Professional Documents
Culture Documents
LOCATION:
OWNER:
BILL OF QUANTITES
UNIT COST
ITEM NO. SCOPE OF WORK QUANTITY Total
Materials
I GENERAL REQUIREMENTS QTY U/M
1.00 Drawings and licenses 1.00 Lot 80,000.00 80,000.00
2.00 Mobilization/Demobilization 1.00 Lot 6,000.00 6,000.00
3.00 Temporary facilities 1.00 Lot 6,000.00 6,000.00
4.00 Clearing and hauling 1.00 Lot 5,000.00 5,000.00
5.00 Temporary water and elect. 1.00 Lot 5,000.00 5,000.00
Sub-total 102,000.00
II EARTHWORKS
1.00 Excavation 251.32 cu.m. 550.00 138,228.42
2.00 Backfill and Compaction 393.53 cu.m. 600.00 236,117.86
Sub-total 374,346.28
IV REBARWORKS
III.1 Foundation
III.1.1 16mm dia. X 6.0m RSB 392.00 pcs 400.00 156,800.00
III.1.2 10mm dia. X 6.0m RSB 188.00 pcs 165.00 31,020.00
III.1.3 Tie Wire 4.00 Rolls 2,700.00 10,800.00
III.2 Ground Floor
III.2.1 16mm dia. X 6.0m RSB 130.00 pcs 400.00 52,000.00
III.2.2 10mm dia. X 6.0m RSB 268.00 pcs 165.00 44,220.00
III.2.3 12mm dia. X 6.0m RSB 39.00 pcs 220.00 8,580.00
III.2.4 Tie Wire 2.00 Rolls 2,700.00
III.3 Second Floor
III.3.1 16mm dia. X 6.0m RSB 701.00 pcs 400.00 280,400.00
III.3.2 10mm dia. X 6.0m RSB 282.00 pcs 165.00 46,530.00
III.3.3 12mm dia. X 6.0m RSB 40.00 pcs 220.00
III.3.4 Tie Wire 4.00 Rolls 2,700.00
III.4 Third Floor
III.4.1 16mm dia. X 6.0m RSB 277.00 pcs 400.00 110,800.00
III.4.2 10mm dia. X 6.0m RSB 241.00 pcs 165.00 39,765.00
III.4.3 Tie Wire 3.00 Rolls 2,700.00 8,100.00
III.5 Roof
III.5.1 16mm dia. X 6.0m RSB 171.00 pcs 400.00 68,400.00
III.5.2 10mm dia. X 6.0m RSB 70.00 pcs 165.00 11,550.00
UNIT COST
ITEM NO. SCOPE OF WORK QUANTITY Total
Materials
III.5.3 Tie Wire 2.00 Rolls 2,700.00 5,400.00
Sub-total 874,365.00
ENGINEER / DATE
OWNER / DATE
UNIT COST
ITEM NO. SCOPE OF WORK QUANTITY Total
Materials