Professional Documents
Culture Documents
Headworks
• Passage of sediment load
All bed load and suspended load must pass the diversion weir. The sediment
transport pattern of the river shall preferably not be disturbed.
• Passage of floods
The design flood shall pass safely. A hazard flood caused by landslide or GLOF
must be considered (and expected).
• Passage of floating debris and ice
All floating debris must pass the diversion weir and not accumulate in front of the
intake.
• Sediment control at the intake
The riverbed shall not be allowed to build up in front of the intake. Bed load must
be prevented from entering the intake.
• Settling basin control
The content of suspended sediment load in the water released from the settling
basins shall be acceptable with respect to sediment induced turbine wear.
2
FACTOR AFFECTING FOR SELECTING OF SITE
• Availability of water
• Water storage capacity
• Accessibility of the site
• Distance from load center
• Type of land of site
• Availability of man and material
• Environmental condition
• Conflict with other uses for drinking water and
irrigation
Selection of location of diversion works
• Site be straight reach
• Narrow Section
• Stable Banks
• Good accessibility
• Construction material should available
around the site
• Diversion during construction should be
possible
• Geologic and topographic conditions should permit
a favourable location of
(a) Spillway and diversion tunnel and
(b) power house and outlet works.
• The location of the construction materials should
be within an economically justified distance from
the project.
WHAT IS Diversion works
“A structure to
divert water
into a conduit
leading to the
power plant” is
called
Diversion
Intake
TYPE OF WEIRS
• Trench weir
• Rock fill weirs
• Vertical drop weirs
• Concrete weir with sloping glacis
• Coanda weir
• Inflated weir/ Rubber dam
7
8
Typical
sections for
wood,
masonry and
concrete weirs
General
Arrangement
of Partial
Weir
Typical Section of Gabion Weir with Downstream Protection
Works
Typical Details of a Raised Weir on Erodable Foundation (Plan)
Typical Details of a Raised Weir on Erodable Foundation
Typical Details of a Weir on Impermeable Foundation
Diversion
weir Intake
Plan
Another type of
Diversion Barrage
Cross – sections
Of diversion barrage
Hydraulic Design
The length of the weir across the flow is required to be sufficient
enough to pass design flood.
This is given by the following relation:
Q = c × b × h3/2, where,
Q = Design flood discharge in cumecs
c = Coefficient of discharge which varies from
1.71 for smooth top surface to 1.33 for rough
surface,
b = Length of weir across the flow in metres, and
h = Water depth atop the weir in metres
For a gabion weir the maximum water depth atop the weir should be
limited to 3 metres
POSITION OF Diversion INTAKES -
Factors governing the arrangement of an intake
• The intake should be aligned so that the trash and ice
tends to float past and not collect at the intake screens.
• The intake should be arranged so that the effect of
such movement (movement of boulders, stones and
sand) will not lead to a partial restriction or blockage
of the intake.
• The intake can often be located so as to enable it to be
constructed before the level of the reservoir is raised.
• Give minimum hydraulic losses.
• Prevent formation of air entraining vortices.
COMPONENTS OF INTAKES:
• Intake Gates
• Trash rakes & screens
• Fish ladders
• Ice, log and trash boom
• Silt Excluders and Silt Ejectors
• Smolt screens
• Under sluices
• Divide wall
INTAKE GATES:
• Gates are installed on the crest of
the dam.
• Permit a temporary lowering of the
crest level in time of flood.
• Vertical and Radial gates can also
used in low level passages through
the base of a dam.
Radial Gates at Älvkarleby, Sweden
36
TRENCH (DROP) WEIR
Boulder stream
Bottom racks
Intake Chamber
Power Channel
37
DESIGN OF TRENCH WEIR AND INTAKE
= 0.789 m
Provide a width of 2.0 m from practical consideration
Check-Width
Width of trash rack for 0.40 m/s velocity of water.Allowable width
through trash rack Q
= V L
8.21
= 0.40 40
= 0.513 m
Width required for 50% clogging
= 2 x 0.513 = 1.02 m
1.02 m is less than 2.0 meter provided and hence safe
Classification of Dams
42
According to size of a Dam
Large dams
Small dams
– According to International commission on Large
Dams, a dam is big if height is more than 15m.
– According to ICOLD, if the height is between 10m-
15m the dams is big:
• If the crest length is bigger than 500m
• If the reservoir capacity is larger than 1 million m3
• If the flood discharge is more than 2000 m3/s
43
According to Height of dam
• High Dam
– If the height is more than 100m.
• Medium Dam
– If the height is between 50-100m
• Low Dam
– If the height is below 50
44
Definition
A dam is a structure which prevents the flow of
water and accumulates it in a reservoir.
45
CLASSIFICATION (TYPES) OF DAMS
• BASED ON PURPOSE
• BASED ON HYDRAULIC DESIGN
• BASED ON MATERIAL OF CONSTRUCTION
• BASED ON STRUCTURAL BEHAVIOUR
• BASED ON SIZE
– HYDRAULIC HEAD
– GROSS STORAGE IN THE RESERVOIR BEHIND THE
DAM
46
BASED ON PURPOSE
1. STORAGE DAM OR IMPOUNDING DAM
2. DETENTION DAM
3. DIVERSION DAM
4. COFFER DAM
5. DEBRIS DAM
47
BASED ON STRUCTURAL BEHAVIOUR
• GRAVITY DAM
• ARCH DAM
• BUTTRESS DAM
• EMBANKMENT DAM
48
49
Factors Affectıng To The Dam Type Selectıon
• Topography
• Geology
• Bearing capacity of the underlying soil
• Foundation settlements
• Permeability of the foundation soil
• Material availability
• Spillway position
• Earthquakes
• Safety
• Height
• Aesthetic view
• Qualified labour
• Cost 50