the governing less sustained load than the masts, con-
Redundancy code. For example, the water-flume test ventional shallow foundations were ap-
Since the City of Chicago Department identified a snowdrift configuration that propriate for the remainder of the
of Buildings reviewed the project for a could form on the downward-sloping structure. The challenge was to find a
building permit shortly after September portions of the roof near the eave, a criti- mast-foundation system compatible with
11, 2001, the City required that structural cal loading condition for the long-span the long-term anticipated settlement of
engineers closely review the redun- roof deck and the overall structure. the rest of the structure. Large differential
dancy of the structure. Since clear re- Further complicating the matter is the settlements between the masts and the
dundancy criteria for this type of tensile cable structure’s sensitivity to unbal- rest of the building could cause the cables
structure had no precedent, the City es- anced loading conditions as well as its to lose tension and experience visible sag.
tablished criteria requiring the investi- dynamic response to lateral loads. The Traditional deep-foundation systems
gation of instantaneous cable failure and wind tunnel test results provide the were deemed not to be cost effective. The
associated effects. The structural design, means to ensure a clear and reliable un- geotechnical engineer recommended a
including stability of the mast with a derstanding of the structure’s response to soil-improvement method called triple-
missing cable, was evaluated and unbalanced loads. A dynamic analysis of tube jet grouting, which was imple-
deemed satisfactory. the structure verified that the building’s mented to limit the long-term settlement
fundamental frequency does not align of the mast foundations to one-half inch.
Reverse Curved Roof Girders with the frequencies of the individual ca- This technique uses a mixture of grout,
The architectural design called for the bles, minimizing concerns about har- water, and air injected under high pres-
natatorium and gymnasium to be en- monics within the structure. sure to create “columns” of a soil-grout
closed by curved S-shaped roofs. Each of mixture. These columns transfer the
the W33×169 roof members, 160’ in the Mast and Tieback Foundations loads from the foundation directly into
gymnasium, 125’ in the natatorium, is The behavior of the cable-stayed the stiff clay layer.
cold-bent about its strong axis with re- structure is sensitive to settlement of the The asymmetry of the cable structure
verse curves to multiple radii. Segments supporting foundation, particularly at results in large uplift reactions at the base
of W33 up to 100’ long were fed through the mast base. Excessive settlement of the of the tieback columns. Deep foundations
a series of rollers to achieve the specified mast foundation could reduce cable ten- relying on friction or soil weight were ex-
radius in just minutes. sions below the envelope of acceptable plored as alternative solutions, but were
tensions, and selecting the appropriate determined not appropriate or not cost
Wind Tunnel Testing and Analysis foundation system for the mast and effective. Concerns with deep founda-
The reverse curvature of the gymna- tieback columns is critical. The soil pro- tions included potentially adverse im-
sium and natatorium roofs present chal- file at the site consists of a top layer of pacts of long-term upward settlements
lenges when applying code provisions sand approximately 15’ deep. Below the on the behavior of the cables, as well as
for wind and drifting snow. Current sand is 15’ of soft clay underlain by stiff highly tensioned elements in the ground
codes and standards do not specifically clay. The relatively high bearing strength that could possibly be disturbed in the
address wind-loading and drift criteria of the sand allows for a reasonably pro- future. In addition, several tieback
columns are closely spaced and areas of perature. Temporary shoring towers at the adjacent masts before the crew
influence overlap. each cable-attachment location were to be moved up and began tensioning cables at
These considerations directed the de- used to keep the structure in the required the next-highest level of each mast. Ca-
sign team toward the solution: rein- geometry prior to cable tensioning. Once bles were tensioned with two hydraulic
forced-concrete counterweights buried the entire structure was erected and sup- jacks pressurized in parallel, attached to
below grade that utilize their self-weight ported by the shoring towers, the cables the two threaded rods on each socket.
to resist the uplift forces from the cable- were to be tensioned simultaneously, lift- Pressure gauges on the jacks allowed the
stayed tension elements. The system en- ing the structure off the shores and re- erector to covert pressures and determine
sures a foundation with no upward sulting in the intended geometry and the exact force in each cable.
displacement over time, and a system cable tensions. This approach has been
that will not be impacted by future re- successfully on other projects, including Conclusion
moval of the surrounding soil. The long- the cable-supported fabric roof at Cable-stayed roof structures can cre-
term groundwater level limits the depth Stuttgart Stadium in Germany. ate dramatic structures that enclose large-
of these foundation elements to approxi- Once a fabricator and erector were volume column-free spaces, and still
mately 10’ below grade. If the concrete awarded the project, the erector investi- provide opportunities for architectural
counterweights extend below the water gated alternate erection scenarios, partic- design freedom. The University of
table, the hydrostatic pressure on the bot- ularly erecting the structure in stages, Chicago Gerald Ratner Athletics Center
tom of the footing produces additional reducing the need for simultaneous jack- is an innovative cable-stayed structural
upward forces. As a result, the counter- ing. The project specifications required system. The structural solution reduces
weights are large in plan relative to their an erection engineer, a structural engi- the depth of the roof members and proj-
depths. In some cases, the depth restric- neer licensed to model the structure and ect cost by using cables to suspend the
tion forces two tie-back columns to an- the erection procedure. The erection en- structure. The roof system also serves as
chor to the same counterweight gineer chose to erect the structure in the building’s finished materials, elimi-
foundation, with footings that reach sizes stages and had to model the erection nating the need for costly ceilings and
of 25’ × 50’ × 8’ deep. procedure using staged non-linear other cladding materials. The cable-
analysis techniques to ensure the final stayed solution creates a thin structure
Cable-Stayed Roof Erection specified geometry and cable tensions that “floats” over the interior spaces, and
Procedure were achieved. The erection engineer allows natural light to penetrate the
ASCE 19-96 Structural Applications of considered an erection procedure where spaces through continuous clerestories
Steel Cables and Buildings suggests the all the cables were attached to the mast, located along the roofline. ★
contract documents show a recom- and the roof girders would be hung di-
mended erection procedure for the pro- rectly from the mast-supported cables, This paper has been edited for space con-
posed structure. During the design eliminating the need for temporary siderations. To learn more about cable-stayed
phase, the challenge was to get the shoring. However, that scenario induced structures, and the design and construction
final structure to the specified geome- unacceptable horizontal thrusts on the of the University of Chicago’s Gerald Ratner
try and cable tensions, knowing that masts from the roof girders. Athletics Center, read the complete text on-
each stage of the erection sequence The contractor’s favored solution was line at www.modernsteel.com or in the
would impact the geometry and cable to erect the roof girders using a single 2004 NASCC Proceedings.
tensions. These discussions helped temporary shoring tower near the mid-
shape the procedure documented on span of each roof girder. Once erected, ca-
the structural drawings. bles are connected to the mast and roof
The original concept on this project girders, and are tensioned in stages, start-
was to fabricate the structure to a speci- ing at the lowest level of splayed cables.
fied geometry at a defined ambient tem- The same procedure was implemented at