ANALISA SEPTICK TANK DAN PERESAPAN

A Bahan
4.000 bh Cincin Beton Ø 70 cm 95,000.00 380,000.00
1.000 bh Penutup Beton 60,000.00 60,000.00
57.082 kg Semen PC 1,120.00 63,931.91
0.380 m3 Kerikil 135,000.00 51,344.14
0.404 m3 Pasir Urug 100,000.00 40,404.00
0.077 m3 Pasir Beton 170,000.00 13,040.73
5.000 kg Ijuk 25,000.00 125,000.00
0.400 m Pipa PVC 2"(Pipa Hawa) 15,000.00 6,000.00
4.000 m Pipa PVC 3" (Pipa Peresapan) 25,000.00 100,000.00
2.000 bh Sambungan Pipa 5,000.00 10,000.00
3.000 bh Elbo 7,500.00 22,500.00
1.000 bh Dop 5,000.00 5,000.00
1.000 kg Lem Pipa 35,000.00 35,000.00
JUMLAH BAHAN 919,720.78
B Peralatan
0.15 hrg Alat Bantu 919,720.78 137,958.12
C Upah
0.5 hrg Upah Kerja 919,720.78 459,860.39

D Jumlah 1,517,539.29
E Overhead & Profit 10% 151,753.93
F Jumlah Total 1,669,293.22
Dibulatkan 1,669,000.00
DAFTAR HARGA BANGUNAN DAN UPAH KERJA KAB.PANGKEP
NO BAHAN / MATERIAL SATUAN JANUARI 2016 KET.
BAHAN PASANGAN
1 Batu Kali
- Utuh M3 Rp 128,000.00
- Batu Pecah 10-15 cm M3 Rp 184,000.00
- Batu Pecah 7-10 cm M3 Rp 215,000.00
- Batu Pecah 5-7 cm M3 Rp 242,000.00
- Batu Pecah 3-5 cm M3 Rp 265,000.00
- Batu Pecah 2-3 cm M3 Rp 300,000.00 Rp 214.29
- Batu Pecah 1-2 cm M3 Rp 300,000.00
- Batu Pecah 0,5-1 cm M3 Rp 400,000.00
2 Batu Gunung M3 Rp 125,000.00
3 Tanah Timbunan M3 Rp 50,000.00
Timbunan Pilihan M3 Rp 90,000.00
4 Pasir
- Pasir Urug M3 Rp 100,000.00
- Pasir Pasang M3 Rp 120,000.00
- Pasir Beton M3 Rp 170,000.00 Rp 121.43
5 Krikil
- Krikil Halus M3 Rp 125,000.00
- Krikil Kasar M3 Rp 135,000.00 Rp 100.00
6 Sirtu
- Sirtu disaring M3 Rp 95,000.00
- Sirtu tidak disaring M3 Rp 80,000.00
- Sirtu Royalti M3 Rp 35,000.00
7 Kapur Hidrasi M3 Rp 115,500.00
8 Semen
- Semen Putih Zak Rp 89,200.00
- Semen @ 50 kg Zak Rp 56,000.00 Rp 1,120.00
- Semen @ 40 kg Zak Rp 46,000.00 Rp 1,150.00
- Semen Warna kg Rp 10,000.00
9 Batu Merah Bj Rp 600.00
10 Paving Mar-Mar 20x10x3 cm Bj Rp 1,400.00
11 Paving Blok Beton Cetak Bj Rp 1,400.00
12 Pecahan Mar-mar M3 Rp 13,125.00
13 Roster Terawang Bh Rp 7,000.00
14 Ijuk Kg Rp 15,000.00
15 Air Kerja Ltr Rp 100.00

BAHAN KAYU
1 Kayu Kls I (Ulin)
- Balok Gergaji Sawmil M3 Rp 14,000,000.00
- Papan Gergaji Sawmil M3 Rp 16,000,000.00
2 Kayu Kls I (Bayam)
- Balok Gergaji Sawmil M3 Rp 10,000,000.00
- Papan Gergaji Sawmil M3 Rp 16,000,000.00
3 Kayu Kls I (Kumea)
- Balok Gergaji Sawmil M3 Rp 6,000,000.00
- Papan Gergaji Sawmil M3 Rp 6,500,000.00
4 Kayu Kls II
- Balok M3 Rp 4,500,000.00
- Papan M3 Rp 5,000,000.00
5 Kayu Kls III
- Balok M3 Rp 2,800,000.00
- Papan M3 Rp 2,800,000.00
- Bambu Btg Rp 20,000.00

BAHAN LANTAI
1 Tegel Keramik
- Putih 30 x 30 Dos Rp 51,000.00 Rp 4,636.36
- Warna 30 x30 cm Dos Rp 56,000.00
- Putih 40 x 40 cm Dos Rp 54,500.00 Rp 9,000.00
- Warna 40 x 40 Dos Rp 60,000.00
- Warna (bermotif) 20 x 25 cm Dos Rp 67,000.00 Rp 3,350.00
- Warna 20 x 25 cm Dos Rp 58,000.00 Rp 2,900.00
- Motif Batu Alam 20 x 40 Dos Rp 120,000.00 Rp 10,000.00
NO BAHAN / MATERIAL SATUAN JANUARI 2016 KET.

BAHAN KACA
1 Kaca Bening 3 mm M2 Rp 77,100.00
2 Kaca Bening 2 mm M2 Rp 55,100.00
3 Kaca bening 5 mm M2 Rp 115,000.00
4 Kaca Buram 3 mm M2 Rp 94,500.00
5 Kaca Buram 2 mm M2 Rp 78,700.00
6 Riben 3 mm M2 Rp 81,300.00
7 Riben 5 mm M2 Rp 97,100.00
8 Rangka nakop lengkap trali Set Rp 26,200.00

BAHAN LANGIT-LANGIT
1 Eternit 100 x 100 Lbr Rp 19,000.00
2 Tripleks
- 122 x 224 x 0.9 cm Lbr Rp 135,000.00
3 Gipsum Board
- 240 x 120 x 0.9 cm Lbr Rp 88,000.00
4 Tepung Gypsum Kg Rp 5,000.00
5 Calse Board 6 mm Lbr Rp 130,000.00
6 Calsiplank Lebar 20 cm - 4 m (Motif) M' Rp 17,000.00
7 Calsiplank Lebar 30 cm - 4 m (Motif) M' Rp 24,000.00
8 List Profil
- List profil 5 x 5 cm M' Rp 7,500.00
- List Profil Gypsum 8 cm M' Rp 15,000.00
11 Lem Kayu Kg Rp 13,000.00
BAHAN BESI
1 Besi Tulangan
- Besi Tulangan Polos Kg Rp 11,000.00
2 Kawat
- Kawat Beton Kg Rp 20,000.00
3 Paku
- Paku Biasa (5-10) cm Kg Rp 17,500.00
- Paku Biasa (1-4) cm Kg Rp 18,000.00
- Paku Asbes Kg Rp 35,000.00
- Paku Seng Kg Rp 23,000.00
- Paku Skrup 3 1/2" Kg Rp 18,000.00
- Paku Skrup 4 1/2" Kg Rp 55,000.00
- Paku Skrup Spandek bh Rp 500.00
- Paku Skrup Drailing bh Rp 750.00
- Paku Payung Berulir Kg Rp 15,000.00
- Paku 2 cm Dos Rp 33,000.00
- Paku Beton Dos Rp 12,000.00
- Paku Nyamuk M2 Rp 8,200.00
4 Besi Besi Hollow
- Hollow untuk Rangka Plafond 4 x 4 c m1 Rp 7,000.00
5 Baja Ringan Untuk Atap
- Canal C75. 0.75 m1 Rp 14,500.00
- Reng U m1 Rp 6,500.00
BAHAN ATAP
1 Atap Aluminium
- Atap Spandek Warna T=0,35 mm m1 Rp 60,000.00
- Nok Spandek Warna T=0,35 mm m1 Rp 57,500.00
2 Seng Plat Rp 20,000.00
NO BAHAN / MATERIAL SATUAN JANUARI 2016 KET.
BAHAN PENGGANTUNG
1 Kunci Pintu 2 Slaag
- Asahi ( besar ) bh Rp 125,000.00

2 Penggantung
- Hak Angin ( besar ) bh Rp 5,750.00
- Grendel Jendela bh Rp 7,500.00
- Grendel Tanam Pintu Ganda bh Rp 25,000.00
- Engsel Pintu bh Rp 20,000.00
- Engsel Jendela bh Rp 7,500.00
- Pegangan Pintu Ganda ( Door Holder ) bh Rp 100,000.00
- Door Closer bh Rp 350,000.00

BAHAN FINISHING CAT


1 Cat Tembok
- Avitex Kg Rp 20,000.00
- Metrolite Kg Rp 27,000.00
- Kimex Kg Rp 25,000.00
- Dulux Kg Rp 105,000.00
2 Cat Kayu
- Glotex Kg Rp 55,000.00
- Avian Kg Rp 55,000.00
- Platone Kg Rp 53,000.00
- ICI Kg Rp 40,000.00
- Vernis Ltr Rp 45,000.00
- Meni Kg Rp 40,000.00
- Minyak Cat Kg Rp 20,000.00
3 Cat Anti Bocor
- Aquaset Kg Rp 42,000.00
- Aquaprof Kg Rp 45,000.00
4 Cap Atap
- Mutiara Kg Rp 22,000.00
- AGA Kg Rp 150,000.00 Rp 37,500.00
- Plamur Kg Rp 7,000.00
- Amplas/Ketas Gosok M Rp 8,000.00
- Kuas Cat bh Rp 15,000.00
- Dempul Kg Rp 35,000.00
- Residu Ltr Rp 5,000.00
5 Minyak Bikisting Liter Rp 8,500.00

BAHAN INSTALASI LISTRIK


1 Pipa Union Untuk Kabel
-5/8-4m Btg Rp 9,000.00 Rp 2,250.00
2 Kabel Listrik
- Kabel NYM (3x2,5) mm m1 Rp 12,500.00
- Kabel NYM (2x2,5) mm m1 Rp 12,000.00
3 Lampu TL
- 1x18 w Bh Rp 40,000.00
- 1x14 w Bh Rp 30,000.00
4 Saklar Phase
- Tunggal Putih Bh Rp 25,000.00
- Tunggal Hitam Bh Rp 15,000.00
- Ganda Putih Bh Rp 27,000.00
- Ganda Hitam Bh Rp 25,000.00
5 Stok Kontak
- Hitam Bh Rp 20,000.00
- Putih Bh Rp 25,000.00
NO BAHAN / MATERIAL SATUAN JANUARI 2016 KET.
6 Skring Case Lokal Biasa
- Lokal 2 Grup Automatis Bh Rp 82,000.00
- Lokal 3 Grup Biasa Bh Rp 93,000.00
7 Fitting Bh Rp 17,000.00
8 Klem Kabel No. 10 Bh Rp 500.00
9 Kabel ITC (2x2x0,6) Bh Rp 14,000.00
10 Klem Kabel No. 12 Bh Rp 500.00
11 Inbow Dos Bh Rp 3,700.00
12 Las Dop Bh Rp 500.00
13 Isolasi Roll Rp 3,500.00
14 T-Doas 5/8" Bh Rp 200.00
15 Stop Kontak Telpon Bh Rp 45,400.00
16 Kontak Sambungan Bh Rp 6,400.00
17 MCB 10 A Bh Rp 50,000.00
UPAH KERJA
1 Mandor Hari Rp 80,000.00
2 Kepala Tukang Hari Rp 120,000.00
3 Tukang Hari Rp 90,000.00
4 Pekerja/Buruh Tak Terampil Hari Rp 65,000.00
5 Pekerja/BuruhTerampil Hari Rp 70,000.00
6 Mekanik Terampil Hari Rp 85,000.00
7 Mekanik TakTerampil Hari Rp 70,000.00
8 Operator Trampil Hari Rp 150,000.00
9 Operator Tak Trampil Hari Rp 100,000.00
10 Pembantu Operator Hari Rp 75,000.00
11 Sopir Truk Hari Rp 80,000.00
12 Pembantu Sopir Hari Rp 60,000.00
ANALISA HARGA SATUAN

A.2.2.1. HARGA SATUAN PEKERJAAN PERSIAPAN


A. 2.2.1.1 Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 70,000.00 28,000.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang Kayu L.03 OH 0.020 120,000.00 2,400.00
Mandor L.04 OH 0.020 80,000.00 1,600.00
JUMLAH TENAGA KERJA 50,000.00
B BAHAN
Dolken kayu φ 8-10/400 cm Btng 1.250 -
Semen Portland Kg 5.000 - -
Pasir beton m3 0.005 -
Koral beton m3 0.009 -
Kayu 5/7 m3 0.072 -
Paku biasa 2" - 5' Kg 0.060 -
Residu Liter 0.400 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,000.00


