You are on page 1of 3

PROJECT :

LOCATION:
OWNER:

BILL OF QUANTITES
UNIT COST
ITEM NO. SCOPE OF WORK QUANTITY Total
Materials
I GENERAL REQUIREMENTS QTY U/M
1.00 Drawings and licenses 1.00 Lot 80,000.00 80,000.00
2.00 Mobilization/Demobilization 1.00 Lot 6,000.00 6,000.00
3.00 Temporary facilities 1.00 Lot 6,000.00 6,000.00
4.00 Clearing and hauling 1.00 Lot 5,000.00 5,000.00
5.00 Temporary water and elect. 1.00 Lot 5,000.00 5,000.00
Sub-total 102,000.00

II EARTHWORKS
1.00 Excavation 251.32 cu.m. 550.00 138,228.42
2.00 Backfill and Compaction 393.53 cu.m. 600.00 236,117.86
Sub-total 374,346.28

III CONCRETING WORKS


III.1 Foundation
III.1.1 Gravel 40.00 cu.m. 1,400.00 56,000.00
III.1.2 Sand 24.00 cu.m. 1,400.00 33,600.00
III.1.3 Cement 359.00 Bags 240.00 86,160.00
III.2 Ground Floor
III.2.1 Gravel 97.00 cu.m. 1,400.00 135,800.00
III.2.2 Sand 58.00 cu.m. 1,400.00 81,200.00
III.2.3 Cement 866.00 Bags 240.00 207,840.00
III.3 Second Floor
III.3.1 Gravel 66.00 cu.m. 1,400.00 92,400.00
III.3.2 Sand 40.00 cu.m. 1,400.00 56,000.00
III.3.3 Cement 593.00 Bags 240.00 142,320.00
III.4 Third Floor
III.4.1 Gravel 39.00 cu.m. 1,400.00 54,600.00
III.4.2 Sand 24.00 cu.m. 1,400.00 33,600.00
III.4.3 Cement 351.00 Bags 245.00 85,995.00
III.5 Roof
III.5.1 Gravel 13.00 cu.m. 1,400.00 18,200.00
III.5.2 Sand 8.00 cu.m. 1,400.00 11,200.00
III.5.3 Cement 111.25 Bags 245.00 27,256.56
Sub-total 1,122,171.56

IV REBARWORKS
III.1 Foundation
III.1.1 16mm dia. X 6.0m RSB 392.00 pcs 400.00 156,800.00
III.1.2 10mm dia. X 6.0m RSB 188.00 pcs 165.00 31,020.00
III.1.3 Tie Wire 4.00 Rolls 2,700.00 10,800.00
III.2 Ground Floor
III.2.1 16mm dia. X 6.0m RSB 130.00 pcs 400.00 52,000.00
III.2.2 10mm dia. X 6.0m RSB 268.00 pcs 165.00 44,220.00
III.2.3 12mm dia. X 6.0m RSB 39.00 pcs 220.00 8,580.00
III.2.4 Tie Wire 2.00 Rolls 2,700.00
III.3 Second Floor
III.3.1 16mm dia. X 6.0m RSB 701.00 pcs 400.00 280,400.00
III.3.2 10mm dia. X 6.0m RSB 282.00 pcs 165.00 46,530.00
III.3.3 12mm dia. X 6.0m RSB 40.00 pcs 220.00
III.3.4 Tie Wire 4.00 Rolls 2,700.00
III.4 Third Floor
III.4.1 16mm dia. X 6.0m RSB 277.00 pcs 400.00 110,800.00
III.4.2 10mm dia. X 6.0m RSB 241.00 pcs 165.00 39,765.00
III.4.3 Tie Wire 3.00 Rolls 2,700.00 8,100.00
III.5 Roof
III.5.1 16mm dia. X 6.0m RSB 171.00 pcs 400.00 68,400.00
III.5.2 10mm dia. X 6.0m RSB 70.00 pcs 165.00 11,550.00
UNIT COST
ITEM NO. SCOPE OF WORK QUANTITY Total
Materials
III.5.3 Tie Wire 2.00 Rolls 2,700.00 5,400.00
Sub-total 874,365.00

