Professional Documents
Culture Documents
Report 85 Pul Coal
Report 85 Pul Coal
FOREWORD
The Power Plant Component of India German Energy Programme (IGEN) is being
implemented in India with the cooperation of Central Electricity Authority (CEA), Ministry
of Power, Government of India and GTZ, Germany. The overall aim of this programme is
to support and prepare public plant operators for performance reporting as well as
implementation of financially attractive and technically viable improvements of power
plant net heat rate.
Under the IGEN programme, mapping of 85 coal based power generating units, ranging
from 100 to 500 MW capacities, were carried out by using a diagnostic tool. This study
has been completed during the period 2007-09 covering state owned plants in 14
States, 17 power utilities and 45 thermal power stations. The mapping studies have
been done on two conditions namely design parameter as well as on actual operating
parameters gathered from different plants for a specific period. The unique feature of
this study is that heat rate of the generating unit is not based on the quantification of
coal consumed and energy generated but with the thermo dynamic balancing of actual
operating parameters.
The primary purpose of mapping study is to provide a data base and broadly identify
areas requiring attention for improving energy efficiency. The baseline mapping
provides an objective method of setting targets and monitoring progress. The reports
provide an indication about the necessity and urgency of taking up detailed Residual Life
Assessment studies and Renovation & Moderation (R&M) measures in some of the plants.
The report, also, indicates measures that could be taken up immediately with
comparatively smaller expenditure to improve plant performance before going in for
regular R&M measures.
The outcome of the study was discussed with the individual State Utilities, who
appreciated the recommendations made and findings of the study. Some of the utilities
have already implemented majority of the recommendations and others are in process of
implementing.
For wider dissemination of the findings of the mapping study, the report is being
uploaded on CEA website for the benefit of power stations where the mapping study was
not carried out. The report highlights the major deviations in operation from design
parameters and measures suggested to improve the performance of the plants. The
power station personnel may implement the recommendations of the mapping studies
to improve the performance of their plants.
Mapping of 85 pulverized coal fired thermal power generating
units in different states
(Under Indo-German Energy Program (IGEN))
SUMMARY REPORT
LIST OF ANNEXURES
1 Description of 85 Final Mapping Reports of Various Generating Units submitted
to CEA
2A Operating Indices for 500 MW units
2B Operating Indices for 250 MW units
2C Operating Indices for 210 MW units
2D Operating Indices for 195-200 MW units
2E Operating Indices for 140 MW units
2F Operating Indices for 120-125 MW units
2G Operating Indices for 100-110 MW units
3A Graph for Operating Gross Heat Rate of 500 MW capacity units (kcal/kWh)
3B Graph for Operating Gross Heat Rate of 250 MW capacity units (kcal/kWh)
3C Graph for Operating Gross Heat Rate of 210 MW capacity units (kcal/kWh)
3D Graph for Operating Gross Heat Rate of 100-125 MW capacity units (kcal/kWh)
3E Graph for Operating Turbine Heat Rate of 500 MW capacity units (kcal/kWh)
3F Graph for Operating Turbine Heat Rate of 250 MW capacity units (kcal/kWh)
3G Graph for Operating Turbine Heat Rate of 210 MW capacity units (kcal/kWh)
3H Graph for Operating Turbine Heat Rate of 100-125 MW capacity units (kcal/kWh)
1.0 INTRODUCTION
The Ministry of Power, Government of India, and Deutsche Gesellschaft fur
Technische Zusammenarbeil (GTZ) Gmbh signed an ‘implementation agreement’
with respect to the Indo-German Energy Programme (IGEN) in the year 2006.
Under the IGEN agreement, power plant component is being implemented by the
Central Electricity Authority (CEA), in association with the Bureau of Energy
Efficiency (BEE), for performance optimization and efficiency improvements of
thermal power plants. The programme aims to support and prepare power plant
operators for performance reporting as well as implementation of financially
attractive and technically viable improvements of power plant net heat rate
under the provisions of the Energy Conservation Act.
Under the first phase of the programme, GTZ provided support to Central
Electricity Authority (CEA) for creating data base of the older thermal power
plants in India. The scope of the work primarily covers the mapping of 85
thermal power generating units using Ebsilon software.