E Overhead & Profit 15% x D 15% 7,500.00
F Harga Satuan Pekerjaan (D+E) 57,500.00

A. 2.2.1.2 Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 -
Tukang Kayu L.02 OH 0.400 -
Kepala Tukang Kayu L.03 OH 0.020 -
Mandor L.04 OH 0.020 -
JUMLAH TENAGA KERJA -
B BAHAN
Dolken kayu φ 8-10/400 cm Btng 1.250 -
Semen Portland Kg 2.500 -
Seng gelombang Lbr 1.200 -
Pasir beton m3 0.005 -
Koral beton m3 0.009 -
Kayu 5/7 m3 0.072 -
Paku biasa 2" - 5' Kg 0.060 -
Meni besi Liter 0.450 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A. 2.2.1.3 Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1.8 meter

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 -
Tukang Kayu L.02 OH 0.300 -
Kepala Tukang Kayu L.03 OH 0.020 -
Mandor L.04 OH 0.020 -
JUMLAH TENAGA KERJA -
B BAHAN
Dolken kayu φ 8-10/400 cm Btng 1.000 -
Semen Portland Kg 2.000 -
Kawat duri m' 25.000 -
Pasir beton m3 0.005 -
Koral beton m3 0.009 -
Paku biasa 2" - 5' Kg 0.060 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A. 2.2.1.4 Pengukuran dan pemasangan 1 m' Bouwplank

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang Kayu L.03 OH 0.010 120,000.00 1,200.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 17,100.00
B BAHAN
Kayu balok 5/7, Kls. II m3 0.012 4,500,000.00 54,000.00
Paku 2"-3" Kg 0.020 15,000.00 300.00
Kayu papan 3/20, Kls. III m3 0.007 2,800,000.00 19,600.00
JUMLAH HARGA BAHAN 73,900.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 91,000.00


E Overhead & Profit 10% x D 10% 9,100.00
F Harga Satuan Pekerjaan (D+E) 100,100.00

A. 2.2.1.5 Pembuatan 1 m2 kantor sementara plesteran

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.000 -
Tukang Kayu L.02 OH 2.000 -
Tukang Kayu L.02 OH 1.000 -
Kepala Tukang Kayu L.03 OH 0.300 -
Mandor L.04 OH 0.050 -
JUMLAH TENAGA KERJA -
B BAHAN
Dolken kayu φ 8-10/400 cm Btng 1.250 -
Kayu m3 0.180 -
Paku biasa Kg 0.080 -
Besi strip Kg 1.100 -
Semen Portland Kg 35,000 -
Pasir pasang m3 0.150 -
Pasir beton m3 0.100 -
Koral beton m3 0.150 -
Bata merah Bh 30.000 -
Seng plat Lbr 0.250 -
Jendela naco Bh 0.200 -
Kaca polos m2 0.080 -
Kunci tanam Bh 0.150 -
Playwood 4mm Lbr 0.060 -
JUMLAH TENAGA KERJA -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -
A. 2.2.1.6 Pembuatan 1 m2 pagar sementara dari rumah jaga (konstruksi kayu)

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 -
Tukang Kayu L.02 OH 1.500 -
Kepala Tukang Kayu L.03 OH 0.150 -
Mandor L.04 OH 0.050 -
JUMLAH TENAGA KERJA -
B BAHAN
Dolken kayu φ 8-10/400 cm Btng 3.000 -
kayu m3 0.276 -
Paku biasa Kg 0.700 -
Seng gelombang Kg 1.500 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A. 2.2.1.7 Pembuatan 1 m2 gudang semen dan peralatan

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 -
Tukang Kayu L.02 OH 2.000 -
Kepala Tukang Kayu L.03 OH 0.200 -
Mandor L.04 OH 0.050 -
JUMLAH TENAGA KERJA -
B BAHAN
Dolken kayu φ 8-10/400 cm Btng 1.700 -
kayu m3 0.210 -
Paku biasa Kg 0.300 -
Semen Portland Kg 10.500 -
Pasir beton m3 0.030 -
Koral beton m3 0.050 -
Seng gelombang Lbr 1.500 -
Seng plat Lbr 0.250 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A. 2.2.1.8 Pembuatan 1 m2 bedeng pekerja

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 -
Tukang Kayu L.02 OH 2.000 -
Kepala Tukang Kayu L.03 OH 0.200 -
Mandor L.04 OH 0.050 -
JUMLAH TENAGA KERJA -
B BAHAN
Dolken kayu φ 8-10/400 cm Btng 1.250 -
kayu m3 0.186 -
Paku biasa Kg 0.300 -
Semen Portland Kg 18.000 -
Pasir beton m3 0.030 -
Koral beton m3 0.050 -
Seng gelombang Lbr 1.500 -
Playwood 4 mm Lbr 1.350 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A. 2.2.1.9 Pembersihan 1 m2 lapangan dan perataan

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 -
Mandor L.04 OH 0.050 -
JUMLAH TENAGA KERJA -
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A. 2.2.1.10 Pembuatan 1 m2 steger/ perancah dari bambu

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 -
Tukang Kayu L.02 OH 2.000 -
Kepala Tukang Kayu L.03 OH 0.200 -
Mandor L.04 OH 0.050 -
JUMLAH TENAGA KERJA -
B BAHAN
Bambu φ 6-8/600 cm Btng 1.250 -
Tali ijuk m3 0.186 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A. 2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40cmx50cmx25cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Tukang Kayu L.02 OH 0.300 -
Kepala Tukang Kayu L.03 OH 0.030 -
JUMLAH TENAGA KERJA -
B BAHAN
Kayu papan kelas III m3 1.250 -
Kayu balok 5/7 kelas III m3 0.186 -
Paku biasa Kg 0.300 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A. 2.2.1.12 Pembuatan 1 m2 jalan sementara

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 -
Mandor L.04 OH 0.005 -
JUMLAH TENAGA KERJA -
B BAHAN
Batu belah m3 0.150 -
Batu pecah m3 0.090 -
Pasir pasang m3 0.010 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A. 2.2.1.13 Pembongkaran 1 m3 beton bertulang

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 13.334 70,000.00 933,380.00
Mandor L.04 OH 0.666 80,000.00 53,280.00
JUMLAH TENAGA KERJA 986,660.00
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 986,660.00


