This document outlines the in-coming inspection procedure for raw materials at Otto Engineering Works. It specifies that raw materials will be unloaded at a designated location and inspected for conformance, with materials either approved or rejected. Approved materials will be identified and stored separately from rejected materials on a first-in, first-out basis. Rejected materials will be returned to suppliers. Dimensional and metallurgical reports will be demanded from suppliers and third-party verification may be conducted annually. Any rejections from manufacturing related to raw materials will be communicated to suppliers for corrective action.
This document outlines the in-coming inspection procedure for raw materials at Otto Engineering Works. It specifies that raw materials will be unloaded at a designated location and inspected for conformance, with materials either approved or rejected. Approved materials will be identified and stored separately from rejected materials on a first-in, first-out basis. Rejected materials will be returned to suppliers. Dimensional and metallurgical reports will be demanded from suppliers and third-party verification may be conducted annually. Any rejections from manufacturing related to raw materials will be communicated to suppliers for corrective action.
This document outlines the in-coming inspection procedure for raw materials at Otto Engineering Works. It specifies that raw materials will be unloaded at a designated location and inspected for conformance, with materials either approved or rejected. Approved materials will be identified and stored separately from rejected materials on a first-in, first-out basis. Rejected materials will be returned to suppliers. Dimensional and metallurgical reports will be demanded from suppliers and third-party verification may be conducted annually. Any rejections from manufacturing related to raw materials will be communicated to suppliers for corrective action.
: QMS/SOP/F:00 OTTO ENGINEERING WORKS, Date: 01.04.2021
ALWAR Revision No.: 00
Revision Date : SCOPE : In-coming / Raw Material Control Procedure. RESPONSIBILITY Raw material to be un-loaded on designated Supervisor location. Raw material to be checked for conformance & Decision to be taken based on inspection QUALITY INSPECTOR findings OK / Rejection. Materials to be identified by Name Plate system / Print of Bag / Identification Tag for Supervisor storage & movements. OK Material to be issued for production on FIFO Supervisor Basis. Rejected Raw material to be stored on Rejection Supervisor area to avoid mixing with OK Lot.
Rejected material to be returned to supplier. Supervisor
Raw material Dimensional & Metallurgical report
to be demand from supplier on Lots basis for Supervisor conformance check & Cross verification by 3rd Party @ yearly if needed. Any Rejections in Mfg. Process related to Raw material to be communicated to supplier for Supervisor CAPA submission. S.N. Revision Details Approved By
Mr. Umesh Gupta
Approved By BADLIWAL ENGG. WORKS IN-COMING INSPECTION REPORT DOC. NO. QMS/RQC/F:00 (As per IS: 2500-Level 1st Sampling Plan) Supplier Name: Kedia Enterprises, Jaipur Bill No.: Date: Inspection Date: Item Name: Exhaust Manifold-298 (Casting) Lot Size: Sample Qty.: OBSERVATIONS RECORD OF 05 SAMPLE PCS. S.N. PARAMETER SPECIFICATIONS Inspection Method REMARKS 1 2 3 4 5 1 Wall Thickness 5 ±0.8 mm Pistal Caliper
2 Height 164 mm Vernier Caliper
3 Flange Thickness 15 mm Vernier Caliper
4 Casting Flashes Removal Visual
Matl. FG:200, Out Sourcing 5 Hardness 160-220 BHN)
Visual Inspection: Free from Visual & Third Party
6 Casting Defects i.e. B/H, Crack, Verification Extra Matl., Poor Shot Blasting, Hardness High/Low. Remarks: Checked By: