ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
STRUCTURE OF TECHNICAL SERVICES
HEAD TECHNICAL
SERVICES
4
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
ACC Concrete Ltd.
Research & Development Centre
ACC-RMX R&D centre is an In-House R&D facility of its
parent organization “ACC. Ltd & Gujarat Ambuja.”
The R&D centre plans to get recognition from The Department of Science &
Technology (Recognition leads to benefits in terms of Tax waivers).
The Centre plans to get accredited against ISO: 17025:1999 (an International
standard stating general requirements for competence of laboratories) by National
Accreditation Board for Testing & Calibration laboratories (NABL).
Accreditation means that the test results produced by the Centre are recognized
world wide.
6
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
7
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
8
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
9
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
10
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
11
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
12
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
ACC-RMX Research & Development Centre
14
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Why Quality Control?
Even with the best mixture designs, failures occur in
concrete structures, some of which are attributable to
design and the others to the material itself. However,
more often than not, the failure is a result of negligence
and lack of attention to quality on the jobsite during
construction.
15
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Probability density function
17
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Grade wise Cube Strength
Monthly Cube Strength- M 20
50
Grade of No. of Avg. Standard
40
Strength MPa
10
0
1 6 11 16 21 26 31 36 41 46 51 56 M 20 59 27.74 2.97
Sample No. 28 Days
45
40 M 25 67 32.02 3.09
Strength MPa
35
30
25
20
15
10
M 30 14 36.01 4.19
13
17
21
25
29
33
37
41
45
49
53
57
61
65
1
50
45
Strength MPa
40
35
30
25
20
1 2 3 4 5 6 7 8 9 10 11 12 13
Sample No.
28 Days
18
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Control Mix for Cement Testing
19
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
BIS acceptance criteria
As per the IS code (Clause 16 of IS 456:2000), for a given
set of tests, the compressive strength is taken as the
average of three tests, no one test differing from the
average by more than 15%. The strength requirements
are deemed to meet standards if the following conditions
are satisfied.
Compressive strength:
Mean of 4 test results > fck + 0.825 σ, or fck + 4 MPa (whichever
is greater)
Individual strength result > fck – 4 MPa
Flexural strength (ft is the characteristic flexural strength):
Mean of 4 test results > ft + 0.3 MPa
Individual strength result > ft – 0.3 MPa
20
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Monthly Reports – Quality Control
Plant Performance - Cement Contents & Standard Deviation for August 2007
PPC PPC PPC PPC PPC PPC PPC Workability
No. of
No. Out cube
Plant M 15 M 20 M 25 M 30 M 35 M 40 M 45 No.
of failur
Teste
Toleran es
CC SD CC SD CC SD CC SD CC SD CC SD CC SD d
ce
Faridabad 240 .. 285 2.3 330 3.3 365 1.4 405 3.1 455 2.9 .. .. Nil
Change
compared
.. .. .. .. .. .. .. .. .. .. .. .. .. .. .. … …
to last month
(+/-)
Greater Noida .. .. 285 1.7 325 … 365 1.51 …. … … … …. … … … …
Change
compared
.. .. .. .. .. .. .. .. .. .. .. .. .. .. .. … …
to last month
(+/-)
Kundali .. .. 285 1.6 .. .. .. .. .. .. .. .. .. .. .. … …
Change
compared
.. .. .. .. .. .. .. .. .. .. .. .. .. .. .. … …
to last month
(+/-)
Average 240 285 1.86 328 3.30 365 1.46 405 3.10 455 2.90
CC :- Cement Content
Aggregate
9 Grading (sieve analysis) Weekly 40 2 IS:2386 (Part 1)
10 Unit weight and voids (Bulk density) Monthly 10 1 IS:2386 (Part 3)
Specific gravity and absorption IS:2386 (Part 4)
23
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Typical Lab model – Mumbai (Central lab)
Total average concrete production considered as 6000 m3 per Plant per
month, hence for 10 plants --- 60’000 m3 / month.