E Overhead & Profit 10% x D 10% 98,666.00
F Harga Satuan Pekerjaan (D+E) 1,085,326.00

A. 2.2.1.14 Pembongkaran 1 m3 dinding tembok bata

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.667 65,000.00 433,355.00
Mandor L.04 OH 0.333 80,000.00 26,640.00
JUMLAH TENAGA KERJA 459,995.00
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 459,995.00


E Overhead & Profit 10% x D 10% 45,999.50
F Harga Satuan Pekerjaan (D+E) 505,994.50

A. 2.2.1.15 Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.042 -
Tukang Kayu L.02 OH 0.004
Kepala Tukang Kayu L.03 OH 0.002
Mandor L.04 OH 0.042 -
JUMLAH TENAGA KERJA -
B BAHAN
Kawat jaring m3 0.143 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A. 2.2.1.16 Pembuatan 1 m2 panel beton pracetak 5x50x213 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.375 -
Tukang Kayu L.02 OH 0.125 -
Kepala Tukang Kayu L.03 OH 0.012 -
Mandor L.04 OH 0.019 -
JUMLAH TENAGA KERJA -
B BAHAN
Panel beton pracetak Lbr 0.986 -
Kolom beton pracetak Btng 0.525 -
Semen PC Kg 45.000 -
Pasir beton m3 0.074 -
Koral m3 0.146 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
ANALISA HARGA SATUAN

A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.1 Pemasangan 1 buah closet duduk/ monoblock'

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.300 76,000.00 250,800.00
Tukang batu L.02 OH 1.100 90,000.00 99,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.1600 80,000.00 12,800.00
JUMLAH TENAGA KERJA 363,600.00
B BAHAN
Closet duduk Unit 1.000 0 -
Perlengkapan Ls 0.060 0 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 363,600.00


E Overhead & Profit 10% x D 10% 36,360.00
F Harga Satuan Pekerjaan (D+E) 399,960.00

A.5.1.1.2 Pemasangan 1 buah closet jongkok porslen

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 70,000.00 70,000.00
Tukang batu L.02 OH 1.500 90,000.00 135,000.00
Kepala Tukang L.03 OH 0.150 120,000.00 18,000.00
Mandor L.04 OH 0.1600 80,000.00 12,800.00
JUMLAH TENAGA KERJA 235,800.00
B BAHAN
Closet jongkok Unit 1.000 110,000.00 110,000.00
Semen portland Kg 6.000 1,120.00 6,720.00
Pasir pasang m3 0.010 120,000.00 1,200.00
JUMLAH HARGA BAHAN 117,920.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 353,720.00


E Overhead & Profit 10% x D 10% 35,372.00
F Harga Satuan Pekerjaan (D+E) 389,092.00
A.5.1.1.3 Pemasangan 1 buah closet jongkok teraso

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 70,000.00 70,000.00
Tukang batu L.02 OH 1.500 90,000.00 135,000.00
Kepala Tukang L.03 OH 0.150 120,000.00 18,000.00
Mandor L.04 OH 0.050 80,000.00 4,000.00
JUMLAH TENAGA KERJA 227,000.00
B BAHAN
Closet jongkok Unit 1.000 110,000.00 110,000.00
Semen portland Kg 6.000 1,120.00 6,720.00
Pasir pasang m3 0.010 120,000.00 1,200.00
Bata merah Bh 7.000 600.00 4,200.00
JUMLAH HARGA BAHAN 122,120.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 349,120.00


E Overhead & Profit 10% x D 10% 34,912.00
F Harga Satuan Pekerjaan (D+E) 384,032.00

A.5.1.1.4 Pemasangan 1 buah urinoir

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 -
Tukang batu L.02 OH 1.000 -
Kepala Tukang L.03 OH 0.100 -
Mandor L.04 OH 0.050 -
JUMLAH TENAGA KERJA -
B BAHAN
Urinoir Unit 1.000 -
Semen portland Kg 6.000 -
Pasir pasang m3 0.010 -
Perlengkapan % 30.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.5 Pemasangan 1 buah wastafel

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.200 -
Tukang batu L.02 OH 1.450 -
Kepala Tukang L.03 OH 0.150 -
Mandor L.04 OH 0.060 -
JUMLAH TENAGA KERJA -
B BAHAN
Wastafel Unit 1.200 -
Semen portland Kg 6.000 -
Pasir pasang m3 0.010 -
Perlengkapan % 12.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A.5.1.1.6 Pemasangan 1 buah bathcuip porselen

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.075 -
Tukang batu L.02 OH 0.750 -
Kepala Tukang L.03 OH 0.075 -
Mandor L.04 OH 0.003 -
JUMLAH TENAGA KERJA -
B BAHAN
Bathcuip Unit 1.000 -
Perlengkapan % 20.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.7 Pemasangan 1 buah bak fibreglass vol 1 m3

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.000 -
Tukang batu L.02 OH 4.500 -
Kepala Tukang L.03 OH 0.050 -
Mandor L.04 OH 0.900 -
JUMLAH TENAGA KERJA -
B BAHAN
Bak fibreglass Unit 1.000 -
Perlengkapan Ls 0.120 0 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.8 Pemasangan 1 buah bak mandi batu bata vol 0.30 m3

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.000 -
Tukang batu L.02 OH 3.000 -
Kepala Tukang L.03 OH 0.300 -
Mandor L.04 OH 0.030 -
JUMLAH TENAGA KERJA -
B BAHAN
Bata merah Bh 150.000 -
Semen portland Kg 120.000 -
Pasir pasang m3 0.300 -
Porselen 11x11 bh 360.000 -
Semen warna kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.9 Pemasangan 1 buah bak mandi teraso vol 0.30 m3

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.000 -
Tukang batu L.02 OH 4.500 -
Kepala Tukang L.03 OH 0.050 -
Mandor L.04 OH 0.900 -
JUMLAH TENAGA KERJA -
B BAHAN
Bak fibreglass Unit 1.000 -
Perlengkapan Ls 0.120 0 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.10 Pemasangan 1 buah bak air fibreglass vol 1 m3

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 -
Tukang batu L.02 OH 0.450 -
Kepala Tukang L.03 OH 0.045 -
Mandor L.04 OH 0.015 -
JUMLAH TENAGA KERJA -
B BAHAN
Bak fibreglass Unit 1.000 -
Perlengkapan Ls 0.120 0 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.11 Pemasangan 1 buah bak beton vol 1 m3

