You are on page 1of 44

Ordinary Breakwaters

Ermia Sarsakh
December, 2021
Introduction
Upright Breakwaters

Sloping Breakwaters

Breakwaters Covered with


Wave-dissipating Blocks
Gravity Breakwaters Pile-type Breakwaters
Upright Wave-absorbing
Block Type Breakwaters

Wave-absorbing Caisson
Type Breakwaters

Sloping-top Caisson
Breakwaters

2
1
Upright Breakwaters

3
a) Caisson type upright breakwater

4
b) Concrete block type upright breakwater

5
2
Sloping Breakwaters

6
a) Rubble mound breakwater

7
b) Dumping block mound sloping breakwater

8
Setting of Basic Cross Section

• Wave transmission
• Caution is necessary
• Crest width based on model experiments
• Slope gradient based on calculation

• Slope gradient for rubble mound type:


1: 2 (1: 1.3) on the seaward side
1: 1.5 (1: 1.5) on the harbor side

9
Performance Verification of Stability of Sloping Section

• Slip failure of the rubble mound section is examined. The examination can
be performed for slip due to eccentric and inclined loads
• In the armor materials the thickness should also be adequate to prevent
sucking-out of the material
• Mass of the rubble and blocks be approximately 1/10 to 1/15 that of the
armor units or more

10
Partial Factors

11
Performance Verification for Stability of Breakwater Head

▷ The head section be constructed in a semi-circular shape


▷ Using armor units with a mass 1.5 times that of the body
section or more

12
3
Breakwaters Covered with
Wave-dissipating Blocks

13
Cross Sections

14
Setting of Basic Cross Section

▷ Upright section crown height = composite breakwaters


▷ Height of wave-dissipating = upright section
▷ The breakwaters covered with wave-dissipating blocks,
overtopping waves and transmitted < the upright
breakwaters and the composite breakwaters with the
same crown heights.

15
Partial Factors

16
All partial factors indicated here are values for the case where the design working
life is the normal 50 years.
17
Performance Verification for Stability of Armoring Section

▷ Regular placing is used rather than pell-mell placing of the


armor material → the necessary mass may be determined
at the judgment of the responsible engineer.
▷ The thickness of the armor layer in case of pell-mell
placing shall generally be 2 layers or more.

18
Performance Verification For Stability of Breakwater Tip

▷ Constructed in a semi-circular shape


▷ Using armor units with a mass of 1.5 times that of the
body or more

19
4
Upright Wave-absorbing
Block Type Breakwaters

20
21
Principals of Performance Verification

▷ Various types of structures have been developed


▷ Select appropriate blocks based on an adequate investigation
▷ The wave reflection coefficient depends upon the wave period
▷ Generally used in inner bays or the inside of harbors
▷ For small heights waves

22
Setting of Basic Cross Section

▷ Crown height = composite breakwaters


▷ hc
▷ h'c
▷ hu

23
Partial factors

24
5
Wave-absorbing Caisson
Type Breakwaters

25
26
Principals of Performance Verification

▷ Hydraulic characteristics are still insufficiently understood


▷ It is preferable to perform hydraulic model tests
▷ Features in comparison with the composite breakwaters:
• Reduction in reflected waves
• Reduction in wave overtopping and transmitted waves
• Reduction in wave force
• It possesses a sea water aeration function

27
Actions

▷ Verification of wave-absorbing performance can be set


separately from verification of the stability
▷ Generally adopted for the purpose of reducing reflected
waves
▷ Necessary to determine wave force using calculation
formulas or hydraulic model tests
▷ The most severe wave force conditions for each member
should be used

28
Setting of Basic Cross Section

▷ The required dimensions should be determined appropriately,


considering the shape of the structure
▷ Determine the dimensions considering these characteristics:
• Wave overtopping
• Transmitted waves
• Wave force

29
Partial factors

30
6
Sloping-top Caisson
Breakwaters

31
Utilizes the wave force acting on the sloping wall to
stabilize the breakwater body simultaneously by
reducing the horizontal wave force

32
Fundamentals of Performance Verification

▷ Normally the sloping surface begin at the SWL


▷ The upright part at the front is armored with wave-dissipating
blocks

33
Setting of Basic Cross Section
▷ At the same crown height, the coefficient of wave
transmission of the sloping-top caisson breakwaters = 2 times
that of the upright breakwaters
▷ Gradient of the sloping wall the effectiveness of the
structure against wave transmission in the harbor
▷ 𝜃 = 45

34
Partial factors

35
6
Sloping-top Caisson
Pile-type Breakwaters
Breakwaters

36
Fundamentals of Performance Verification

▷ divided into curtain wall and steel pipe pile


▷ The curtain wall breakwater: permeable - used in waters
with a low wave height
▷ Steel pipe pile breakwater :curtain section is eliminated -
waves are stopped only by the piles

37
38
39
Curtain wall breakwaters features

▷ Reduction in Kr as same level as wave-dissipating


▷ Exchange of sea water can be expected through slits
▷ Energy dissipating effect with the double-curtain-walled
▷ Velocity of flows passing under the curtain wall is quite high
▷ It is necessary to take appropriate acions to prevent or
washing-out of sand

40
Setting of Basic Cross Section

▷ Considering:
• the condition of sea states in the area
• the target reflection coefficient
• the target transmission coefficient
• constructability

41
42
43
Thanks!

44

You might also like