Professional Documents
Culture Documents
Effective Grouting Materials For Tunneling Through Unconsolidated Ground
Effective Grouting Materials For Tunneling Through Unconsolidated Ground
Unconsolidated Ground
Shingo Wakita1, Kensuke Date1, Takuji Yamamoto1, Hiroshi Yanagisawa2, Naoki Uesugi3
1
Kajima Technical Research Institute, Tokyo, Japan
2
Kajima Corporation, Yokohama, Japan
3
Road Bureau, City of Yokohama, Japan
ABSTRACT
With the increasing use of NATM in urban areas, numerous types of forepoling have been adopted to
reduce surface settlement or reinforce a cutting face. Actual ground is, however, heterogeneous, and
accordingly grouting materials are not injected as adequately as expected at the design stage. Grouting
consequently produces only inadequate reinforcing effects in many cases. A new grouting method has
been developed which allows the use of different grouting materials, according to the change in the
ground conditions. The grouting materials associated with this method are superior to conventional
materials in having good penetration into dense sandy ground and early development of strength. The
method’s superiority has been verified through injection tests and field use.
1. INTRODUCTION
Generally, urban tunnels are exposed to severe excavation conditions e.g. in unconsolidated sandy
layers, with a thin earth cover, right under existing structures and near underground structures.
However, cost pressures and handling of diverse cross sections have been recently required, and
accordingly NATM has been introduced under such conditions.
The fact that NATM has been adopted under such conditions owes greatly to the development of
auxiliary methods. In particular, forepoling has been frequently used to stabilize the ground around the
cutting face, and to control the settlement of ground surface. This method involves the driving of pipes
and the injecting of grouting materials into the ground ahead of face prior to excavation. Among many
forepoling methods, the long-forepoling method, being considered to be the most effective for the
control of ground deformation, has been most frequently adapted. Another forepoling method (Figure
1) has been developed that is more effective for controlling ground deformation and is less costly than
5 degrees 14 degrees
H13 1
the long-forepoling method. A design method for forepoling, based on the cylindrical shell theory, has
been used to verify the superiority of this new forepoling method.
In applying the new forepoling method, it has been found that the grouting materials are not always
injected radially and uniformly. In many cases of actual injection, the grouting material was only
injected within the inside of steel pipes or runs away, and, as a result, the ground was not improved
sufficiently. It is considered that this occurred for two reasons: one is because the adopted material
was not appropriate for the ground to be improved, and the other is because the ground conditions
changed as a tunnel proceeded. Consequently, it is necessary to prepare a few types of grouting
material to excavate ground safely, but it takes much time to change grouting materials. Moreover, all
grouting materials currently available have at least one disadvantage, for example, lack of penetration,
shortage of strength or adverse environmental effects.
In order to solve these problems, many mixing tests and in-situ injection tests have been carried out,
resulting in the development of a new grouting method. In this method, two types of grouting
materials are available, and can be changed in a short time according to the change of ground
condition. Both materials have the high penetrability and early development of strength. In this paper,
the outline of the method is given, followed by the result of injection tests and actual grouting work.
The soils in urban areas are generally classified into two major types according to the way grouting
materials are injected (Table 1). One is the sandy ground in which grout permeates into the voids
between sand particles (ground condition 1). The other is the clay or fissured ground where grout
splits or penetrates into cracks (ground condition 2). Therefore the requirements for grouting materials
vary according to the ground conditions. The requirements in ground condition 1 are good penetration
and a long gel time in order for grout to permeate into fine voids. To excavate soon after grouting,
grout should give a high early strength.
In ground condition 2, the objective of soil improvement is the increase of the bond strength by vein-
type grouting. The grouting material is required to have a high early strength. Because the grouting
materials are highly likely to run away, the gel time should be easily controllable. Furthermore, if
permeation grouting is possible as well as vein-type grouting, the ground can be reinforced further.
Thus, higher penetrability is desired.
Mode of injection
-High permeability (permeable even in dense soil) -Early development of strength and cohesion
Requirements of grout material itself
-Long gel time for grout to permeate
for grouting material into fine voids -Easy-controllable gel time
-Early development of strength of solidified sand -High permeability
Tunnel excavation in urban areas often involves grouting right under houses or near the water-bearing
ground from which groundwater is withdrawn. Grouting materials should therefore be friendly to the
environment.