Estimated
No. of tests
volume of
to be done No. of
Sr. Frequency of concrete per Relevant
Details of the tests to be done in a month test per
No. tests month for Code
for 10 day
10 plants
plants
(m3)
24
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Typical Lab model – Mumbai (Central lab)
Total average concrete production considered as 6000 m3 per Plant per
month, hence for 10 plants --- 60’000 m3 / month.
Estimated
No. of tests
volume of
to be done No. of
Sr. Frequency of concrete per Relevant
Details of the tests to be done in a month test per
No. tests month for Code
for 10 day
10 plants
plants
(m3)
Admixture
19 Marsh Cone (Compatibility studies) As per requirement 0 0 IS: 9103
20 Specific Gravity 0 0 0 IS: 9103
21 Water reduction 0 60000 0 0 IS: 9103
Cement
22 Compressive strength Weekly 40 2 IS: 4031 (Part 6)
23 Consistency Weekly 40 2 IS:4031 (Part 4)
25
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Typical Lab model – Mumbai (Central lab)
Total 11
26
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Typical Lab model – Mumbai (Central lab)
1 Compression 2* 6,00,000
testing machine
2 Flexural testing 1 60,000
machine
3 Pan mixer 1 1,11,000
* Second machine will be purchased when volume increases to a
level when it is necessary
27
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Lab model – Stand Alone Lab
Total average concrete production considered as 3000 m3( per shift)
Estimated
No. of tests No. of
Sr. Details of the tests to be Frequency of volume of Relevant
to be done test
No done tests concrete per Code
in a month per day
month (m3)
Aggregate
1 Grading (sieve analysis) Weekly 4 1 IS:2386 (Part 1)
2 Unit weight and Bulk density Monthly 1 0 IS:2386 (Part 3)
Specific gravity and absorption
3000
3 a) By Pycnometer method Weekly 4 0
Concrete
29
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Quality Statement
We are fully committed to:
Meeting or exceeding our customers product and service
expectations.
Maintaining a professional and rewarding environment for
our employees.
Improving our competitiveness in the marketplace.
Provide leadership in improving the image and
performance levels of the RMX industry in India.
30
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
PROCESS
A set of Interrelated activities which transforms inputs
into desired output
31
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Process Approach
Plan : Establish objectives and processes necessary to
deliver results in accordance with the requirements and
the organization policies.
DO : Implement the Processes
Check: Monitor and measure the processes against
defined policies , objectives and requirements
32
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Business Operating System ( BOS )
33
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Purpose of BOS
To facilitate the standardization of Processes and
Procedures throughout the Company.
To foster a culture of doing things right the first time
every time.
Cut down on time and energy used to resolve issues.
Eliminate confusions and follow up on unnecessary queries.
Streamline business processes to facilitate higher
operating efficiencies - increase productivity.
Facilitate the training of new employees.
34
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
ACC RMX BOS Objectives
To provide full transparency; all employees are aware of
the responsibilities of their colleagues.
To ensure that Job descriptions and KPI’s in line with
actual working practice.
Improve level of service and quality of the Product.
35
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Management Commitment to BOS
To ensure that BOS policies objectives, procedures and
work instructions are disseminated and implemented
throughout ACC RMX.
To maintain and modify procedures as required to
reflect current situation and requirements of both the
Operations and the Customers.
To ensure that sufficient resources ( both in terms of HR
and infrastructure ) are available for BOS in order to
fulfill the needs of the operations and the customers.
To review all aspects of the BOS on a regular basis,
promote and encourage continuous improvement.
36
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Overview BOS
Pricing
Production
Order taking & PP 1 Start up / shut down
scheduling PP 2 Shift handover
PP 3 Automatic bathching
PP11 Order entry – stand alone PP 4 Manual batching Dispatching
PP12 Order entry – cluster PP 5 Ordering raw materials
PP16 Order entry - pumping PP 6 Receiving raw materials PP13 Dispatching of concrete
PP 7 Inventory control PP17 Dispatch - pumping
PP 8 Raw materials management
Invoicing Maintenance
Delivery
PT 7 Delivery of concrete
PP 10 Breakdown of RMX Trucks
PP 18 Execution pumping
PP 09 Handling of rejected concrete
Complaints
management
PP 15 Complaints management
Proof of delivery
PP 14 Proof of delivery
37
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Overview BOS
Pricing
Production
Order taking & PP 1 Start up / shut down
scheduling PP 2 Shift handover
PP 3 Automatic bathching
PP11 Order entry – stand alone PP 4 Manual batching Dispatching
PP12 Order entry – cluster PP 5 Ordering raw materials
PP16 Order entry - pumping PP 6 Receiving raw materials PP13 Dispatching of concrete
PP 7 Inventory control PP17 Dispatch - pumping
PP 8 Raw materials management
Invoicing Maintenance
Delivery
PT 7 Delivery of concrete
PP 10 Breakdown of RMX Trucks
PP 18 Execution pumping
PP 09 Handling of rejected concrete
Complaints
management
PP 15 Complaints management
Proof of delivery
PP 14 Proof of delivery
38
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Mix Designs
Definition
It is a method of designing concrete of required grade having
required workability and strength.
Scope
Includes all the activities beginning from obtaining information on
product specification to batch of concrete for regular production.
Involvement
Cluster Plant.
- Quality Incharge, Lab officer, Lab Technician
Stand alone Plant.
- Head QC, Lab officer, Lab Technician
39
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Mix Designs
Links with other processes.
Quotation ,Quality control, pricing
Documented procedures.
PT 1.Generating Mix Design
Key benefits.
Clarifies the interaction between the involved in the process.
Clarifies all the roles and responsibilities of the involved in the process.
Ensures standardization of all the processes in all Plants.
Operate a mix cost Optimization program
Systems Used.
SAP, Command Alkon, Conad
40
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Overview BOS
Pricing
Production
Order taking & PP 1 Start up / shut down
scheduling PP 2 Shift handover
PP 3 Automatic bathching
PP11 Order entry – stand alone PP 4 Manual batching Dispatching
PP12 Order entry – cluster PP 5 Ordering raw materials
PP16 Order entry - pumping PP 6 Receiving raw materials PP13 Dispatching of concrete
PP 7 Inventory control PP17 Dispatch - pumping
PP 8 Raw materials management
Invoicing Maintenance
Delivery
PT 7 Delivery of concrete
PP 10 Breakdown of RMX Trucks
PP 18 Execution pumping
PP 09 Handling of rejected concrete
Complaints
management
PP 15 Complaints management
Proof of delivery
PP 14 Proof of delivery
41
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Overview BOS
Pricing
Production
Order taking & PP 1 Start up / shut down
scheduling PP 2 Shift handover
PP 3 Automatic bathching
PP11 Order entry – stand alone PP 4 Manual batching Dispatching
PP12 Order entry – cluster PP 5 Ordering raw materials
PP16 Order entry - pumping PP 6 Receiving raw materials PP13 Dispatching of concrete
PP 7 Inventory control PP17 Dispatch - pumping
PP 8 Raw materials management
Invoicing Maintenance
Delivery
PT 7 Delivery of concrete
PP 10 Breakdown of RMX Trucks
PP 18 Execution pumping
PP 09 Handling of rejected concrete
Complaints
management
PP 15 Complaints management
Proof of delivery
PP 14 Proof of delivery
42
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Quality Control
Definition
It is a inherent characteristic of product which fulfill the customer
requirement.
Scope
Includes all the activities beginning from testing of concrete
constituents to testing of fresh and hardened concrete
Cluster Plant.
- Quality Incharge, Lab Officer, Lab Technician,
Stand alone Plant.
- Lab Officer, Lab Technician
43
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Quality Control
Links with other processes.
Production,Dispatching and Delivery .
Documented procedures.
PT 2 to PT 6
PT 8 to PT 12
Key benefits.
Clarifies the interaction between the involved in the process.
Clarifies all the roles and responsibilities of the involved in the process.
Ensures standardization of all the processes in all Plants.
Systems Used.
