Professional Documents
Culture Documents
Scenarios
Update
NZGP1 Scenarios and modelling
results for an unconstrained
transmission grid
December 2021
NZGP1 Scenarios Update Transpower New Zealand Limited 02
Executive Summary
This update describes the scenarios we will reasonable EDGS 2019 variations, we are using the same
scenario names as used by the Ministry of Business,
be using for our Net Zero Grid Pathways 1
Innovation and Employment (MBIE).
(NZGP1) Major Capex Project investigation.
This report also describes the outcome from our
Electricity will play an important role in generation expansion model, for each of these
scenarios, assuming an unconstrained transmission
reducing New Zealand’s greenhouse gas grid. These generation expansion plans will not appear
emissions. The demand for electricity is likely in our Investment Test application, but they do provide
to rise significantly in the coming decades and relevant directional information on what future electricity
the supply of electricity will reduce from being generation might be built.
reliant on fossil fuels to an increasing reliance Given the considerable uncertainty in future electricity
demand and supply, there are some potential futures
on renewable energy sources. which are possible but not yet certain enough to include
Such changes create considerable commercial in the NZGP1 scenarios. Some of these have significant
opportunities and our electricity industry is currently transmission implications and to ensure they are not
in a phase where existing and new participants are ignored, we have developed a set of sensitivity scenarios
exploring ideas. This creates considerable uncertainty for as well. These are listed in this document. Our NZGP1
Transpower and the services that will be required from the investigation will explore some sensitivity scenarios,
transmission grid. including variations on Southland supply and demand
and the transmission implications of Lake Onslow being
We use scenarios to consider the effect of such developed for dry year reserve.
uncertainty and are required to use the Electricity
Demand and Generation Scenarios (EDGS) or reasonable Our wider Net Zero Grid Pathways Project (NZGP) is
variations of them, in our investment cases where we also considering issues beyond those being investigated
seek Commerce Commission approval for a Major Capex in NZGP1 and includes a broader range of uncertainties.
Project (MCP). We will update interested parties separately on
that project.
As a first step in our NZGP1 MCP investigation, we
reviewed the latest EDGS, produced in 2019 (EDGS 2019)
and concluded they needed to be updated.
After seeking advice from an expert panel and three
written consultations, we have settled on a suitable set of
scenarios, which are described in this document as our
NZGP1 scenarios. The scenarios are described in detail
in this document and compared to the EDGS 2019. Given
the significant transmission grid investment that will likely
result from our NZGP1 and ongoing NZGP investigations,
this provides transparency for those interested in the
drivers for identified investments.
Our NZGP1 scenarios are variations of the EDGS 2019
and in our view, meet the Commerce Commission’s
requirements for being considered reasonable variations.
There are five scenarios, and we have varied input
assumptions between the scenarios in a very similar
way to the EDGS 2019. Accepting that our scenarios are
Stephen Jones - Grid Planning and Investment Manager
NZGP1 Scenarios Update Transpower New Zealand Limited 03
Contents
Process to date 07
electricity
Electrification
Technology trends of heat Ensuring the interconnected grid
(incl. non-network alternatives)
+ stays ‘ahead of the game’
New renewable to enable connections
power plants
Rules of the game: Increasing
• Business supply of
electricity More distributed Operating a distributed and highly
• Society
and renewable renewable (95%+) electricity system
• Investors
electricity system
Figure ES1 – Transpower’s enabling role in support of New Zealand pursuing net-zero carbon by 2050
NZGP1 Scenarios Update Transpower New Zealand Limited 05
OTB
Process to date
The Capex IM allows for EDGS variations to be used, where • Hence, we undertook further consultation, via a written
the variations are both reasonable and have regard to the consultation paper, in regard to generation scenarios.
views of interested persons. This was in May 2021. We targeted potential generation
investors, although the consultation was open to all
The latest EDGS were published in 2019 but reflecting
interested persons. That consultation was open for 6
the rapid pace of change in New Zealand’s energy sector
weeks and closed in June 2021. Feedback suggested
at the moment, there have been several relevant and
there is too much uncertainty regarding future
important changes which are not reflected in the EDGS
generation possibilities for grid-connected generation
2019. These include, but are not limited to:
in New Zealand, to reflect in just five nationally
• MBIE generation cost stack update, which describes determined scenarios, as the EDGS 2019 are.
potential new generation plant information
• With that feedback in mind, we published our first
• The New Zealand Aluminium Smelter at Tiwai Point’s formal NZGP1 document – the long-list consultation
announcement to close in 2024 (and the subsequent document in August 2021. That consultation was
effect on North Island thermal generators) open for 6 weeks and closed in October 2021. The
• Investor interest in grid-scale batteries submissions we received (excluding two that were
provided on a confidential basis) are published on our
• Government investigation of Onslow pumped hydro website, along with this update paper.
scheme i.e. the NZ battery workstream.
