Professional Documents
Culture Documents
Group 3
CONTENT
1. GENERAL INFORMATION & LOCATION
2. HISTORY
3. CONCEPT
4. CORE DESIGN
5. CLASSIFICATION IT FALLS INTO
6. LOAD DISTRIBUTION
7. STRUCTURAL DESIGN CONSIDERATIONS
8. MATERIALS AND TECHNIQUES
9. FOUNDATION INCORPORATED
The CN Tower in downtown
Toronto is a
prestressed-concrete
communications/observation
tower and an iconic symbol of
Canada. The tower was built by
Canadian National in response
to the need for uninterrupted
communications broadcasting
over the skyline of buildings
constructed during Toronto’s
1960s boom.
GENERAL LOCATION
INFORMATION The CN Tower is located at 301
• LOCATION : 301 Front Street West Toronto, Front Street West in the heart of the
Ontario Entertainment District, on the north
shore of Lake Ontario, Toronto,
• CONSTRUCTION PERIOD : 1973 – 1976
Canada. The Tower is easily
• COST : $63,000,000 accessible from Union Station and
the streets and major roads.
• ARCHITECTS : John Andrews, Webb Zerafa,
Menkes Housden
CENTRAL HOLLOW
HEXAGONAL SHAFT
ELEVATORS
CORE DESIGN
CLASSIFICATION OF STRUCTURE
EXTERIOR STRUCTURES
TUBE SYSTEM
Interior main
structure
LOAD AND DESIGN CONSIDERATIONS
STRUCTURAL DESIGN CONSIDERATIONS
● The high magnitude of the forces to be dealt with implied the use of a large quantity of high
strength steel tendons (a total in excess of 1000 tons was eventually used)
● Because of the record-breaking height of the Tower, it was anticipated that construction would
last through at least one winter. Consequently, the concreting and post-tensioning operations
would have to be planned to withstand very severe weather conditions.
● The verticality and length of the tendons would be a significant departure from previously-known
practice, and would introduce a whole new set of practical considerations, relating to the placing,
securing, stressing, and grouting of the tendons. For instance, an accurate prediction of the
post-tensioning losses was very difficult because of insufficient experience with this type of
application.
● Grouting of vertical ducts would cause substantial hydrostatic pressure inside the ducts, the
consequences of which were hard to predict.
STRUCTURAL DESIGN CONSIDERATIONS
● The decision to post-tension the ring beam at the supporting structure for the skypod posed
intricate problems of geometry, relating to restricted space and the requirement to produce a
uniform and symmetrical final stress in the twelve sided polygon.
● Similarly, the decision to post-tension the ring beam at the supporting structure for the skypod
posed intricate problems of geometry, relating to restricted space and the requirement to
produce a uniform and symmetrical final stress in the twelve-sided polygon.
● At an early design stage, it appeared logical to construct the Tower shaft by the slipform
technique. Since this method of construction is fairly sophisticated, it also meant that severe
restrictions would be imposed on such items as time schedules and space requirements relating
to detailing, placing, and stressing the tendons.
● The fact that part of the tendons had to be placed and stressed in the cold season, when the
temperature of the concrete of the Tower walls would be below freezing, made it impossible to
perform the grouting operation until many months later. Hence, the possibility of corrosion had to
be considered.
LOAD DISTRIBUTION Y AXIS
Lift
Six glass elevators up and down from its exterior to 6 meters per
second, at 1 meter and a half where there are strong winds.
Antenna
The transmitting antenna measures 102 meters and consists of 44
pieces of steel with 8 tons the heaviest.
CONSTRUCTION TECHNIQUES
SLIP FORM