Professional Documents
Culture Documents
EG. 1
1. Sketch the AON
2. Determine the project Duration & Critical Path
3. Free float of F
4. Total float of F.
1. Sketch the Gantt Chart
2. Determine the project Duration
3. Free float of F
4. Total float of F.
a
b e d c f
g h
j i
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
1. Sketch the AON
2. Determine the project Duration
3. Free float of F
4. Total float of F.
a
c
b
f
i
h i
j
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
1. Sketch the AON
2. Determine the project Duration & Critical Path
3. Free float of F
4. Total float of F.
a
c
b
f
i
h i
j
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
EG. 2
1. Sketch the AON
2. Determine the project Duration & Critical Path
3. Free float of C Activity Description
Immediate Duration
Predecessor (days)
4. Total float of C. A Develop product - 4
specifications
B Design A 6
manufacturing
process
C Source and purchase A 3
materials
D Source and B 6
purchase tooling
and equipment
E Receive and install D 14
tooling and
equipment
F Receive materials C 5
G Pilot production run E,F 2
H Evaluate product G 2
design
I Evaluate process G 3
performance
J Write documentation H, I 4
report
K Transition to J 2
manufacturing
Duration
Activity Predecessor
1. Sketch the Gantt Chart (days)
A - 4
2. Determine the project Duration & Critical Path
3. Free float of C B A 6
4. Total float of C.
C A 3
D B 6
E D 14
F C 5
G E,F 2
H G 2
I G 3
J H, I 4
K J 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
Figure 5-23
A Gantt
Chart of a
Sample
Project
Figure 5-24 A Gantt Chart of Sample Project Showing Critical
Path, Path Connections, Slack, EST, LST, EFT, and LFT
a
b
c
d
e
f
g
h
Figure 5-25 A Gantt Chart of a Day Care Project Showing
Expected Durations, Critical Path, Milestone, and Resource
Requirements
Figure 5-26 A Progress Report on a Day Care Project
Showing Actual Progress Versus Baseline
EXTENSIONS TO PERT/CPM
Finish-to-start linkage
Start-to-start linkage
Finish-to-finish linkage
Start-to-finish linkage
Figure 5-27 Precedence Diagramming
Conventions
Other Methods