The mapping has been done for two conditions, namely for design parameters
and for the actual operating status for the plant parameters gathered from
different plant locations. The primary purpose is to provide a database within
CEA and broadly identify areas needing attention in the short, medium and long
term for improving energy efficiency. The baseline mapping provides an
objective method of setting targets and monitoring progress.
Evonik Energy Services India (EESI) was appointed to carry out the mapping of
the 85 power generating units. EESI is a 100% owned subsidiary of Evonik Energy
Services GmbH Germany. Evonik, Germany, owns and operates a number of
large coal fired power plants with an installed capacity of 11,000 MW in
Germany and other countries.
3.0 METHODOLOGY
Design and current operating data for the units were obtained through
questionnaires sent by CEA to concerned utilities. Further required data were
collected during site visits by Evonik engineers. A design model was then built
on the basis of design data obtained from site using Ebsilon software. Actual
4.0 FINDINGS
The mapping studies revealed that most of the units are being operated under
various constraints like poor quality of coal, poor spare and activity planning,
turbine and other equipments, Poor condenser vacuum, high steam
consumption, poor housekeeping, operating parameters different from the
rated values and obsolete instrumentation. These have resulted in high heat
rates and unreliable plant operations. These observations are analyzed below.
The analysis brings out, also, that deterioration in the turbine heat rate is the
major factor for gross heat rate deterioration. For example, the weighted
average deterioration of turbine heat rate came as 10% compared to the average
gross heat rate deviation of 18 %
Assumption
Units operate at an average gross heat rate which deviates only by 7.5 % from
the average design heat rate.
Table 5 below gives the potential savings in coal consumption and economy in
cost if all the units of a particular capacity group operate at an average heat rate
which deviates by 7.5% only from the average design heat rate as compared to
the situation in which all the units in the group operate at the actual operating
heat rate.
Assumptions:
Average calorific value of coal - 3626 kcal/kg
Price of coal - Rs 1400/ton
Average plant load factor (2008-09) - 77.2%
It must be observed that the significance of the above factors differs amongst
different capacity ranges, as also, in between units of the same range. In
general, the deviations from optimum are less for 250 MW and 500 MW units.
One of the major cause for the unreliability is poor Housekeeping and
equipment maintenance planning.
Ebsilon software has been used to simulate and frame models with the design
and the operating parameters. The software enables assessment of impact of
changes in some parameters over those on other related parameters. The
thermodynamic cycle analysis balances in totality and we can access the impact
of one system gain on the other system. Such changes include deviations in coal
quality; change in environmental parameters, cooling water temperature has
been assessed. The base model in each case was developed on the basis of
design parameters. Thereafter actual operating parameters were obtained from
site and put in the sub-profile of the design model to obtain the performance of
the unit under current operational conditions and assess the deviations.
Deviations in the following can be determined with the help of the model taking
into account the impact of external factors and current condition of the plant
after operation of so many running hours. Most units already crossed more than
100,000 running hour’s needs immediate attention to retain the following
parameters within the best possible limits. In some cases it was already crossing
the limits that require immediate R&M.
• Short term
• Medium term
• Long term
The medium term recommendations pertain to those works which can be taken
up during major shut down or during overhauling. These recommendations
relate to attending to coal firing system, air dampers, flue gas system, cooling
towers etc and other major defects observed by Evonik engineers.
12.0 CONCLUSION
The mapping exercise of the 85 power plants has generated a lot of data and
information on the performance of power plants. The reports have been sent to
respective plant authorities and presentations have been made before the top
managements at the respective utility headquarters. The reports provide an
indication about the necessity and urgency of taking up detailed RLA / CA
studies and R&M measures in some of the plants. The reports, also, indicate
measures that could be taken up immediately with comparatively small
expenditure to improve plant performance before going in for regular R&M
measures.
The improvement in heat rate of units to within 7.5 per cent of the design heat
rate, as is normally accepted after R&M is undertaken for the units, results in
expected saving of about 6.93 million tons of coal per year for all the 85 units
for which Ebsilon mapping studies were undertaken. This saving in coal could
enable generation of about 9,600 MU per year if used in 500 MW units.