In our long-list consultation document, we described
We therefore consider it necessary to vary the EDGS 2019 a possible approach to developing scenarios suitable
for the purposes of our NZGP1 investigation. A number of for NZGP1. That approach reflected the considerable
other electricity scenarios have been published, including uncertainty in regard to where new generation will be
those by the Climate Change Commission (CCC) and built, but was complex and necessarily involved significant
Transpower’s own Whakamana i Te Mauri Hiko (WiTMH). It judgement. Although it is a possible approach, we have
would be difficult to adopt any of those and justify them decided it would be both difficult to apply, potentially
as EDGS 2019 variations, so we have unpacked the EDGS contentious, and may be difficult to demonstrate to the
2019 and updated those elements which need updating, Commerce Commission that the resultant scenarios are
to ensure consistency. We compare our EDGS 2019 reasonable variations of the EDGS.
variations with these alternative scenarios further on in this
document, as a sense check. Therefore, we have changed our approach and the
scenarios we are presenting here and using for our NZGP1
To ensure we reflect the views of interested persons, investigation, are aligned with EDGS 2019. We are using
we have used a consultative approach to review the the same five scenarios as in EDGS 2019, but with updated
EDGS 2019. A full description of our interactions with inputs and the differences between scenarios is very
stakeholders can be found on our website at: similar to the EDGS 2019. We are calling our scenarios,
http://www.transpower.co.nz/NZGP NZGP1 scenarios.
Table 1 lists some of the more important parameters reflected in the EDGS 2019 demand scenarios:
Table 1 – Some important parameters for each of the EDGS 2019 demand scenarios
2. Electricity demand and generation scenarios (EDGS) | Ministry of Business, Innovation & Employment (mbie.govt.nz)
3. (x%/x%) refers to light vehicle%/heavy vehicle% of fleet which are electric by 2050
4. Transpower plans are based on electricity demand at our grid exit points (GXP’s).
Domestic solar PV is treated the same as other embedded generation, as a subtractor from gross (end-user) demand.
5. x% refers to the percentage of houses in New Zealand with solar PV panel installations
NZGP1 Scenarios Update Transpower New Zealand Limited 09
Table 2 lists some of the more important parameters included in the EDGS 2019 generation scenarios,
along with a summary of the EDGS 2019 generation expansion plans:
Table 2 – Some important parameters for each of the EDGS 2019 generation scenarios and new generation builds by 2050
6. 2050 energy sector emissions, reflecting changes resulting from renewable electricity generation,
process heat conversions and electric vehicle uptake, compared to 2017 emissions
NZGP1 Scenarios Update Transpower New Zealand Limited 10
Table 3 – A comparison of Table 1 EDGS 2019 demand scenario parameters with the equivalent NZGP1 parameters
Note that our NZGP1 scenarios all reflect Tiwai aluminium smelter closing in 2024. The EDGS 2019 assume Tiwai does not close. This difference
accounts for a significant part of the difference between the NZGP1 and EDGS 2019 electricity demands and peak demands. The Tiwai aluminium
smelter consumes approximately 5 TWh of electricity per annum and contributes approximately 0.6 GW of peak demand.
NZGP1 Scenarios Update Transpower New Zealand Limited 11
Table 4 includes the same comparison for the EDGS 2019 generation scenarios and our NZGP1 generation scenarios.
Table 4 – A comparison of some EDGS 2019 and NZGP1 generation scenario parameters (continues on following page)
7. The term “2020 tuned” is further explained in the section “Tuning the generation scenario input assumptions”, page 17.
8. Excepting grid-scale solar in the NZGP1 scenarios. As discussed in the section on grid-scale solar, page 18, we have reduced the discount rate to 5% for grid-scale solar generation projects
NZGP1 Scenarios Update Transpower New Zealand Limited 12
Table 4 – A comparison of some EDGS 2019 and NZGP1 generation scenario parameters (continued from previous page)
NZGP1 Scenarios Update Transpower New Zealand Limited 13
75 75
70 70
65 65
60 60
National demand (TWh)
55 55
50 50
45 45
40 40
35 35
2020 2025 2030 2035 2040 2045 2050 2020 2025 2030 2035 2040 2045 2050
Year Year
EDGS 2019 Disruptive NZGP1 Disruptive NZGP1 Disruptive CCC Headwinds
EDGS 2019 Environmental NZGP1 Environmental NZGP1 Environmental CCC Tailwinds
EDGS 2019 Global NZGP1 Global NZGP1 Global CCC Current policy reference
EDGS 2019 Growth NZGP1 Growth NZGP1 Growth WiTMH Accelerated electrification
EDGS 2019 Reference NZGP1 Reference NZGP1 Reference WiTMH Business as usual
WiTMH Mobilise to decarbonise
Figure 1 – Comparison of EDGS 2019 and NZGP1 national Figure 2 – Comparison of NZGP1, CCC and WiTMH national
electricity demand scenarios to 2050 electricity demand scenarios to 2050
9. https://www.climatecommission.govt.nz/our-work/advice-to-government-topic/inaia-tonu-nei-a-low-emissions-future-for-aotearoa/modelling/
10. Transpower report: Opportunity to decarbonise our economy | Transpower
NZGP1 Scenarios Update Transpower New Zealand Limited 14
Considering the similarity between our NZGP1 scenarios The answer is that while the national electricity demand
and EDGS 2019 national electricity demand scenarios, the scenarios are similar, the peak demand profiles (on an
question might be asked as to why we are using EDGS 2019 hourly basis) behind each scenario, are more significantly
variations at all. Why not just use the original EDGS 2019 different. Figure 3 compares the daily national demand
demand scenarios? profile for a typical winter day in 2050 for both the EDGS
2019 and our NZGP1 scenarios. Our NZGP1 forecasts
have been built up from a base electricity forecast plus
individual forecasts for process heat, electric vehicles
and rooftop solar PV and these are shown individually.
