Republic of the Philippines

CAMARINES SUR POLYTECHNIC COLLEGES


Nabua, Camarines Sur

COLLEGE OF ENGINEERING
Bachelor of Science in Civil Engineering

COMPUTATION OF DEAD LOAD

Structural Elements Dead Loads


Roof
Slab
- Floor Fill (100mm. Stone Concrete) = 0.023x100 2.3 kPa
- Ceiling (13mm. Gypsum Board) 0.104 kPa
TOTAL SLAB DEAD LOAD 2.404 kPa

Area of Slab (15.6x11) = 171.6m^2


TOTAL Weight of Slab = (15.6x11) x 2.404 412.53 KN

Parapet Wall
- 6” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on both sides
Front and Back Area (15.6x0.2) = 3.12m^2
Total weight = [2.97 + 2(0.24)] (15.6x0.2) x 2 21.528 KN
Right and Left Area (11x0.2) = 2.2m^2
Total weight = [2.97 + 2(0.24)] (11x0.2) x 2 15.18 KN

Beam
(y = 23.6 KN/m^3)
- Area of Beam (0.3mx0.38m) = 0.114m^2
Total Length of Beam = 138.8m
Total Weight of Beam = (23.6) (.3x.38) (138.8) 373.428 KN

822.67 KN
4th Floor
Column
(y = 23.6 KN/m^3)
- Area of Column (0.4mx0.4m) = 0.16m^2
- Height of Column (3.18m)
- No. of Column = 26
Total Weight of Column = (23.6) (.4x.4) (3.18) (26) 312.20 KN

Walls and Partitions


- 6” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on
both sides (Exterior Walls)
Front Wall Area [(2.6x2.8) – (0.8x2.1)] x 6 = 33.6m^2
Total weight = [2.97 + 2(0.24)] (33.6) 115.82 KN
Rear Walls
Area1 = [(2.6x2.8) – (0.5x0.5)] x 3 = 21.09m^2
Area2 = (2.6x1.25) x 3 = 9.75m^2
Total weight = (21.09 + 9.75) [2.97 + 2(0.24)] 106.398 KN
Side walls
Area1 (2x1.25) x 2 = 5m^2
Area2 (3.1x2.8) x 2 = 17.36m^2
Area3 (3.4x2.8) x 2 = 19.04m^2
Area4 (2.5x2.8) = 7m^2
Area 5 (1.2x1.25) = 1.5m^2
Total weight = (5 + 17.36 + 19.04 + 7 + 1.5) [2.97 + 2(0.24)] 172.155 KN

- 4” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on


both sides (Interior Walls)
Area1 (2x1.25) x 2 = 5m^2
Area2 (3.1x2.8) x 5 = 43.4m^2
Area3 (3.4x2.8) x 2 = 19.04m^2
Area4 (2.5x2.8) x 5= 35m^2
Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur

COLLEGE OF ENGINEERING
Bachelor of Science in Civil Engineering

Area 5 [(2.6x2.8) – (0.8x2.1)] x 12 = 67.2m^2


Total Area = 5 + 43.4 + 19.04 + 35 + 67.2 = 169.64m^2
Total weight = (169.64) [2.97 + 2(0.24)] 563.205 KN

Slab
- Floor Fill (125mm. Stone Concrete) = 0.023x125 2.875 kPa
- Floor Finish (Ceramic Tile on 13mm mortar bed) 0.77 kPa
- Ceiling (13mm. Gypsum Board) 0.104 kPa
TOTAL SLAB DEAD LOAD 3.749 kPa

Area of Slab (15.6x11) = 171.6m^2


Area Covered by stair = 3.565m^2
TOTAL Weight of Slab = [(15.6x11) – 3.565] x 3.759 629.963 KN

Beam
(y = 23.6 KN/m^3)
- Area of Beam (0.3mx0.38m) = 0.114m^2
Total Length of Beam = 138.8m
Total Weight of Beam = (23.6) (.3x.38) (138.8) 373.428 KN

Door
- Panel Type (0.48 kPa)
No. of door = 9
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 0.48] x 9 7.258 KN
- Flush Type (0.383 kPa)
No. of door = 3
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 0.383] x 3 1.93 KN
- Glass Door (1.30 kPa)
No. of door = 6
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 1.30] x 6 13.104 KN

Window
- Fixed Glass (0.96 kPa)
No. of Window = 3
Area of window = (0.3mx0.3m)
Total weight of window = [(0.3x0.3) x 0.96] x 3 0.26 KN