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.500 -
Tukang batu L.02 OH 4.500 -
Kepala Tukang L.03 OH 0.050 -
Mandor L.04 OH 0.018 -
JUMLAH TENAGA KERJA -
B BAHAN
Beton 1:2:3 m3 0.900 -
Baja tulangan Kg 180.000 -
Kayu bekisting m2 8.000 -
Ubin porselen bh 500.000 -
Perlengkapan % 10.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A.5.1.1.12 Pemasangan 1 buah bak cuci piring stainlessteel

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.030 -
Tukang batu L.02 OH 0.300 -
Kepala Tukang L.03 OH 0.030 -
Mandor L.04 OH 0.015 -
JUMLAH TENAGA KERJA -
B BAHAN
Bak cuci piring Unit 1.000 -
Waterdrain Bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.13 Pemasangan 1 buah bak cuci piring teraso

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 -
Tukang batu L.02 OH 0.500 -
Kepala Tukang L.03 OH 0.050 -
Mandor L.04 OH 0.025 -
JUMLAH TENAGA KERJA -
B BAHAN
Bak cuci piring Unit 1.000 -
Waterdrain Bh 1.000 -
Semen portland Kg 20.000 -
Pasir pasang m3 0.050 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A.5.1.1.14 Pemasangan 1 buah floor drain

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.010 70,000.00 700.00
Tukang batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 120,000.00 1,200.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 11,300.00
B BAHAN
Floor drain Unit 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,300.00


E Overhead & Profit 15% x D 15% 5,445.00
F Harga Satuan Pekerjaan (D+E) 41,745.00

A.5.1.1.15 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.160 -
Tukang batu L.02 OH 0.720 -
Kepala Tukang L.03 OH 0.072 -
Mandor L.04 OH 0.011 -
JUMLAH TENAGA KERJA -
B BAHAN
Bata merah Bh 40.000 -
Sement portland Kg 44.000
Pasir pasang m3 0.070
Pasir beton m3 0.060 -
Kerikil m3 0.070
Baja tulangan Kg 1.600 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A.5.1.1.16 Pemasangan 1 buah bak kontrol pasangan bata 45x45 tinggi 50 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.200 -
Tukang batu L.02 OH 1.150 -
Kepala Tukang L.03 OH 0.011 -
Mandor L.04 OH 0.016 -
JUMLAH TENAGA KERJA -
B BAHAN
Bata merah Bh 70.000 -
Sement portland Kg 77.000
Pasir pasang m3 0.130
Pasir beton m3 0.090 -
Kerikil m3 0.020
Baja tulangan Kg 2.600 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.17 Pemasangan 1 buah bak kontrol pasangan bata 60x60 tinggi 65 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.200 -
Tukang batu L.02 OH 1.150 -
Kepala Tukang L.03 OH 0.011 -
Mandor L.04 OH 0.016 -
JUMLAH TENAGA KERJA -
B BAHAN
Bata merah Bh 123.000 -
Sement portland Kg 114.000
Pasir pasang m3 0.184
Pasir beton m3 0.120 -
Kerikil m3 0.033
Baja tulangan Kg 4.850 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.18 Pemasangan 1 m' pipa galvanis diameter ½"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 70,000.00 3,780.00
Tukang batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.009 120,000.00 1,080.00
Mandor L.04 OH 0.027 80,000.00 2,160.00
JUMLAH TENAGA KERJA 15,120.00
B BAHAN
Pipa galvanis ½" m' 1.200 26,500.00 31,800.00
Perlengkapan Ls 0.350 9,275.00 3,246.25
JUMLAH HARGA BAHAN 35,046.25
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,166.25


E Overhead & Profit 15% x D 15% 7,524.94
F Harga Satuan Pekerjaan (D+E) 57,691.19
A.5.1.1.19 Pemasangan 1 buah kran diameter ½" atau ¾"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.010 70,000.00 700.00
Tukang batu L.02 OH 0.400 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.040 120,000.00 4,800.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 41,900.00
B BAHAN
Kran air Bh 1.000 12,500.00 12,500.00
Sealtape Bh 0.025 3,000.00 75.00
JULAH HARGA BAHAN 12,575.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 54,475.00


E Overhead & Profit 10% x D 10% 5,447.50
F Harga Satuan Pekerjaan (D+E) 59,922.50

A.5.1.1.20 Pemasangan 1 m' pipa galvanis diameter ¾"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 76,000.00 4,104.00
Tukang batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.009 100,000.00 900.00
Mandor L.04 OH 0.027 80,000.00 2,160.00
JUMLAH TENAGA KERJA 15,264.00
B BAHAN
Pipa galvanis ¾" m' 1.200 29,333.33 35,200.00
Perlengkapan Ls 0.350 10,266.67 3,593.33
JUMLAH HARGA BAHAN 38,793.33
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 54,057.33


E Overhead & Profit 15% x D 15% 8,108.60
F Harga Satuan Pekerjaan (D+E) 62,165.93

A.5.1.1.21 Pemasangan 1 m' pipa galvanis diameter 1"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 70,000.00 3,780.00
Tukang batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.009 120,000.00 1,080.00
Mandor L.04 OH 0.027 80,000.00 2,160.00
JUMLAH TENAGA KERJA 15,120.00
B BAHAN
Pipa galvanis 1" m' 1.200 39,333.33 47,200.00
Perlengkapan Ls 0.350 13,766.67 4,818.33
JUMLAH HARGA BAHAN 52,018.33
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 67,138.33


E Overhead & Profit 15% x D 15% 10,070.75
F Harga Satuan Pekerjaan (D+E) 77,209.08
A.5.1.1.22 Pemasangan 1 m' pipa galvanis diameter 1½"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 76,000.00 8,208.00
Tukang batu L.02 OH 0.180 90,000.00 16,200.00
Kepala Tukang L.03 OH 0.018 100,000.00 1,800.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 26,608.00
B BAHAN
Pipa galvanis 1½" m' 1.200 -
Perlengkapan Ls 0.350 - -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,608.00


E Overhead & Profit 15% x D 15% 3,991.20
F Harga Satuan Pekerjaan (D+E) 30,599.20

A.5.1.1.23 Pemasangan 1 m' pipa galvanis diameter 3"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 76,000.00 10,260.00
Tukang batu L.02 OH 0.225 90,000.00 20,250.00
Kepala Tukang L.03 OH 0.023 100,000.00 2,250.00
Mandor L.04 OH 0.007 80,000.00 560.00
JUMLAH TENAGA KERJA 33,320.00
B BAHAN
Pipa galvanis 3" m' 1.200 -
Perlengkapan Ls 0.350 - -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,320.00