V FORMWORKS AND SCAFFOLDINGS


1.00 4x8ft Phenolic Board 1/2" 40.00 pcs 750.00 30,000.00
2.00 4x8ft Phenolic Board 3/4" 60.00 pcs 550.00 33,000.00
3.00 2x2x12 Good Lumber 180.00 pcs 250.00 45,000.00
4.00 2x5x12 Good Lumber 70.00 pcs 365.00 25,550.00
5.00 Scalfoldings 1.00 Lot 18,000.00 18,000.00
6.00 Others 1.00 Lot 6,000.00 6,000.00
Sub-total 157,550.00

VI STRUCTURAL STEEL AND METAL WORKS


1.00 2" x 2" X 1/4" X 6.0M ∠ BAR 741.00 pcs 650.00 481,650.00
2.00 1-1/2" X 11/2" X 3/16" X 6.0M ∠ BAR 832.00 pcs 570.00 474,240.00
3.00 50 X 75 C- PURLINS X 6.0M 114.00 pcs 500.00 57,000.00
4.00 2 X 10 C-PURLINS X 6.0M 25.00 pcs 1,200.00 30,000.00
5.00 Stainless Gutter x 2.4m 153.60 Lm 510.00 78,336.00
6.00 Ridge Cap x 2.4m 44.00 Lm 510.00 22,440.00
7.00 0.4mm Rib Type Roof 265.00 LM 280.00 74,200.00
8.00 Text Screws 15.00 box 750.00 11,250.00
9.00 Miscellaneous and hardware 1.00 lot 8,000.00 8,000.00
Sub-total 1,237,116.00

VII MASONRY WORKS


VII.1 Foundation
VII.1.1 5" CHB 1,322.00 pcs 14.00 18,508.00
VII.1.2 4" CHB 824.00 pcs 13.00 10,712.00
VII.1.3 Sand 9.00 cu.m 1,400.00 12,600.00
VII.1.4 Cement 108.00 bags 240.00 25,920.00
VII.2 Ground Floor
VII.2.1 5" CHB 3,159.00 pcs 14.00 44,226.00
VII.2.2 4" CHB 1,888.00 pcs 13.00 24,544.00
VII.2.3 Sand 22.00 cu.m 1,400.00 30,800.00
VII.2.4 Cement 253.00 bags 240.00 60,720.00
VII.3 Second Floor
VII.3.1 5" CHB 1,960.00 pcs 14.00 27,440.00
VII.3.2 4" CHB 2,301.00 pcs 13.00 29,913.00
VII.3.3 Sand 18.00 cu.m 1,400.00 25,200.00
VII.3.4 Cement 214.00 bags 240.00 51,360.00
VII.4 Third Floor
VII.4.1 5" CHB 1,624.00 pcs 14.00 22,736.00
VII.4.2 4" CHB 2,986.00 pcs 13.00 38,818.00
VII.4.3 Sand 20.00 cu.m 1,400.00 28,000.00
VII.4.4 Cement 231.00 bags 240.00 55,440.00
Sub-total 506,937.00

VIII RETAINING WALL


1.00 10mm dia. X 6.0m RSB 220.00 pcs 165.00 36,300.00
2.00 16mm dia. X 6.0m RSB 12.00 pcs 400.00 4,800.00
3.00 Ready Mix Concrete 14.00 cu.m 5,200.00 72,800.00
4.00 Gravel Bedding 2.00 cu.m 1,500.00 3,000.00
5.00 Tie Wire 2.00 Rolls 2,300.00 4,600.00
Sub-total 121,500.00
IX Total Direct Cost 4,495,985.83
Labor Cost ~50% 50% 2,247,992.92
Contractor's Profit
Markup/ Contingencies ~5% 5% 224,799.29
TOTAL AMOUNT ROUGHIN IN ₱ 6,968,778.04

ENGINEER / DATE

OWNER / DATE
UNIT COST
ITEM NO. SCOPE OF WORK QUANTITY Total
Materials

You might also like