Assume Plumbing and Electrical Fixture 15 KN

Stair (Assume 40% of Slab Weight)


Total weight = (629.963 x 0.40) 251.99 KN

Railings (0.30 kPa)


Area1 (1.25mx5.2m) x 3 = 19.5m^2
Area2 (1.25mx2m) x 3 = 7.5m^2
Total weight = (19.5 + 7.5) (0.30) 8.1 KN

Canopy (y = 23.6 KN/m^3)


Area of Canopy = (.3mx.3m) = 0.09m^2
Thickness = 0.1m
No. of canopy = 3
Total weight = (0.09) (.1) (23.6) (3) 0.64 KN
2571.451 KN
Assume 10% of total Dead Load
2571.451 KN x 0.1 257.145 KN
Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur

COLLEGE OF ENGINEERING
Bachelor of Science in Civil Engineering

2828.596 KN
3rd Floor
Column
(y = 23.6 KN/m^3)
- Area of Column (0.4mx0.4m) = 0.16m^2
- Height of Column (3.18m)
- No. of Column = 26
Total Weight of Column = (23.6) (.4x.4) (3.18) (26) 312.20 KN

Walls and Partitions


- 6” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on
both sides (Exterior Walls)
Front Wall Area [(2.6x2.8) – (0.8x2.1)] x 6 = 33.6m^2
Total weight = [2.97 + 2(0.24)] (33.6) 115.82 KN
Rear Walls
Area1 = [(2.6x2.8) – (0.5x0.5)] x 3 = 21.09m^2
Area2 = (2.6x1.25) x 3 = 9.75m^2
Total weight = (21.09 + 9.75) [2.97 + 2(0.24)] 106.398 KN
Side walls
Area1 (2x1.25) x 2 = 5m^2
Area2 (3.1x2.8) x 2 = 17.36m^2
Area3 (3.4x2.8) x 2 = 19.04m^2
Area4 (2.5x2.8) = 7m^2
Area 5 (1.2x1.25) = 1.5m^2
Total weight = (5 + 17.36 + 19.04 + 7 + 1.5) [2.97 + 2(0.24)] 172.155 KN

- 4” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on


both sides (Interior Walls)
Area1 (2x1.25) x 2 = 5m^2
Area2 (3.1x2.8) x 5 = 43.4m^2
Area3 (3.4x2.8) x 2 = 19.04m^2
Area4 (2.5x2.8) x 5= 35m^2
Area 5 [(2.6x2.8) – (0.8x2.1)] x 12 = 67.2m^2
Total Area = 5 + 43.4 + 19.04 + 35 + 67.2 = 169.64m^2
Total weight = (169.64) [2.97 + 2(0.24)] 563.205 KN

Slab
- Floor Fill (125mm. Stone Concrete) = 0.023x125 2.875 kPa
- Floor Finish (Ceramic Tile on 13mm mortar bed) 0.77 kPa
- Ceiling (13mm. Gypsum Board) 0.104 kPa
TOTAL SLAB DEAD LOAD 3.749 kPa

Area of Slab (15.6x11) = 171.6m^2


Area Covered by stair = 3.565m^2
TOTAL Weight of Slab = [(15.6x11) – 3.565] x 3.759 629.963 KN

Beam
(y = 23.6 KN/m^3)
- Area of Beam (0.3mx0.38m) = 0.114m^2
Total Length of Beam = 138.8m
Total Weight of Beam = (23.6) (.3x.38) (138.8) 373.428 KN

Door
- Panel Type (0.48 kPa)
No. of door = 9
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 0.48] x 9 7.258 KN
- Flush Type (0.383 kPa)
No. of door = 3
Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur

COLLEGE OF ENGINEERING
Bachelor of Science in Civil Engineering

Area of door = (0.8mx2.1m)


Total weight of door = [(2.1x0.8) x 0.383] x 3 1.93 KN
- Glass Door (1.30 kPa)
No. of door = 6
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 1.30] x 6 13.104 KN

Window
- Fixed Glass (0.96 kPa)
No. of Window = 3
Area of window = (0.3mx0.3m)
Total weight of window = [(0.3x0.3) x 0.96] x 3 0.26 KN

Assume Plumbing and Electrical Fixture 15 KN

Stair (Assume 40% of Slab Weight)


Total weight = (629.963 x 0.40) 251.99 KN

Railings (0.30 kPa)