E Overhead & Profit 15% x D 15% 4,998.00
F Harga Satuan Pekerjaan (D+E) 38,318.00

A.5.1.1.24 Pemasangan 1 m' pipa galvanis diameter 4"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 76,000.00 10,260.00
Tukang batu L.02 OH 0.225 90,000.00 20,250.00
Kepala Tukang L.03 OH 0.023 100,000.00 2,250.00
Mandor L.04 OH 0.007 80,000.00 560.00
JUMLAH TENAGA KERJA 33,320.00
B BAHAN
Pipa galvanis 4" m' 1.200 -
Perlengkapan Ls 0.350 - -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,320.00


E Overhead & Profit 15% x D 15% 4,998.00
F Harga Satuan Pekerjaan (D+E) 38,318.00
A.5.1.1.25 Pemasangan 1 m' pipa PVC tipe AW diameter ½"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 70,000.00 2,520.00
Tukang batu L.02 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.006 120,000.00 720.00
Mandor L.04 OH 0.002 80,000.00 160.00
JUMLAH TENAGA KERJA 8,800.00
B BAHAN
Pipa PVC tipe AW diameter ½" m' 1.200 4,125.00 4,950.00
Perlengkapan Ls 0.350 1,443.75 505.31
JUMLAH HARGA BAHAN 5,455.31
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 14,255.31


E Overhead & Profit 10% x D 10% 1,425.53
F Harga Satuan Pekerjaan (D+E) 15,680.84

A.5.1.1.26 Pemasangan 1 m' pipa PVC tipe AW diameter ¾"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 70,000.00 2,520.00
Tukang batu L.02 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.006 120,000.00 720.00
Mandor L.04 OH 0.002 80,000.00 160.00
JUMLAH TENAGA KERJA 8,800.00
B BAHAN
Pipa PVC tipe AW diameter ¾" m' 1.200 5,375.00 6,450.00
Perlengkapan Ls 0.350 1,881.25 658.44
JUMLAH HARGA BAHAN 7,108.44
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,908.44


E Overhead & Profit 15% x D 15% 2,386.27
F Harga Satuan Pekerjaan (D+E) 18,294.70

A.5.1.1.27 Pemasangan 1 m' pipa PVC tipe AW diameter 1"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 70,000.00 2,520.00
Tukang batu L.02 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.006 120,000.00 720.00
Mandor L.04 OH 0.002 80,000.00 160.00
JUMLAH TENAGA KERJA 8,800.00
B BAHAN
Pipa PVC tipe AW diameter 1" m' 1.200 7,500.00 9,000.00
Perlengkapan Ls 0.350 2,625.00 918.75
JUMLAH HARGA BAHAN 9,918.75
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 18,718.75


E Overhead & Profit 15% x D 15% 2,807.81
F Harga Satuan Pekerjaan (D+E) 21,526.56
A.5.1.1.28 Pemasangan 1 m' pipa PVC tipe AW diameter 1½"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 70,000.00 3,780.00
Tukang batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.009 120,000.00 1,080.00
Mandor L.04 OH 0.003 80,000.00 240.00
JUMLAH TENAGA KERJA 13,200.00
B BAHAN
Pipa PVC tipe AW diameter 1½" m' 1.200 10,000.00 12,000.00
Perlengkapan Ls 0.350 3,500.00 1,225.00
JUMLAH HARGA BAHAN 13,225.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,425.00


E Overhead & Profit 15% x D 15% 3,963.75
F Harga Satuan Pekerjaan (D+E) 30,388.75

A.5.1.1.29 Pemasangan 1 m' pipa PVC tipe AW diameter 2"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 70,000.00 3,780.00
Tukang batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.009 120,000.00 1,080.00
Mandor L.04 OH 0.003 80,000.00 240.00
JUMLAH TENAGA KERJA 13,200.00
B BAHAN
Pipa PVC tipe AW diameter 2" m' 1.200 15,000.00 18,000.00
Perlengkapan Ls 0.350 5,250.00 1,837.50
JUMLAH HARGA BAHAN 19,837.50
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,037.50


E Overhead & Profit 15% x D 15% 4,955.63
F Harga Satuan Pekerjaan (D+E) 37,993.13

A.5.1.1.30 Pemasangan 1 m' pipa PVC tipe AW diameter 2½"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 70,000.00 5,670.00
Tukang batu L.02 OH 0.135 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.014 120,000.00 1,620.00
Mandor L.04 OH 0.004 80,000.00 320.00
JUMLAH TENAGA KERJA 19,760.00
B BAHAN
Pipa PVC tipe AW diameter 2½" m' 1.200 20,000.00 24,000.00
Perlengkapan Ls 0.350 7,000.00 2,450.00
JUMLAH HARGA BAHAN 26,450.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 46,210.00


E Overhead & Profit 15% x D 15% 6,931.50
F Harga Satuan Pekerjaan (D+E) 53,141.50
A.5.1.1.31 Pemasangan 1 m' pipa PVC tipe AW diameter 3"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 70,000.00 5,670.00
Tukang batu L.02 OH 0.135 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.014 120,000.00 1,620.00
Mandor L.04 OH 0.004 80,000.00 320.00
JUMLAH TENAGA KERJA 19,760.00
B BAHAN
Pipa PVC tipe AW diameter 3" m' 1.200 25,000.00 30,000.00
Perlengkapan Ls 0.350 8,750.00 3,062.50
JUMLAH HARGA BAHAN 33,062.50
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 52,822.50


E Overhead & Profit 10% x D 10% 5,282.25
F Harga Satuan Pekerjaan (D+E) 58,104.75

A.5.1.1.32 Pemasangan 1 m' pipa PVC tipe AW diameter 4"

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 70,000.00 5,670.00
Tukang batu L.02 OH 0.135 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.014 120,000.00 1,620.00
Mandor L.04 OH 0.004 80,000.00 320.00
JUMLAH TENAGA KERJA 19,760.00
B BAHAN
Pipa PVC tipe AW diameter 4" m' 1.200 45,000.00 54,000.00
Perlengkapan Ls 0.350 15,750.00 5,512.50
JUMLAH HARGA BAHAN 59,512.50
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 79,272.50


E Overhead & Profit 15% x D 15% 11,890.88
F Harga Satuan Pekerjaan (D+E) 91,163.38

A.5.1.1.33 Pemasangan 1 m' pipa air limbah jenis pipa tanah Ø 20 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 -
Tukang batu L.02 OH 0.040 -
Kepala Tukang L.03 OH 0.004 -
Mandor L.04 OH 0.004 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa tanah m' 1.600 -
Semen portland kg 35.000 -
Pasir pasang m3 0.014 -
Pasir urug m3 0.014 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A.5.1.1.34 Pemasangan 1 m' pipa air limbah jenis pipa tanah Ø 15 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.060 -
Tukang batu L.02 OH 0.030 -
Kepala Tukang L.03 OH 0.003 -
Mandor L.04 OH 0.003 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa tanah m' 1.600 -
Semen portland kg 0.680 -
Pasir pasang m3 0.013 -
Pasir urug m3 0.011 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.35 Pemasangan 1 m' pipa beton Ø 15 - 20 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 -
Tukang batu L.02 OH 0.070 -
Kepala Tukang L.03 OH 0.007 -
Mandor L.04 OH 0.007 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa tanah Ø 15 - 20 cm m' 1.100 -
Bata merah m3 0.027 -
Semen portland kg 3.920 -
Pasir pasang m3 0.056 -
Pasir urug m3 0.024 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.36 Pemasangan 1 m' pipa beton Ø 30 - 100 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.380 -
Tukang batu L.02 OH 0.190 -
Kepala Tukang L.03 OH 0.019 -
Mandor L.04 OH 0.019 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa tanah Ø 30 - 100 cm m' 1.100 -
Bata merah m3 0.550 -
Semen portland kg 10.300 -
Pasir pasang m3 0.061 -
Pasir urug m3 0.069 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.5.1.1.36 Pemasangan 1 m' pipa beton Ø 30 - 100 cm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.380 -
Tukang batu L.02 OH 0.190 -
Kepala Tukang L.03 OH 0.019 -
Mandor L.04 OH 0.019 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa tanah Ø 30 - 100 cm m' 1.100 -
Bata merah m3 0.550 -
Semen portland kg 10.300 -
Pasir pasang m3 0.061 -
Pasir urug m3 0.069 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
ANALISA HARGA SATUAN

A.8.4.3. HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA

A.8.4.3.1 Pemasangan 1 buah valve Ø 150 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.429 -
Tukang pipa L.02 OH 0.715 -
Mandor L.04 OH 0.1430 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 150 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.100 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.2 Pemasangan 1 buah valve Ø 200 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.714 -
Tukang pipa L.02 OH 0.857 -
Mandor L.04 OH 0.171 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 200 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.300 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.3 Pemasangan 1 buah valve Ø 250 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.714 -
Tukang pipa L.02 OH 0.857 -
Mandor L.04 OH 0.171 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 250 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.400 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.4 Pemasangan 1 buah valve Ø 300 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.000 -
Tukang pipa L.02 OH 1.000 -
Mandor L.04 OH 0.200 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 300 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.500 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.5 Pemasangan 1 buah valve Ø 400 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.429 -
Tukang pipa L.02 OH 1.715 -
Mandor L.04 OH 0.343 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 400 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 1.000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.6 Pemasangan 1 buah valve Ø 450 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.429 -
Tukang pipa L.02 OH 1.715 -
Mandor L.04 OH 0.343 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 450 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 1.000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A.8.4.3.7 Pemasangan 1 buah valve Ø 500 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.000 -
Tukang pipa L.02 OH 2.000 -
Mandor L.04 OH 0.400 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 500 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 1.000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.8 Pemasangan 1 buah valve Ø 600 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.421 -
Tukang pipa L.02 OH 0.711 -
Mandor L.04 OH 0.142 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 600 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.600 -
Mobil crane =< 3 ton hari 0.300 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.9 Pemasangan 1 buah valve Ø 700 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.429 -
Tukang pipa L.02 OH 0.715 -
Mandor L.04 OH 0.143 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 700 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.500 -
Mobil crane =< 3 ton hari 0.500 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -
A.8.4.3.10 Pemasangan 1 buah valve Ø 800 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.786 -
Tukang pipa L.02 OH 0.893 -
Mandor L.04 OH 0.179 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 800 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.500 -
Mobil crane =< 3 ton hari 0.500 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.11 Pemasangan 1 buah valve Ø 900 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.714 -
Tukang pipa L.02 OH 0.857 -
Mandor L.04 OH 0.171 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 900 mm bh 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.750 -
Mobil crane =< 3 ton hari 0.750 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 15% x D 15% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.12 Pemasangan 1 buah valve Ø 1000 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.571 -
Tukang pipa L.02 OH 1.286 -
Mandor L.04 OH 0.257 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 1000 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 1.000 -
Mobil crane =< 3 ton hari 1.000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -
A.8.4.3.13 Pemasangan 1 buah valve Ø 1100 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.000 -
Tukang pipa L.02 OH 1.500 -
Mandor L.04 OH 0.300 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 1100 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 1.000 -
Mobil crane =< 3 ton hari 1.000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.14 Pemasangan 1 buah valve Ø 1200 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.000 -
Tukang pipa L.02 OH 1.500 -
Mandor L.04 OH 0.300 -
JUMLAH TENAGA KERJA -
B BAHAN
Valve Ø 1200 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 1.000 -
Mobil crane =< 3 ton hari 1.000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.15 Pemasangan 1 buah Tee Ø 150 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 -
Tukang pipa L.02 OH 0.053 -
Mandor L.04 OH 0.011 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 150 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.028 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -
A.8.4.3.16 Pemasangan 1 buah Tee Ø 200 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.216 -
Tukang pipa L.02 OH 0.108 -
Mandor L.04 OH 0.022 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 200 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.029 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.17 Pemasangan 1 buah Tee Ø 250 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.326 -
Tukang pipa L.02 OH 0.163 -
Mandor L.04 OH 0.033 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 250 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.039 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.18 Pemasangan 1 buah Tee Ø 300 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.436 -
Tukang pipa L.02 OH 0.218 -
Mandor L.04 OH 0.044 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 300 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.500 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.19 Pemasangan 1 buah Tee Ø 400 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.656 -
Tukang pipa L.02 OH 0.328 -
Mandor L.04 OH 0.066 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 400 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.500 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.20 Pemasangan 1 buah Tee Ø 450 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.766 -
Tukang pipa L.02 OH 0.383 -
Mandor L.04 OH 0.077 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 450 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.500 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.21 Pemasangan 1 buah Tee Ø 500 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.876 -
Tukang pipa L.02 OH 0.438 -
Mandor L.04 OH 0.088 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 500 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.600 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.22 Pemasangan 1 buah Tee Ø 600 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.096 -
Tukang pipa L.02 OH 0.548 -
Mandor L.04 OH 0.110 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 600 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.193 -
Mobile crane =< 3 ton hari 0.096 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.23 Pemasangan 1 buah Tee Ø 700 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.316 -
Tukang pipa L.02 OH 0.658 -
Mandor L.04 OH 0.132 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 700 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.225 -
Mobile crane =< 3 ton hari 0.113 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.24 Pemasangan 1 buah Tee Ø 800 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.536 -
Tukang pipa L.02 OH 0.768 -
Mandor L.04 OH 0.154 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 800 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.257 -
Mobile crane =< 3 ton hari 0.129 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.25 Pemasangan 1 buah Tee Ø 900 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.756 -
Tukang pipa L.02 OH 0.878 -
Mandor L.04 OH 0.176 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 900 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.321 -
Mobile crane =< 3 ton hari 0.161 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.26 Pemasangan 1 buah Tee Ø 1000 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.976 -
Tukang pipa L.02 OH 0.988 -
Mandor L.04 OH 0.198 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 1000 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.366 -
Mobile crane =< 3 ton hari 0.183 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.27 Pemasangan 1 buah Tee Ø 1100 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.196 -
Tukang pipa L.02 OH 1.098 -
Mandor L.04 OH 0.220 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 1100 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.386 -
Mobile crane =< 3 ton hari 0.193 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.3.28 Pemasangan 1 buah Tee Ø 1200 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.416 -
Tukang pipa L.02 OH 1.208 -
Mandor L.04 OH 0.242 -
JUMLAH TENAGA KERJA -
B BAHAN
Tee Ø 1200 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Sewa tripot/Tackel dan handle crabe 2T hari 0.450 -
Mobile crane =< 3 ton hari 0.225 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4. HARGA SATUAN PEKERJAAN PENYAMBUNGAN PIPA BAARU KE PIPA LAMA