It has been observed, also, that in addition to the plant problems explained
above, there is need to give attention to improved maintenance practices,
manpower planning, training of engineers, installation of, preferably, on-line
monitoring system and updating of auto controls and instrumentation. The use
of computers for maintaining plant history records should be more extensive. It
is necessary to carry out total audit of plant functions covering management
issues, delegation of powers and inventory management which are equally
important to improve the plant performance. The institutional arrangements
require the establishment of an energy efficiency cell at each power plant
location. The concept of Model Power Plant has been suggested by CEA to
sustain the benefits of the mapping exercise.
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
Note: Observations/analysis presented in the table are based on the operating parameters as observed at the time of Mapping Studies
SL. NO. Year of Age Mode Load Gross Turbine Boiler Main Steam Condenser Auxiliary
Commiss- till (MW) Heat Rate Heat Rate Efficiency Flow Tempera- Pressure Vacuum Power
ioning 2008 (kcal/kWh) (kcal/kWh) (%) (tph) ture (°C) (kg/cm2) (mmHg) Cons.
(%)
1 1974/2000 34 Design 120 2388.4 2054.7 86.00 360.0 540.0 130.4 690.0 10.02
Operating 66 2764.1 2244.3 81.20 200.0 532.0 73.5 684.1
Dev (%) -45.0% 15.7% 9.2% -5.6% -44.4% -1.5% -43.6% -0.9%
2 1978/2000 30 Design 120 2394.5 2054.7 86.00 362.0 535.0 130.0 690.0 13.47
Operating 98 2709.7 2207.9 81.50 290.0 530.0 107.0 676.0
Dev (%) -18.3% 13.2% 7.2% -5.2% -19.9% -0.9% -17.7% -2.0%
3 1981 27 Design 120 2442.0 2100 85.99 410.0 537.0 128.8 700.0 10.36
Operating 114 2796.0 2261.5 80.88 410.0 532.0 126.2 680.0
Dev (%) -5.0% 14.4% 7.7% -5.9% 0.0% -0.9% -2.0% -2.9%
4 1977 31 Design 120 2442 2100 86.00 362.0 535.0 130.0 690.0 14.32
Operating 102.9 2689.9 2187.7 81.30 320.0 530.0 120.0 670.0
Dev (%) -14.3% 10.1% 4.1% -5.5% -11.6% -0.9% -7.7% -2.9%
5 1988 20 Design 120 2442.0 2100 85.50 372.0 537.0 127.0 684.0 13.66
Operating 73 2801.7 2306.9 82.30 246.0 536.0 118.0 664.0
Dev (%) -39.2% 14.8% 9.8% -3.7% -33.9% -0.2% -7.1% -2.9%
6 1976 32 Design 120 2346 2100 89.60 370.0 537.8 127.6 686.0 10.54
Operating 108 2862.0 2360.6 82.50 328.0 510.0 106.0 663.0
Dev (%) -10.0% 24.4% 14.5% -7.9% -11.4% -5.2% -16.9% -3.4%
7 1977 31 Design 120 2442 2100.0 86.00 403.0 540.0 133.0 686.0 12.41
Operating 78.46 3730.0 2796.0 75.00 273.0 523.0 102.8 654.0
Dev (%) -34.6% 54.2% 33.4% -12.8% -32.3% -3.1% -22.7% -4.7%
Dev (%) -41.6% 31.2% 18.2% -9.2% -27.9% -5.6% -39.4% -4.3%
9 1999 9 Design 125 2400.0 2022.0 84.30 390.0 540.0 132.0 710.0 11.50
Operating 128 2771.0 2162.0 78.00 391.0 539.0 145.0 676.4
Dev (%) 2.4% -15.5% -6.9% 7.5% -0.3% 0.2% -9.8% 4.7%
Total Average Design Values 120.6 2395.4 2063.4 86.15 374.8 537.4 129.9 691.8 12.21
Average Operating Values 93.2 2921.9 2333.9 80.09 300.7 526.3 108.6 669.7
Average Deviations (%) -22.8% 18.5% 11.5% -5.4% -20.2% -2.0% -18.6% -2.1%
Minimum of Operating Values 66 2689.9 2162.0 75.00 200.0 505.0 73.5 654.0 10.02