SAP, Command Alkon, Conad
44
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Screen shot and process flows
PT2 Field sampling & testing of concrete
PT 11 Testing of Aggregates
45
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
ACC RMX Generating mix designs
No
Obtaining
information about
New raw
Product Is a new mix Create a mix Is a trial mix Is a new BOM Create a BOM in
materials No Yes No Yes
specifications & design required design required? required? SAP
required ?
performance of
existing mixes
Yes
Yes No
Define the new
raw materials
needed
Modify existing Enter mix design
Prepare a trial mix
BOM in SAP in batch computer
Mix design
No
Yes confirmed
No
No
Material
Material exists
suitable for mix Yes
in SAP
design
46
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Quality Assurance
Addresses the entire cycle starting from initial product
identification to final inspection reliability. Quality
assurance achieve quality by implementing a set of laid
down procedures
Quality Assurance is towards improvement of Process
capability, Detection and prevention of Non Conformity
Quality assurance can be achieved through the use of
comprehensive process systems,procedures, work
instructions, Quality formats and Auditing of Quality
System
47
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Concrete Technology
Concrete is most widely used man made construction
material in the world.
Concrete is obtained by mixing cementitious material ,
water, aggregate and admixtures (if required)
The mixture when Placed in forms and allowed to cure ,
harden into rock like mass known as concrete
Key characteristic of concrete is strength and durability.
Concrete possesses high compressive strength but low
tensile strength.
48
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Grade of Concrete
Concrete is generally Graded according to its
compressive strength IS 456 :2000
Example M 25
M stands for Mix
25 Stands for Specified
characteristic strength of 150mm work cube
at 28 days expressed in MPa(N/mm2)
49
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
INSPECTION AND TEST PLAN
ITP laid down the frequency, reference standard and
acceptance criteria for routine testing of concrete and
concrete constituents at plant and central lab.
50
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Quality Reporting
All tests observation in laboratory as well as site shall
be reported in prescribed formats.
Every test record shall be signed by the observer
unsigned record is not valid.
Records shall be established and maintained to provide
evidence of conformity to the requirements. Record
shall be legible, readily identifiable and retrievable.
Sample Formats
Cube Sampling and Testing
Format
S.No. Description No.
1 Lab Equipment register FT 1
2 Lab calibration checking FT 2
3 Lab scale check standard Mass FT 3
4 Checking Slump Cone FT 4
5 Checking Cube Moulds FT 5
Checking ambient and Curing
6 Temperature FT 6
52
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
TEST RESULT REPORTING FORMATS
7 Sampling and testing of concrete FT 7
8 Calibration of Batching Plant FT 8
9 Yield Check FT 9
10 Correction for moisture FT 10
11 Concrete Investigation Report FT 11
12 Checking sieves (Aggregate) FT 12
13 Checking Sieves standard sand sample FT 13
14 Checking Working Thermometer FT 14
53
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
TEST RESULT REPORTING FORMATS
54
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
TEST RESULT REPORTING FORMATS
23 Verification of Density Container FT 23
56
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Document Control
Prevent the unintended use of obsolete documents and
to apply suitable identification to them if retained for any
purpose.
List of Formats , Work instruction .attachment shall be
governed by the Master control List which will be
updated on any revision.
Document has flexibility of revision but There is no
revision possible in record
57
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Quality AUDIT
Quality Audit is a systematic and independent examination
conducted to determine whether quality objectives and
related results conform to company's quality system and
effectively implemented
OBJECTIVE:-
58
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Quality AUDIT
OBJECTIVE:-
59
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Quality AUDIT
Sample:-
The audit is performed based on samples picked up by
each auditor for assessment purpose. The sample can
be ,processes and related documents.
60
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Non Conformity (NC)
Non fulfillment of specified requirements
61
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
Attending Non conformities
Correction:-
62
ACC Concrete Ltd QA/QC in ACCCL (optional) 16.07.2018/SN/SN
(optional) Filename.ppt
ACC Concrete Ltd
QUALITY POLICY
ACC Concrete is a subsidiary of ACC Cement Limited