A.8.4.4.1 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 80 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.466 -
Tukang pipa L.02 OH 0.733 -
Mandor L.04 OH 0.1470 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 80 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 0.606 -
Sewa genset 1500 watt hari 0.075 -
Sewa pompa submersible 3m3/h hari 0.968 -
Sewa tripot/Tackel dan handle crabe 2T hari 0.865 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.2 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 100 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.646 -
Tukang pipa L.02 OH 0.823 -
Mandor L.04 OH 0.1650 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 100 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 0.650 -
Sewa genset 1500 watt hari 0.159 -
Sewa pompa submersible 3m3/h hari 1.078 -
Sewa tripot/Tackel dan handle crabe 2T hari 0.911 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -
A.8.4.4.3 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 150 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.096 -
Tukang pipa L.02 OH 1.048 -
Mandor L.04 OH 0.2100 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 150 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 0.760 -
Sewa genset 1500 watt hari 0.369 -
Sewa pompa submersible 3m3/h hari 1.353 -
Sewa tripot/Tackel dan handle crabe 2T hari 1.026 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.4 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 200 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.546 -
Tukang pipa L.02 OH 1.273 -
Mandor L.04 OH 0.255 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 200 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 0.870 -
Sewa genset 1500 watt hari 0.579 -
Sewa pompa submersible 3m3/h hari 1.628 -
Sewa tripot/Tackel dan handle crabe 2T hari 1.141 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.5 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 250 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.996 -
Tukang pipa L.02 OH 1.498 -
Mandor L.04 OH 0.300 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 250 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 0.980 -
Sewa genset 1500 watt hari 0.789 -
Sewa pompa submersible 3m3/h hari 1.903 -
Sewa tripot/Tackel dan handle crabe 2T hari 1.256 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.6 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 300 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.446 -
Tukang pipa L.02 OH 1.723 -
Mandor L.04 OH 0.345 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 300 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 1.090 -
Sewa genset 1500 watt hari 0.999 -
Sewa pompa submersible 3m3/h hari 2.178 -
Sewa tripot/Tackel dan handle crabe 2T hari 1.371 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.7 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 400 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.356 -
Tukang pipa L.02 OH 2.173 -
Mandor L.04 OH 0.435 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 400 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 1.310 -
Sewa genset 1500 watt hari 1.419 -
Sewa pompa submersible 3m3/h hari 2.728 -
Sewa tripot/Tackel dan handle crabe 2T hari 1.601 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.8 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 450 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.796 -
Tukang pipa L.02 OH 2.398 -
Mandor L.04 OH 0.480 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 450 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 1.420 -
Sewa genset 1500 watt hari 1.629 -
Sewa pompa submersible 3m3/h hari 3.003 -
Sewa tripot/Tackel dan handle crabe 2T hari 1.716 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.9 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 500 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 5.246 -
Tukang pipa L.02 OH 2.623 -
Mandor L.04 OH 0.525 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 500 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 1.530 -
Sewa genset 1500 watt hari 1.839 -
Sewa pompa submersible 3m3/h hari 3.278 -
Sewa tripot/Tackel dan handle crabe 2T hari 1.831 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.10 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 600 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.146 -
Tukang pipa L.02 OH 3.037 -
Mandor L.04 OH 0.615 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 600 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 1.750 -
Sewa genset 1500 watt hari 2.259 -
Sewa pompa submersible 3m3/h hari 3.828 -
Sewa tripot/Tackel dan handle crabe 2T hari 2.061 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.11 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 700 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.046 -
Tukang pipa L.02 OH 3.523 -
Mandor L.04 OH 0.705 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 700 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 1.970 -
Sewa genset 1500 watt hari 2.679 -
Sewa pompa submersible 3m3/h hari 4.378 -
Sewa tripot/Tackel dan handle crabe 2T hari 2.291 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -

A.8.4.4.12 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 800 mm

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.946 -
Tukang pipa L.02 OH 3.973 -
Mandor L.04 OH 0.795 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa Ø 800 mm bh 1.000 -
JUMLAH TENAGA KERJA -
C PERALATAN
Peralatan potong pipa T2/mekanik/cilinder saw hari 2.190 -
Sewa genset 1500 watt hari 3.099 -
Sewa pompa submersible 3m3/h hari 4.928 -
Sewa tripot/Tackel dan handle crabe 2T hari 2.521 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 10% x D 10% -
F Harga Satuan Pekerjaan (D+E) -