H13 2
One of the characteristics of tunneling in Japan is the change in geological conditions with the advance
of excavation. Consequently, a few types of grouting material are necessary to excavate the ground
safely, but it takes much time and cost to change grouting materials. In the selection of grouting
materials, ground conditions and their changes should be carefully identified.
In Japan, cement and urethane grouts have been used for grouting in forepoling, and sodium silicate
grout for waterproofing. A comparison among these types of grout is given in Table 2. Cement grout
is used more than any other type of grout for forepoling. But, it is a suspension grouting material, so it
does not permeate in dense sandy ground and it may run away into cracks because of unstable gel
time. Under such ground conditions, urethane grout has a superior overall capacity. In Japan, however,
urethane grout is not generally applied, in order to avoid damage to human health and prevent the
contamination of groundwater. The grout is adopted only in emergency e.g. in the case where the
settlement of ground surface is of concern. Sodium silicate grout has not been used during tunnel
excavation because it has been intended for waterproofing, so it has a relatively weak strength. Those
types of sodium silicate grout that develop relatively high strength have slow gel time, so they have
not been adopted in tunnel forepoling.
To solve the problems described in Section 2.2, a new grouting method has been developed. The
initial focus was placed on sodium silicate grout in view of the environmental issues and the cost.
Conventional sodium silicate grout, however, could not produce adequate strength, so an optimum mix
proportion of sodium silicate and hardeners was selected so as to develop strength early. Ground
conditions 1 and 2 are expected to be encountered irregularly as tunnel excavated. It has been decided
therefore to use either of two different types of substance B (hardeners) in addition to substance A
(Special sodium silicate grout) according to the ground condition. For substance B, the Solution-type
grout fit for ground condition 1 and the Suspension-type grout effective in ground condition 2 are
made available in this method. The approach is expected to prevent the loss of construction time
because of the use of multiple materials and enable grouting materials to be switched with the
minimum amount of work (only switch substance B).
Control of gel time 10 to 120 minutes *3 40 to 120 seconds A few seconds to a few minutes
Safety and
Small Great Small
environmental load
*1 Some grouting materials use superfine cement to compensate for the low permeability of ordinary
cement.
*2 The grout has a rapid rise time, so fracture grouting is likely to take place in dense sandy ground.
*3 Cement grout generally has unstable gel time.
The physical properties of materials used in this method are listed in Table 3. As shown in the table,
both grouting materials can develop strength early The solution-type grout develops a compressive
strength of solidified sand of 1.0 N/mm2 in a day, and Suspension-type grout develops a compressive
strength of the grout material itself of 0.5 N/mm2 in a day. Both grouting materials enable the control
of gel time by changing the amount of gel time controlling agent in substance B.
H13 3
3. COMPARATIVE GROUTING TESTS
In-situ and laboratory injection tests were conducted to verify the penetration of the two types of
grouting materials, the condition of completed columns of solidified soil, and to compare the materials
with conventional grouting materials.
In-situ comparative injection tests were conducted using Solution-type grout and urethane grout in
dense sandy ground (ground condition 1). Six-meter steel pipes were driven on the cut surface of a
slope for grout injection. The sandy ground composed 37% of sand, 34% of silt and 29% of clay. The
specifications for injection are listed in Table 4. For Solution-type grout, injection pressure was held to
a low level of 0.1 to 0.15 MPa in every hole from the initial stage of injection. The design quantity of
Solution-type grout could be injected at a rate slightly higher than the level adopted in ordinary
chemical grouting (around 10 L/min). When urethane grout was injected, the maximum injection
pressure was double that for Solution-type grout.
Figure 2 shows the columns of solidified soil that were excavated one week after grouting. When
Solution-type grout was employed, solidified columns of mean diameter of 800 to 1400 mm were
8 to 45 minutes 4 to 10 minutes
Gel time
Can be reduced to approximately 3 minutes Can be reduced to approximately 30 seconds
constructed. On the other hand, urethane grout was injected by fracture grouting and failed to form
cylindrical columns of solidified soil. In short, permeation grouting of Solution-type grout was
possible while urethane grout was impossible. It was concluded that the new method can achieve
permeation grouting in dense sandy ground, forming an arch of reinforced soils using forepoling.