Area1 (1.25mx5.2m) x 3 = 19.5m^2
Area2 (1.25mx2m) x 3 = 7.5m^2
Total weight = (19.5 + 7.5) (0.30) 8.1 KN

Canopy (y = 23.6 KN/m^3)


Area of Canopy = (.3mx.3m) = 0.09m^2
Thickness = 0.1m
No. of canopy = 3
Total weight = (0.09) (.1) (23.6) (3) 0.64 KN
2571.451 KN
Assume 10% of total Dead Load
2571.451 KN x 0.1 257.145 KN

2828.596 KN
2nd Floor
Column
(y = 23.6 KN/m^3)
- Area of Column (0.4mx0.4m) = 0.16m^2
- Height of Column (3.18m)
- No. of Column = 26
Total Weight of Column = (23.6) (.4x.4) (3.18) (26) 312.20 KN

Walls and Partitions


- 6” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on
both sides (Exterior Walls)
Front Wall Area [(2.6x2.8) – (0.8x2.1)] x 6 = 33.6m^2
Total weight = [2.97 + 2(0.24)] (33.6) 115.82 KN
Rear Walls
Area1 = [(2.6x2.8) – (0.5x0.5)] x 3 = 21.09m^2
Area2 = (2.6x1.25) x 3 = 9.75m^2
Total weight = (21.09 + 9.75) [2.97 + 2(0.24)] 106.398 KN
Side walls
Area1 (2x1.25) x 2 = 5m^2
Area2 (3.1x2.8) x 2 = 17.36m^2
Area3 (3.4x2.8) x 2 = 19.04m^2
Area4 (2.5x2.8) = 7m^2
Area 5 (1.2x1.25) = 1.5m^2
Total weight = (5 + 17.36 + 19.04 + 7 + 1.5) [2.97 + 2(0.24)] 172.155 KN

- 4” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on


Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur

COLLEGE OF ENGINEERING
Bachelor of Science in Civil Engineering

both sides (Interior Walls)


Area1 (2x1.25) x 2 = 5m^2
Area2 (3.1x2.8) x 5 = 43.4m^2
Area3 (3.4x2.8) x 2 = 19.04m^2
Area4 (2.5x2.8) x 5= 35m^2
Area 5 [(2.6x2.8) – (0.8x2.1)] x 12 = 67.2m^2
Total Area = 5 + 43.4 + 19.04 + 35 + 67.2 = 169.64m^2
Total weight = (169.64) [2.97 + 2(0.24)] 563.205 KN

Slab
- Floor Fill (125mm. Stone Concrete) = 0.023x125 2.875 kPa
- Floor Finish (Ceramic Tile on 13mm mortar bed) 0.77 kPa
- Ceiling (13mm. Gypsum Board) 0.104 kPa
TOTAL SLAB DEAD LOAD 3.749 kPa

Area of Slab (15.6x11) = 171.6m^2


Area Covered by stair = 3.565m^2
TOTAL Weight of Slab = [(15.6x11) – 3.565] x 3.759 629.963 KN

Beam
(y = 23.6 KN/m^3)
- Area of Beam (0.3mx0.38m) = 0.114m^2
Total Length of Beam = 138.8m
Total Weight of Beam = (23.6) (.3x.38) (138.8) 373.428 KN

Door
- Panel Type (0.48 kPa)
No. of door = 9
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 0.48] x 9 7.258 KN
- Flush Type (0.383 kPa)
No. of door = 3
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 0.383] x 3 1.93 KN
- Glass Door (1.30 kPa)
No. of door = 6
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 1.30] x 6 13.104 KN

Window
- Fixed Glass (0.96 kPa)
No. of Window = 3
Area of window = (0.3mx0.3m)
Total weight of window = [(0.3x0.3) x 0.96] x 3 0.26 KN

Assume Plumbing and Electrical Fixture 15 KN

Stair (Assume 40% of Slab Weight)


Total weight = (629.963 x 0.40) 251.99 KN

Railings (0.30 kPa)


Area1 (1.25mx5.2m) x 3 = 19.5m^2
Area2 (1.25mx2m) x 3 = 7.5m^2
Total weight = (19.5 + 7.5) (0.30) 8.1 KN

Canopy (y = 23.6 KN/m^3)


Area of Canopy = (.3mx.3m) = 0.09m^2
Thickness = 0.1m
No. of canopy = 3
Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur

COLLEGE OF ENGINEERING
Bachelor of Science in Civil Engineering

Total weight = (0.09) (.1) (23.6) (3) 0.64 KN


2571.451 KN
Assume 10% of total Dead Load
2571.451 KN x 0.1 257.145 KN

2828.596 KN
Ground Floor
Column
(y = 23.6 KN/m^3)
- Area of Column (0.4mx0.4m) = 0.16m^2
- Height of Column (3.28m)
- No. of Column = 26
Total Weight of Column = (23.6) (.4x.4) (3.28) (26) 322.017 KN

Walls and Partitions


- 6” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on
both sides (Exterior Walls)
Front Walls
Area1 [(2.6x2.9) – (0.85x2.1) – (0.9x1.2)] x 3 = 14.025m^2
Area2 [(2.6x2.9) – (1.6x1.2)] x 3 = 16.86m^2
Total weight = [2.97 + 2(0.24)] (14.025 + 16.86) 106.553 KN
Rear Walls
Area1 = [(2.6x2.9) – (0.5x0.5)] x 3 = 21.87m^2
Area2 = (2.6x1.25) x 3 = 9.75m^2
Total weight = (21.87 + 9.75) [2.97 + 2(0.24)] 109.089 KN
Side walls
Area1 (2x1.25) x 2 = 5m^2
Area2 (3.1x2.9) x 2 = 17.98m^2
Area3 (3.4x2.9) x 2 = 19.72m^2
Area4 (2.5x2.9) = 7.25m^2
Area 5 (1.2x1.25) = 1.5m^2
Total weight = (5 + 17.98 + 19.72 + 7.25 + 1.5) [2.97 + 2(0.24)] 177.503 KN

- 4” CHB, fully grouted using 21.2 KN/m^3 density unit, plastered on


both sides (Interior Walls)
Area1 (2x1.25) x 2 = 5m^2
Area2 (3.1x2.9) x 2 = 17.98m^2
Area3 (3.4x2.9) x 2 = 19.72m^2
Area4 (2.5x2.9) x 5= 36.25m^2
Area 5 [(2.6x2.9) – (0.8x2.1)] x 6 = 35.16m^2
Area6 (1.2x2.9) x 3= 10.44m^2
Total Area = 5 + 17.98 + 19.72 + 36.25 + 35.16 + 10.44 = 124.55m^2
Total weight = (124.55) [2.97 + 2(0.24)] 429.70 KN

Slab
- Floor Fill (125mm. Stone Concrete) = 0.023x125 2.875 kPa
- Floor Finish (Ceramic Tile on 13mm mortar bed) 0.77 kPa
TOTAL SLAB DEAD LOAD 3.645 kPa

Area of Slab (15.6x11) = 171.6m^2


TOTAL Weight of Slab = (171.6) x (3.645) 625.482 KN

Door
- Panel Type (0.48 kPa)
No. of door = 6
Area of door = (0.85mx2.1m)
Total weight of door = [(2.1x0.85) x 0.48] x 6 5.141 KN
- Flush Type (0.383 kPa)
Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur

COLLEGE OF ENGINEERING
Bachelor of Science in Civil Engineering

No. of door = 3
Area of door = (0.8mx2.1m)
Total weight of door = [(2.1x0.8) x 0.383] x 3 1.93 KN

Window
- Sliding Type Window (0.96kPa)
Window1 (0.9mx1.2m) x 3= 3.24m^2
Window2 (1.6mx1.2m) x 3= 5.76m^2
Total weight = [(3.24 + 5.76) x 0.96] 8.64KN
- Fixed Glass (0.96 kPa)
No. of Window = 3
Area of window = (0.3mx0.3m)
Total weight of window = [(0.3x0.3) x 0.96] x 3 0.26 KN

Assume Plumbing and Electrical Fixture 15 KN

Stair (Assume 40% of Slab Weight)


Total weight = (625.482 x 0.40) 250.193 KN

Canopy (y = 23.6 KN/m^3)


Area of Canopy = (.3mx.3m) = 0.09m^2
Thickness = 0.1m
No. of canopy = 3
Total weight = (0.09) (.1) (23.6) (3) 0.64 KN
2052.148 KN
Assume 10% of total Dead Load
2052.148 KN x 0.1 205.215 KN

2257.363 KN
TOTAL DEAD LOADS 11565.821 KN

John Harvey C. Hugo


BSCE-4C