8000 8000
6000 6000
National demand (MW)
4000 4000
2000 2000
0 0
-2000 -2000
0 5 10 15 20 25 30 35 40 45 0 5 10 15 20 25 30 35 40 45
Trading Period Trading Period
Base demand Batteries Solar Process Heat EV Charging Base demand Batteries Solar Process Heat EV Charging
Grid load Grid load
Figure 3 – Comparison of a daily demand profile for a typical winter day in both the EDGS 2019 and NZGP1 Reference scenarios
NZGP1 Scenarios Update Transpower New Zealand Limited 15
Not only do the individual forecasts that make up each Comparison of EDGS 2019 and NZGP1 daily demand profiles
scenario differ, but the overall peak demand for that day Reference Scenario of a winter day 2050
differs. Figure 4 compares the total peak demand lines 8500
from Figure 3 on a graph.
As seen, the NZGP1 peak demand is higher and this is 8000
the case across all scenarios. This is important from a
transmission planning perspective as the transmission
grid capacity we plan for depends upon peak electricity
0
Global Reference Growth Environmental Disruptive
Wairarapa wind generation c. We have used the Climate Change Commission (CCC)
gas price as reflected in their “All other CCC scenarios”
Our preliminary generation expansion plans built
assumption (included in their Emissions Budgets
significant (500 – 1000 MW) new wind generation in the
advice to government recently13), in our modelling.
Wairarapa from the late 2020’s to early 2030’s. We suspect
This equates to the following gas price assumption:
this is due to the high capacity factors for wind in this
region, compared to other regions, but at the same time,
we note a lack of interest from generation developers in 2030 2040 2050
this region, who we would expect to be talking to us if such Gas price, $/GJ 6.65 6.89 7.84
generation were to be built in that timeframe.
There are consented projects in the region which have Table 6 – Gas price assumption
not yet lapsed, but these projects do not appear to be
of immediate interest to generation investors. Given d. Similarly, we have used the CCC carbon costs from
the effect these projects would have on generation their recent Emissions Budget advice to government,
development and NZGP1 in particular, should they in our modelling. In their advice, the CCC outline carbon
proceed, we have not discarded them, but they are abatement costs that would be required to eliminate
flagged on the generation stack with a “not before fossil-fuel emissions from those sectors where there
2035” flag. are low-emissions alternatives and they use these
costs in their analysis. This equates to the
Other important variations following assumption:
a. Grid-scale batteries are included on our modified
generation stack. 2020 2030 2040 2050
b. Wind generation plant is assumed to have a 30 year Carbon cost, $/tonne CO2e 30 138 186 250
life in our model and approximately 670 MW of existing
wind generation reaches the end of its life during the Table 7 – Carbon cost assumption
period 2030 – 2050. Based on consultation feedback,
we have re-powered these sites, rather than assume
those plants are totally decommissioned. It is expected
that the cost of building a new windfarm on an existing
site will be considerably lower than building a new
windfarm elsewhere, so wind generators are likely to
re-power their existing sites. Not only will they be re-
powered but the replacement turbines are likely to be
significantly bigger.
In our modelling, we have assumed that all existing
windfarms are re-powered once the existing generation
reaches end-of-life and that the re-powered site will
have approximately 2.1 times the capacity it
had previously.
13. Ināia tonu nei: a low emissions future for Aotearoa » Climate Change
Commission (climatecommission.govt.nz)
NZGP1 Scenarios Update Transpower New Zealand Limited 20
e. We have used National Renewable Energy Laboratory Some other important assumptions
(NREL) learning curves to determine how the cost
Some other important assumptions included in the
of wind and solar generation will reduce over time.
NZGP1 scenarios, but which are not specific to the
These learning curves are widely used in the electricity
generation stack:
industry to reflect future cost declines. They assume a
cost factor of 1.0 in 2021, with a decrease over time. • New Zealand’s Aluminium Smelter at Tiwai Point closes
in 2024 in all scenarios.
Wind capital cost projections • Gas peakers are available all the way through to 2050,
1.2 and the model can build new gas peakers, if the model
decides this is economic.
1 • The Stratford gas plant, TCC, closes in 2023 and the
Huntly Rankine units close in 2030.