H13 4
Solution-type grout Urethane grout
No.1 No.2
6m long
Cylindrical column of solidified sand was confirmed when Suspension-type grout was applied. When
cement grout was injected, approximately 30-cm-square solidified masses collapsed one after another
at the start of excavation and only a column close to the polyvinyl chloride pipes was left in the end.
The collapse probably occurred because conventional cement grout failed to combine compacted
columns of solidified sand with polyvinyl chloride pipes or combine columns to one another. As a
H13 5
result of the test, Suspension-type grout was found to have high permeability and be applicable to
construct combined solidified columns. The grout is therefore expected to be effective for reinforcing
the ground.
Direction of excavation
Figure 6. Tunnel along the Mori branch route and surrounding environment
H13 6
4.2 Adoption of the new grouting method at exit portals
Tunnel portals are vulnerable to slope failures, landslides, unsymmetrical earth pressures, insufficient
bearing capacity of soil, face collapses and ground surface settlements because they have a thin earth
cover, and are constructed in geological materials such as talus deposits and weathered rocks. The exit
portal of the Mori branch route was designated as a steep slope failure hazard area because of past
slope failures. Ground surface settlements or slope failures upon the completion of tunnel excavation
were of concern. Reinforcing measures were therefore required at the completion of construction, and
pipe roofing was planned. However the construction yard was narrow and the road width was too
small for delivering heavy equipment. So it was impossible to apply such reinforcing measures as pipe
roofing and soil improvement from the ground surface.
As a means of reinforcement from inside the
tunnel, constructing an arch of reinforced soils
ntal inclinometers
Positions of horizo using the forepoling method, which was employed
placement
for monitoring dis Steel pipe length in ordinary sections, was planned. Figure 7 shows
1 2 3 4 5 6
6.5 m the drawing of the plan. A complex sequence of
7.5 m clay, silt, mudstone and sand formations existed at
Steel 8.5 m the portals. When conventional cement grout was
pipes used, cement grout was expected to run through
10.0 m
Cutting the cracks or voids. The use of urethane grout was
2m excavation
Face
SL
not recommended in view of the existence of
4m excavation private houses in the vicinity and environmental
impact. Grouting materials that could be injected in
limited grout zones under complicated ground
Figure 7. Positions of steel pipes and conditions were required, and the new grouting
horizontal inclinometers installed method was adopted.
near the exit portal of the tunnel
H13 7
Table 6. Injection specifications
Grouting material Design quantity Desired diameter of
Construction section Rate of injection Condition for termination
used in the work of grouting solidified columns
Steel pipe length = l Design quantity of
No.1 Tunnel Solution-type grout l = 10.0 m 441 L 16 L / min grouting
l = 8.5 m 355 L 450 mm or
l = 7.5 m 298 L initial injection pressure
No.2 Tunnel Suspension-type grout 16 L / min
l = 6.5 m 241 L +0.3 MPa
0 0
Displacement of
-3 -3
[mm]
-6 -6
-9 -9
-12 -12
-15 -15
No.1 Tunnel No.2 Tunnel
Figure 9. Results of measurement with horizontal inclinometers
5. CONCLUSIONS
Forepoling has frequently been applied to the tunnel excavation by NATM in urban areas. However,
actual ground is not homogeneous, and thereby some grouting materials are not injected or run away,
and, consequently, grouting produces only inadequate reinforcing effects. A new grouting method has
been developed, in which two grouting materials are available and they can be easily exchanged
according to the change of ground condition. One is Solution-type grout which is suitable for dense
sandy ground, while the other is Suspension-type grout appropriate for clay or fissured ground. The
superiority of proposed grouting method has been confirmed as follows: First, through an injection test,
the solution-type grout has shown higher penetrability than urethane-based grout, and thereby
produced more cylindrical columns of solidified soil; Second, through an injection test using man-
made ground, the suspension-type grout was superior to cement-based grout; Finally, in order to
control surface ground settlement, this method has been successfully applied to work at tunnel portals.
REFERENCE
H13 8