Centering and shuttering including strutting, propping etc.

removal of form
for
Stairs, (excluding landings) except spiral-staircases
DESCRIPTION QUANTITY UNIT RATE
Cost of plank 38mm (2nd class kail wood)
Waist bottom 3.484 sqm
shuttering of steps 1.56 sqm
Face of landing 0.195 sqm
Side of waist 0.3484 sqm
Side of steps 0.18 sqm
Total 5.7674 sqm
TOTAL WITH WASTAGE 6.06 sqm
VOLUME 0.23 cum
MATERIAL( QUANTITY TAKEN FOR COST OF USING ONCE)
Assuming shuttering material will
become unserviceable after use of
8 times

Second class kail wood in planks 0.029 cum 26000


Second class kail wood in scantling 0.005 cum 26000

Safeda ballies 125 mm diameter 0.800 m 40


volume of safeda ballies 0.079 cum
CARRIAGE OF MATERIAL

Carriage of timber
0.112 cum 118.6
LABOURS(For assembling, erection, dismantling
and cleaning)
Carpenter 2nd class 1.73022 day 679
Beldar 0.980458 day 558
EQUIPMENTS
Sundries 16.033372 l.s 2
TOTAL
1% Water Charge
TOTAL
CONCTRACTORS PROFIT AND OH
TOTAL
Cost for Given area
Cost for 1 SQM
ng, propping etc. and SPAN LANDING UNIT

piral-staircases 2.4 1 M

AMOUNT HEIGHT OF STAIRCASE 1.2 M


WIDTH OF STAIRCASE 1.3 M
THICKNESS OF WAIST SLAB 0.13 M
LENGTH OF WAIST 2.68 M
TREAD 0.3 M
RISER 0.15 M
PLANK THICKNESS 0.038 M
SPACING OF BATTENS 0.8 M
SAFEDA BALLIES DIA 0.125 M

Running meter safeda ballies 6.4 m

ONCE)

747.8876 MATERIAL UNIT RATE


126.75 Second class kail wood cum 26000
in planks
Second class kail wood
32 in scantling
cum 26000

Safeda ballies 125 mm


diameter m 40
CARRIAGE OF
UNIT RATE
MATERIAL
13.298672 Carriage cum 118.59
ng LABOURS UNIT RATE
Carpenter 2nd class DAY 679
1174.8194 Beldar DAY 558
547.09556 EQUIPMENTS UNIT RATE
Sundries L.S 2

32.066744
2673.918
26.73918
2700.6571
405.09857
3105.7557

3105.7557

538.50187