TERTIARY AND VOCATIONAL EDUCATION COMMISSION

COMMON WRITTEN EXAMINATION – 2018


Drafting Technology
NVQ Level 5 Semester ll Examination
Perform Investigation Pertaining to building Constructions -F45T003U08
Time: 03 hours Total Marks 100

Instructions to candidates (Please read carefully):

1. Answer any 5(Five) Questions.

2. Answers should be methodical and focused.

3. Return this Question paper together with your answer sheet.

4. All questions carry equal marks.

1. A Client want to start up a four story building for his office in Demaagoda. You are advised to
prepare a design brief for the above project. What are the details you will ask from the client to
prepare a design brief? (20
marks)

2. What are the components of a site investigation report and why do we need to have a site
investigation report before designing? (20 marks)

3. Calculate unit rate per 1 M2 of 1 brick thick wall in stretcher bond with1:6 cement mortar in ground
level.

1000 Bricks delivered to site at Rs.15, 000/- , add wastage 2 %,1 M3 Sand at Rs.18,000/- delivered to
site, add wastage 2% ,1 bag Cement (50 kg) 1000/- including delivery and unloading, add wastage 2%
,Density of Cement 1420 kg/M3, Shrinkage of Mortar 35%

Mixing

2 Unskilled labour mix 0.30m3

Wastage on Mortar 10%

2 skilled +1 unskilled labour will lay 120 bricks per hour.

Labour rate
TERTIARY AND VOCATIONAL EDUCATION COMMISSION
COMMON WRITTEN EXAMINATION – 2018
Skilled- 8 hour per day Rs. 2000/-(250/- per hour)

Unskilled- 8 hour per day Rs. 1500/-(187.5/- per hour)

Assume

60 bricks per 1M2 of wall. 0.01 M3 of mortar per 1M2 of wall. (20 Marks)

4. As a Consultant you have completed the designing of a house project at Colombo. Now the client
wants to get the building plan approved from local authority. Explain the approval procedure step by
step. (Plot coverage, FAR, and other important things and relevant documents should be indicate in
your answer.)

(20 Marks)

5. Write Short Note on following.


1. Anti-termite treatment
2. Methods of Water proofing
3. Tender document
4. Erection Activities at site (20 Marks)

6. A Client wants to design a house (1 story) with Green Building Concepts. Building area (Assume).Give
your plan view & front elevation with following requirements.
1. Car park
2. 2 Nos of toilet
3. 3 Bed rooms
4. Kitchen
5. Living area (20 Marks)