0.8
• A biofuel peaking plant can be built from 2035, if the
0.6
model decides it is economic. We have nominally
placed this at Huntly, however it could be connected
anywhere north of Whakamaru, without affecting this
0.4
particular investigation. We assume the following costs:
0.2
Cost element Cost
0 Capital costs ($/kW) 1030
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
2049
2051
2053
2055
2057
2059
Figure 6 – Wind capital cost projections over time Table 8 – Generation cost assumed for a biofuel peaking plant
The Reference scenario use the NREL moderate cost These cost result in relatively high cost generation, with a
projections for both wind and grid-scale solar generation. short-run marginal cost of $305/MWh.
0.8
0.6
0.4
0.2
0
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
2049
2051
2053
2055
2057
2059
Year
Solar ProdS0 Solar NREL Advanced
Solar ProdS1 Solar NREL Moderate
Solar CCC Solar NREL Conservative
Global scenario
20 Distrib. Batteries
Wind
14
National Installed capacity (GW)
Hydro
12 Biofuel
NI Process
10
NI Geothermal
8 Gas OCGT
Gas CCGT
6
NI Coal
Diesel
4
0
2025 2030 2035 2040 2045 2050
Time
Figure 8 – Total generation capacity over time, by technology in the NZGP1 Global scenario
The Global scenario sees the least amount of new generation built by 2050. Electricity demand rises by approximately
10% compared to now, with Tiwai closure in 2024 providing a similar amount of electricity to that demand increase. The
generation built is primarily to replace generation decommissioned, with the move toward a highly renewable electricity
system requiring more capacity to be built (thermal generation has a high capacity factor (approximately 90%), compared
to wind at approximately 40% and grid-scale solar at 20%. In this scenario 600 MW of biofuel plant is built, along with
approximately 1000 MW of new wind and 150 MW of new grid-scale solar.
NZGP1 Scenarios Update Transpower New Zealand Limited 22
Reference scenario
20 Distrib. Batteries
Wind
14
National Installed capacity (GW)
Hydro
12 Biofuel
NI Process
10
NI Geothermal
8 Gas OCGT
Gas CCGT
6
NI Coal
Diesel
4
0
2025 2030 2035 2040 2045 2050
Time
Figure 9 – Total generation capacity over time, by technology in the NZGP1 Reference scenario
In the Reference scenario, electricity demand grows by 28% by 2050, with a corresponding increase in new generation
build. A biofuel plant is also built in this scenario, a small amount of new geothermal, approximately 2000 MW of new wind
and 700 MW of grid-scale solar.
Growth scenario
20 Distrib. Batteries
Wind
14
National Installed capacity (GW)
Hydro
12 Biofuel
NI Process
10
NI Geothermal
8 Gas OCGT
Gas CCGT
6
NI Coal
Diesel
4
0
2025 2030 2035 2040 2045 2050
Time
Figure 10 – Total generation capacity over time, by technology in the NZGP1 Growth scenario
In the Growth scenario, we also see a biofuel plant being built, approximately 500 MW of new geothermal generation,
along with 2500 MW new wind generation and 1250 MW grid-scale solar generation.
NZGP1 Scenarios Update Transpower New Zealand Limited 23
Environmental scenario
20 Distrib. Batteries
Wind
14
National Installed capacity (GW)
Hydro
12 Biofuel
NI Process
10
NI Geothermal
8 Gas OCGT
Gas CCGT
6
NI Coal
Diesel
4
0
2025 2030 2035 2040 2045 2050
Time
Figure 11 – Total generation capacity over time, by technology in the NZGP1 Environmental scenario
In the Environmental scenario, we also see a biofuel plant being built, approximately 400 MW geothermal,
3000 GW of new wind and 1700 MW of grid-scale solar.
Disruptive scenario
20 Distrib. Batteries
Wind
14
National Installed capacity (GW)
Hydro
12 Biofuel
NI Process
10
NI Geothermal
8 Gas OCGT
Gas CCGT
6
NI Coal
Diesel
4
0
2025 2030 2035 2040 2045 2050
Time
Figure 12 – Total generation capacity over time, by technology in the NZGP1 Disruptive scenario
The Disruptive scenario reflects the highest growth in electricity demand in our scenarios and the model takes a slightly
different approach. It does not build a new biofuel plant. Rather it maximises geothermal build, builds a similar amount of
new wind to the Environmental scenario, but 2600 MW of grid-scale solar.
NZGP1 Scenarios Update Transpower New Zealand Limited 24
Global
70 Distrib. Batteries
60 Rooftop Solar
Wind
50
National annual energy generation
Hydro
(TWh, average hydro)
Biofuel
40
NI Process
NI Geothermal
30
Gas OCGT
Gas CCGT
20 NI Coal
Diesel
10
0
2020 2025 2030 2035 2040 2045 2050
Time
Figure 13 – Total generation over time, by technology in the NZGP1 Global scenario
Reference
70 Distrib. Batteries
60 Rooftop Solar
Wind
50
National annual energy generation
Hydro
(TWh, average hydro)
Biofuel
40
NI Process
NI Geothermal
30
Gas OCGT
Gas CCGT
20 NI Coal
Diesel
10
0
2020 2025 2030 2035 2040 2045 2050
Time
Figure 14 – Total generation over time, by technology in the NZGP1 Reference scenario
NZGP1 Scenarios Update Transpower New Zealand Limited 25
Growth
70 Distrib. Batteries
60 Rooftop Solar
Wind
50
National annual energy generation
Hydro
(TWh, average hydro)
Biofuel
40
NI Process
NI Geothermal
30
Gas OCGT
Gas CCGT
20 NI Coal
Diesel
10
0
2020 2025 2030 2035 2040 2045 2050
Time
Figure 15 – Total generation over time, by technology in the NZGP1 Growth scenario
Environmental
70 Distrib. Batteries
60 Rooftop Solar
Wind
50
National annual energy generation
Hydro
(TWh, average hydro)
Biofuel
40
NI Process
NI Geothermal
30
Gas OCGT
Gas CCGT
20 NI Coal
Diesel
10
0
2020 2025 2030 2035 2040 2045 2050
Time
Figure 16 – Total generation over time, by technology in the NZGP1 Environmental scenario
NZGP1 Scenarios Update Transpower New Zealand Limited 26
Disruptive
70 Distrib. Batteries
60 Rooftop Solar
Wind
50
National annual energy generation
Hydro
(TWh, average hydro)
Biofuel
40
NI Process
NI Geothermal
30
Gas OCGT
Gas CCGT
20 NI Coal
Diesel
10
0
2020 2025 2030 2035 2040 2045 2050
Time
Figure 17 – Total generation over time, by technology in the NZGP1 Disruptive scenario
Other aspects of our generation scenarios Grid-scale solar as % of new wind and solar capacity
in NZGP1 scenarios in 2050
The figures and tables that follow illustrate some
aspects of the scenarios. They are in no particular 60%
The following table shows the wind : solar ratios Figure 18 – Ratio of wind capacity to grid-scale solar capacity
(on an installed capacity basis) in each of our scenarios. in the NZGP1 generation scenarios
The Reference scenario is close to our target of 75%
wind : 25% solar, so we consider these scenarios
reasonably reflect the consultation feedback. The wind
: solar ratio does vary across scenarios, which usefully
builds in a sensitivity to this assumption. Interestingly,
a higher proportion of solar is built as 2050 electricity
demand increases.
NZGP1 Scenarios Update Transpower New Zealand Limited 27
Proportion of wind and grid-scale solar generation Wind and grid-scale solar generation as a
of total grid-connected generation capacity in 2050 % of total grid-connected capacity in 2050
New Zealand’s desire to have a highly, if not 100% 50%
renewable electricity system will rely heavily on wind
and grid-scale solar generation.
40%
Figure 19 shows the percentage of wind and grid-scale
solar generation capacity in our total generation mix,
30%
in 2050. As illustrated, these technologies reach almost
50% in the Disruptive scenario by 2050.
20%
The ratio of wind : solar is different from Figure 18 because
Figure 19 includes re-powered wind generation.
10%
0%
Global Reference Growth Environmental Disruptive
Wind % Solar %
Proportion of wind and grid-scale solar electricity Wind and grid-scale solar generation as a
generation as a % of total generation in 2050 % of total grid-connected energy in 2050
Following on from the previous observation, the 40%
percentage of wind and grid-scale generation
35%
dispatched in 2050 is shown in Figure 20.
30%
25%
20%
15%
10%
5%
0%
Global Reference Growth Environmental Disruptive
Wind % Solar %
4%
2%
0%
Global Reference Growth Environmental Disruptive
Wind generation repowering Retired and repowered wind generation in all scenarios
Figure 22 shows the MW of wind generation which 2000
reaches end-of-life in our scenarios and the re-powered
wind generation assumed to be built on the same site. 1500
Older technology turbines are assumed to be replaced
by newer and larger turbines, but fewer of them. The 1000
repowered capacity of these windfarms is approximately
2.1 times the capacity of the retired windfarm. 500
MW
0
-500
-1000
Global Reference Growth Environmental Disruptive
2
Region 2 includes the Bay of Plenty, Taupo volcanic zone, and
Hawkes Bay. Generation expansion withing this region is likely
1 2 to exacerbate the transmission constraint on the Wairakei ring
while reducing the need for upgrades in the Central North
Island and on the HVDC.
Figure 24 shows the wind repowering by region. Repowered wind generation, by region, by 2050
As seen, a significant majority occurs in Region 3.
1600
This reflects the high proportion of our current wind
1400
generation installed in the Manawatu/Wairarapa regions.
The wind capacity factor in those regions is the highest in 1200
New Zealand, which we presume is a significant factor.
1000
800
600
400
200
0
Global Reference Growth Environmental Disruptive
New wind generation capacity installed by region, New wind generation, installed capacity, by region,
by 2050 by 2050
Figure 24 shows which regions the wind repowering 5000
occurs in and Figure 25 shows the regions in which new 4500
wind generation is built. There is also a high proportion
4000
built in the lower North Island.
3500
3000
MW
2500
2000
1500
1000
500
0
Global Reference Growth Environmental Disruptive
Total wind generation capacity installed by region, Total wind generation, installed capacity, by region,
by 2050 by 2050
Figure 24 shows which regions the wind repowering 5000
occurs in. Figure 25 shows the regions in which new wind 4500
generation is built. Figure 26 adds these together to show
4000
the total wind generation installed, by region, by scenario,
by 2050. 3500
3000
MW
2500
2000
1500
1000
500
0
Global Reference Growth Environmental Disruptive
New grid-scale solar generation capacity installed Total grid-scale solar generation, installed capacity,
by region, by 2050 by region, by 2050
Figure 27 is the equivalent of Figure 25 for wind 3000
generation, but for grid-scale solar. As seen, the model
does not build any grid-scale solar in the lower North 2500
Island and builds the majority in the upper North Island.
This is consistent with our view of market expectations. 2000
MW
1500
1000
500
0
Global Reference Growth Environmental Disruptive
Renewables %
Another aspect of interest in our unconstrained grid scenarios is the renewables %, being the percentage of electricity
generated from renewable sources of electricity.
Rather than present this in diagrammatic form, we include Table 5, which shows the renewable %, by scenario, in each
of 2030, 2040 and 2050.
As shown, the renewables % increases over time and by 2050 all of our scenarios are over 99% renewable. We allow gas
peakers to remain in all scenarios and these still generate a small amount of electricity in 2050. It may be surprising that
they do not operate more often and this is likely to be due to the high carbon cost used in our modelling ($250 per tonne
by 2050). It is questionable whether it would actually economic to retain the gas peakers, given their low utilisation and in
practice we may see 100% renewables by 2050 because the gas peakers have been retired.
Please note that we classify geothermal generation as renewable for this calculation. Existing geothermal generation
is assumed to continue emitting CO2.
Renewables %
Table 9 – Renewables % - percentage of electricity produced from renewable generation, over time, by scenario
NZGP1 Scenarios Update Transpower New Zealand Limited 32
HVDC transfers
The following figures show electricity transfers across the HVDC inter-island link with an unconstrained HVDC link,
i.e. not limited by the capacity of the link today. The Investment Test will be used to determine the capacity which can be
economically justified under NZGP1. Northward (from the South Island to the North Island) transfers are shown as positive
and southward (from the North Island to the South Island) transfers as negative. Each set of three graphs show a snapshot
in 2030, 2040 and 2050 respectively.
1500 1500
1000 1000
HVDC South to North flow (MW)
0 0
-500 -500
-1000 -1000
-1500 -1500
-2000 -2000
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100
% time spent in exceedance % time spent in exceedance
Mean hydro P90 Maximum Exist. max northwards flow Mean hydro P90 Maximum Exist. max northwards flow
P10 Minimum Exist. max southwards flow P10 Minimum Exist. max southwards flow
Figure 28 – HVDC transfers in 2030 in the NZGP1 Global scenario Figure 29 – HVDC transfers in 2040 in the NZGP1 Global scenario
1500 1500
1000 1000
HVDC South to North flow (MW)
500 500
0 0
-500 -500
-1000 -1000
-1500 -1500
-2000 -2000
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100
% time spent in exceedance % time spent in exceedance
Mean hydro P90 Maximum Exist. max northwards flow Mean hydro P90 Maximum Exist. max northwards flow
P10 Minimum Exist. max southwards flow P10 Minimum Exist. max southwards flow
Figure 30 – HVDC transfers in 2050 in the NZGP1 Global scenario Figure 31 – HVDC transfers in 2030 in the NZGP1
Reference scenario
NZGP1 Scenarios Update Transpower New Zealand Limited 34
1500 1500
1000 1000
HVDC South to North flow (MW)
0 0
-500 -500
-1000 -1000
-1500 -1500
-2000 -2000
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100
% time spent in exceedance % time spent in exceedance
Mean hydro P90 Maximum Exist. max northwards flow Mean hydro P90 Maximum Exist. max northwards flow
P10 Minimum Exist. max southwards flow P10 Minimum Exist. max southwards flow
Figure 32 – HVDC transfers in 2040 in the NZGP1 Figure 33 – HVDC transfers in 2050 in the NZGP1
Reference scenario Reference scenario
1500 1500
1000 1000
HVDC South to North flow (MW)
500 500
0 0
-500 -500
-1000 -1000
-1500 -1500
-2000 -2000
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100
% time spent in exceedance % time spent in exceedance
Mean hydro P90 Maximum Exist. max northwards flow Mean hydro P90 Maximum Exist. max northwards flow
P10 Minimum Exist. max southwards flow P10 Minimum Exist. max southwards flow
Figure 34 – HVDC transfers in 2030 in the NZGP1 Growth scenario Figure 35 – HVDC transfers in 2040 in the NZGP1 Growth scenario
NZGP1 Scenarios Update Transpower New Zealand Limited 35
1500 1500
1000 1000
HVDC South to North flow (MW)
0 0
-500 -500
-1000 -1000
-1500 -1500
-2000 -2000
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100
% time spent in exceedance % time spent in exceedance
Mean hydro P90 Maximum Exist. max northwards flow Mean hydro P90 Maximum Exist. max northwards flow
P10 Minimum Exist. max southwards flow P10 Minimum Exist. max southwards flow
Figure 36 – HVDC transfers in 2050 in the NZGP1 Growth scenario Figure 37 – HVDC transfers in 2030 in the NZGP1
Environmental scenario
1500 1500
1000 1000
HVDC South to North flow (MW)
500 500
0 0
-500 -500
-1000 -1000
-1500 -1500
-2000 -2000
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100
% time spent in exceedance % time spent in exceedance
Mean hydro P90 Maximum Exist. max northwards flow Mean hydro P90 Maximum Exist. max northwards flow
P10 Minimum Exist. max southwards flow P10 Minimum Exist. max southwards flow
Figure 38 – HVDC transfers in 2040 in the NZGP1 Figure 39 – HVDC transfers in 2050 in the NZGP1
Environmental scenario Environmental scenario
NZGP1 Scenarios Update Transpower New Zealand Limited 36
1500 1500
1000 1000
500 500
0 0
-500 -500
-1000 -1000
-1500 -1500
-2000 -2000
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100
% time spent in exceedance % time spent in exceedance
Mean hydro P90 Maximum Exist. max northwards flow Mean hydro P90 Maximum Exist. max northwards flow
P10 Minimum Exist. max southwards flow P10 Minimum Exist. max southwards flow
Figure 40 – HVDC transfers in 2030 in the NZGP1 Figure 41 – HVDC transfers in 2040 in the NZGP1
Disruptive scenario Disruptive scenario
Disruptive scenario – 2050 In all scenarios, maximum northward flows (in the most
extreme dry year) exceed the capacity of the existing
2000
HVDC link and would also exceed the capacity of a 1400
MW transfer limit. This is due to Tiwai closure in 2024,
1500
which creates a surplus of SI hydro generation.
1000 In 2030, a 1400 MW capacity HVDC link would have
HVDC South to North flow (MW)
14. The term “tuned gen stack” means MBIE’s generation stack, but altered to reflect those changes
discussed in the report section “Tuning the generation scenario input assumptions”, page 17.
NZGP1 Scenarios Update Transpower New Zealand Limited 38
Battery build
The amount of grid-scale batteries built in our scenarios varies as shown in Table 12.
This build may seem low (excepting in the Disruptive b. Lake Onslow in the South Island is developed. A
scenario where widescale battery build occurs to manage pumped hydro scheme which stores enough water to
renewable generation intermittency) considering the generate about the same amount of electricity as the
amount of interest currently in building grid-scale Huntly Rankine units, or more, in a dry hydrological year.
batteries in New Zealand, the amount of batteries built c. A mixed North Island solution, which may include a
worldwide and the prediction that grid-scale battery costs mixture of solutions e.g.:
will decrease over time.
• Continued use of gas peaking plant
We observe that these grid-scale batteries are built
• Generation overbuild
exclusively for transmission purposes. Other grid-scale
batteries may also be built, to capture other value streams • A biofuel or hydrogen generation plant to effectively
for their owners, but these are not included as they would replace Huntly
have limited use from a transmission perspective.
• Smaller pumped storage project/s
Emissions budgets • Multi-fuel plant being installed in some industrial
We have not given thought yet, whether the CCC’s applications. These could be powered by some
recommended emissions budgets for New Zealand will mixture of electricity, gas, biofuel or hydrogen.
impact these scenarios. We will consider that in the The alternative which has the most impact on transmission
coming months and make adjustments if necessary, requirements is the Lake Onslow alternative. This is located
before publishing a short-list consultation document in the South Island, with most electricity demand being
in 2022. in the North Island. If Lake Onslow is developed, existing
Dry year reserve transmission between Lake Onslow and the North Island
may become congested. Although not reflected in our
How dry year reserve will be provided in the future NZGP1 scenarios, we will consider this alternative as a
is uncertain. sensitivity scenario in our NZGP1 analysis.
In our highest electricity demand scenario, hydro still Our current modelling reflects the Huntly Rankine units
provides 40% of our electricity in an average hydrological being closed in 2030 and the model has several options
year. This drops to 33% in a dry year and that shortfall is open to it in the event of a dry hydrological year:
provided using dry year reserve.
a. gas peakers can be used and new gas peakers built
Currently the Huntly Rankine units, fuelled using coal or
b. generation can be “overbuilt”. When this occurs,
gas, meet that shortfall. These units are retired by 2030
some generators are under-utilised in average
in our modelling and an alternative is required to ensure
hydrological years, but fully utilised when there
security of electricity supply over time.
is a dry hydrological year
Such alternatives are currently being considered – by both c. a biofuel (and/or hydrogen) peaking plant can be built,
market participants and MBIE’s Battery Project, with some effectively replacing the Huntly Rankine units
possibilities being:
d. incurring deficit i.e. not meeting demand.
a. Allow gas peakers to remain in the North Island, with This is a high cost option, but is included to
more being built as required. This would not achieve a avoid model infeasibilities.
100% renewables future (a feasible mix is approximately
95-97% renewables), but may be the least capital
intensive.
NZGP1 Scenarios Update Transpower New Zealand Limited 39
We find that gas peakers are not used very often and no If our scenarios had favoured any particular (yet uncertain)
new gas peaking is built in our scenarios (excepting a small approach, then we would have locked the resultant grid
amount in the Growth scenario, in 2045). We suspect that flows into our analysis. Because our scenarios utilise a
the $250 per tonne CO2e carbon price by 2050 means range of approaches to meet dry year security of supply,
that the model can minimise its cost by utilising other they minimise the effect of this significant uncertainty on
approaches to ensuring dry year security of supply. our analysis.
We observe a range of approaches being used in our We note that this should not be taken as a suggestion that
unconstrained grid scenarios and we conclude that these approaches might be best for New Zealand, or that
these scenarios are fit for purpose. The economics in our a mixed North Island solution is preferred, rather that we
scenarios do not clearly favour one approach over another have minimised the effect of this major uncertainty in the
and that we are not over-representing any one approach. scenarios to be used for our NZGP1 MCP.
The main approaches used are to overbuild generation (up
to 200 MW of geothermal is over built in some scenarios NZGP1 investment drivers
and up to 500 MW wind in other scenarios), build a biofuel Previous work identified the need for our NZGP1
replacement for the Huntly Rankine units (which could be investigation. It is worth noting the aspects of our
fuelled by biofuel or hydrogen) and in limited cases incur a unconstrained grid scenarios which support that need:
small amount of deficit i.e. do not meet demand. Table 13
• HVDC flows north increase significantly once Tiwai
shows the mix of approaches used in each scenario:
aluminium smelter is closed and investment to increase
the transfer capability north may be justified. Our
Dry year approach Year
investigation will consider senstivitiy scenarios where
NZGP1 Global 2035 2040 2045 Tiwai closure is deferred and where new Southland
demand emerges.
Biofuel
• The high amount of wind generation in the lower North
Overbuild Island may justify increasing the capacity of the grid
Deficit backbone between Bunnythorpe and Whakamaru.
NZGP1 Reference 2035 2040 2045 • Connection of new generation to the Wairakei Ring,
from new geothermal and Bay of Plenty may justify
Biofuel increasing the capacity of the Wairakei Ring.
Overbuild
Deficit
NZGP1 Growth 2035 2040 2045
Biofuel
Overbuild
Deficit
NZGP1 Environmental 2035 2040 2045
Biofuel
Overbuild
Deficit
NZGP1 Disruptive 2035 2040 2045
Biofuel
Overbuild
Deficit
Table 14 – Earliest commissioning dates for various enhancement options being considered in NZGP1
It should also be noted that the outcome of NZGP Stage 1 and Stage 2 will likely be advised
in 2022, which will provide information on the longer term.
NZGP1 Scenarios Update Transpower New Zealand Limited 41
Table 14 – Forecast electricity demand in TWh, by year, by NZGP1 scenario, out to 2050
NZGP1 Scenarios Update Transpower New Zealand Limited 42
Table 15 – Forecast electricity peak demand in MW, by year, by NZGP1 scenario, out to 2050
NZGP1 Scenarios Update Transpower New Zealand Limited 43
12 12
5.0
10 6.5 10
Energy (TWh)
Energy (TWh)
8 8
6.5
3.0 3.2
6 6 5.5
3.4
4.6 4.9 2.2
4 4 0.9 7.6 7.6
2.4
5.1 5.1 5.1 5.0
2 4.0 2 4.1
3.2 3.2 3.3 3.2 3.2 3.5
1.5 1.9 1.9 1.9 1.7
1.2
0 0
Global Reference Growth Environmental Disruptive Global Reference Growth Environmental Disruptive
EDGS 2019: Low Temp. Medium Temp. High Temp. EDGS 2019
NZGP1: Low Temp. Medium Temp. High Temp. NZGP1: Heavy Fixed Charging Light Smart Charging Light
Figure 43 – Comparison of 2050 process heat conversion Figure 44 – Comparison of 2050 electric vehicle electricity
electricity demand, in TWh, by scenario – EDGS compared demand, in TWh, by scenario – EDGS compared to NZGP1
to NZGP1
5
Energy (TWh)
6.4 6.4
3
4.6 4.6
2
3.9
3.1
2.8
1 2.3
1.1
0.9
0
Global Reference Growth Environmental Disruptive
EDGS 2019 NZGP1