Maximum of Operating Values 128.0 3730.0 2796.0 82.50 410.0 539.0 145.0 684.1 14.32
Note: Observations/analysis presented in the table are based on the operating parameters as observed at the time of Mapping Studies
Note: Observations/analysis presented in the table are based on the operating parameters as observed at the time of Mapping Studies
2700
kcal/kWh
2646.7
2650
2590.0
2600
2563.0
2550
2523.4
2508.0
2500
2450
2400
ANNEXURE-3B
2900
kcal/kWh
2800 2773.0
2751.1
2667.0 2698.8
2700
2600
2546.1
2500
2400
2300
2200
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
BAC/IGEN//EBSILON MAPPING SUMMARY REPORT 43 of 59
ANNEXURE-3C
3200
kcal/kWh
3100 3063.6
3000 2970.4
2900 2875.1
2805.0
2800
2711.4
2672.1
2700
2602.1
2600 Gross Heat
2529.4 Share of
Rate
2500 units
(kcal/kWh)
2383.7 - 2500 12.2%
2400
2500 - 2600 10.2%
2300 2600 - 2700 24.5%
2200 2700 - 2800 20.4%
2800 - 2900 22.4%
2100
2900 - 10.2%
2000
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
4000
kcal/kWh
3800 3730.0
3600.8
3600
3400
3172.4
3200
3067.5
3000 2883.0
2851.3
2764.1 2801.7
2800 2689.9 2709.7
2600
2400
2200
2000
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
2200
kcal/kWh
2178.6
2180
2160
2140
2120
2090.9 2093.0 2095.7
2100
2087.0
2080
2060
2040
2020
2000
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
2350
kcal/kWh
2284.0 2294.0
2300
2231.9
2250
2210.6
2200
2179.2
2150
2100
2050
2000
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
2500
kcal/kWh
2000
1950
1900
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
3000
kcal/kWh
2881.4
2900
2796.0
2800
2700
2600
2500
2478.5
2440.3
2400 2360.6
2306.9
2300
2215.0 2244.3
2187.7
2200
2100
2000
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
86
%
84.12
83.50
84
83.05
82
81.40
80
79.00
78
76
74
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
86 85.6
%
84
82.9 83.0
82.7 82.7
82
80
78
76
74
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
90 Boiler
Share of
%
Efficiency
units
88 (%)
- 78 6.1% 86.0
86 78 - 80 18.4% 84.8
80 - 82 18.4% 83.9
84
82 - 84 36.7% 82.3
82.7
82.0
82 84 - 20.4%
81.0
80 79.6
78.6
78 77.1
76
74
72 71.0
70
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
86
%
84
82.2 82.3 82.3 82.5
82 81.2 81.3 81.5
80.9 81.0
80.0 80.0
80
78.8
78.1
78
76
75.0
74
72
70
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
9.0
8.69
%
8.5
7.81
8.0
7.71
7.50 7.51
7.5
7.0
6.5
6.0
5.5
5.0
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
11.0
%
10.04
10.0 9.73
9.58
9.33
9.0
8.54
8.0
7.0
6.0
5.0
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
14.0
%
Auxiliary
Share of 12.87
13.0 Power
units
Cons.%
8-9 22.4%
12.0
9 - 10 55.1%
10 - 11 12.2% 11.15
11.0 11 - 12 8.2%
12 - 2.0%
9.92
10.0 9.70
9.15 9.32
9.00
9.0 8.66
8.07
8.0
7.0
6.0
5.0
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
18
%
16 15.31
14.32 14.44
14 13.47 13.57 13.66
13.04
12.41
12
10.54
10.02 10.36
10 9.38 9.60
9.11
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model
Dry gas
loss
Cooling tower
performance
Note: Observations/analysis presented in the table are based on the parameters at the time of Mapping Studies and simulated by model