Professional Documents
Culture Documents
Method Statement For Installation of DBs
Method Statement For Installation of DBs
3. Location of Activity
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
5. Operation
3. Installation:
6. Responsibilities
1. Project Manager
2. Site Engineer
3. Foreman
4. Safety Engineer
c. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
8. Materials Requirements
9. Equipments Requirement
The equipment that will be engaged for Installation of DBs, SMDBs and
MDBs works will be as follows:
1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
8. Crimping tool
13. Distribution
1. Project Manager
2. Site Engineer
3. Foremen
Inspection And Test Plan For Installation of DBs, SMDBs and MDBs
Testing
ITP Inspection Type of Verifying /
Reference Requirement/
Claus Descriptio Inspectio Control
Document Acceptance
e No n n Data Forms
Criteria
Design
drawings,
Review of
Design and Design All the Authorities
1 Document
Drawings Drawings Drawings Departments
s
Requirement
s.
Approved Should be as
Review of Drawing per the
Material Submittals
2 Document and approved
Approval Documents
s Specificati drawing and
on Specification
Properlocation
Check Visual, installation,
Switchgear Insulation termination etc Approved
Approved
installation Resistance Material should Drawing
3 Method
and cable and have minimum Method
Statement
termination Continuity status of – NO Statement
s. TestReport Objection with
comments
Visual,
Insulation
No obstructions
Request for Resistance
Approved Level, and it is Approved
4 inspection and
Drawing in proper Drawings
of works Continuity
position
Test
report.
Method Statement for Installation of GI
Conduits & Accessories
1. Purpose
2. Scope
3. Legislation and Code of Practice
4. Reference
5. Definitions
6. Resources
6.1. Equipment
6.2. Safety of Equipment’s
7. Safety Precautions
7.1. Construction Hazards
7.2. Personal Protective Equipment
7.3. Safety Training and Emergency procedures
7.4. First Aid
9.Construction Program
9.1 Housekeeping
9.3 Responsibilities
9.4 Records
10.Inspection and Testing
11.Related Forms
12.Attachments
1. Purpose
This document describes the methodology of Installation of GI conduits and accessories for
the project, and to ensure that all concerned persons are familiar with the sequence of
activities, utilization of resources, and execution of the works in compliance with applicable
Safety and Quality Procedures, and Project Documents and Specification.
This method statement is intended to outline the activities and the methods used for the
Installation of GI conduits and accessories. All activities will be carried out in accordance
with the contract details and in full compliance to the Contract Specifications and documents.
All work within the rights-of-way of the standards and specifications will be done in
compliance with requirements issued by authorities.
4. Reference
Contract Specifications
Approved Drawings
5. Definitions
6. Resources
NO DESCRIPTION
.
Bending machine
Die sets
Measuring tape
Screw driver
Chalk mate thread
Oil
Drill machine
Screw driver
Necessary measures will be taken for the safety of the equipment and any other works
affected by the works subject of this document. Relevant entities which might require
protection include any such works in the vicinity of the area of work or on the service access
or discharge path.
The construction team will ensure that any such requirements are documented.
The hazards identified above will be controlled under the overall Project Safety Plan which is
a separate document communicated to all parties on the project.
The works subject of this document requires that the PPE must be used as required.
Before commencing any works, all employees will attend a site safety induction training to
ensure all safety measures are understood and implemented and to cover specific procedures
in case of emergency. If necessary, practical training exercises will be conducted on escape
routes, signage, evacuation and rescue.
Prior to the commencement of work, arrangements will be made for medical facilities and
medical personnel to be available from prompt attention to the injured person. The
contractor’s vehicle assigned to the job site will be used for transporting the injured person to
the first aid station and to the nearest hospital when required.
8. Detailed Construction Sequence (Methodology)
8.1. Procedure
Architectural Drawing
1. Check the route of GI conduiting to make sure that it is free from debris
and obstruction of any other activity.
4. Identify the circuit start point and end points to mark the conduit route as
per approved drawings.
5. Make hole in wall/concrete using drill machine for rawal plug, fix rawal
plug inside hole and then fix base of saddle by screw every 2 meter span.
7. Install conduits and all accessories as per approved shop drawing and
tight with saddle and screw, make joints using threaded fittings.
14.Conduits are to be used for exposed installations over false ceilings when
the false ceiling is used as return plenum.
The risk assessment mentioning necessary control measures is attached to this method
statement to follow and implement the requirements
9. Construction Program
9.1 Housekeeping
The work area shall be maintained neat and tidy as reasonably practical at all times.
Executed works in areas were other works are still being carried out shall be protected as per
the contract requirements.
9.3 Responsibilities
9.4 Records
In accordance with the Quality Management System, the following records will be
maintained as documentary evidence of the establishment of this method statement:
12. Attachments
Risk Assessment
The below method statement describes some standard operating steps to install the
emergency lighting system for any kind of project the method statement can be modified as
per different project requirements. We have given this as a general guide and manufacturer
instruction and site specific specification should be followed while doing the installation of
emergency lighting.
1. Drill machine
2. Portable electric drill
3. Forklift
4. Step Ladder
5. Scaffolding Platform
6. Digital Multifunction tester
7. Spirit Level, Water tube & Plumb
8. Hammer
9. Hacksaw
10.Marker and Masking tape
Method Statement for installation of emergency lighting
3. Wherever the emergency lighting cable passes through walls, floors, floor
screeds, bricks walls etc a suitable sleeve shall be provided.
8. Install all safety luminaries to cover the specific hazards and to locate the
safety equipment installed. Intersections with other corridors, changes
level, staircases, fire alarm call points and operation equipment and other
life safety equipment will be done as shown in the approved shop
drawings.
9. All emergency lights having high frequency ballasts will have a built in or
separate monitoring facility as approved already and monitoring module
to be installed and addressed before fixing the luminaries.
10.All panels & equipment shall be connected and labelled as per approved
shop drawings & schematic diagrams.
11.Make sure that all metallic equipment, accessories & light fittings are
properly earthed.
16.