Professional Documents
Culture Documents
HYDROGRAPH
INTRODUCTION
HYDROGRAPH
The graphical relation between any hydrological quantity (stage, velocity,
discharge, etc.) and the time is known as a hydrograph. Hydrographs are of three
types:
a. Discharge Hydrograph
b. Stage Hydrograph
c. Velocity Hydrograph
147
Effective Rainfall
As discussed under Hydrologic Cycle (Chapter One), all of the rain usually does
not go into the stream but a certain part of it reaches the stream and causes rise in
the stream-flow while the remaining part of rain is accounted for in various forms
of precipitation losses. The portion of rainfall which contributes to stream-flow is
called Effective Rainfall.
A useful index to define the location of the peak of the hydrograph is the basin
lag, which is the time difference between the center of mass of the rainfall and the
center of the mass of the hydrograph. Rise of the stream-flow depends upon the
effective rainfall and type of the soil, and time lag depends upon type of area and
also upon characteristics of rainfall (Figure 6.1).
148
Parts of a Hydrograph
The shape of the rising limb depends upon the storm characteristics which are the
duration of rainfall, intensity of rainfall, areal distribution of the rainfall, etc.
The crest segment is controlled by the storm characteristics and the distribution of
streams in the area, which further depends upon geological structure of the area.
The falling limb depends upon the control on storage release, which itself depends
upon the geological structure.
Components of Hydrograph
A hydrograph normally consists of the four components:
i. Channel Precipitation
ii. Direct Runoff (DRO)
iii. Inter Flow or Sub-surface Flow
iv. Ground or Base Flow
149
HYDROGRAPH ANALYSIS
Separation of Hydrograph Components
Hydrograph Analysis means dividing total runoff indicated by the hydrograph into
its (above-mentioned) components, of which direct runoff (DRO) and Base Flow
are more important.
Let us consider a hydrograph as shown in figure 6.3. From point ‘A’ draw a
straight horizontal line which meets the falling limb of hydrograph at point ‘B’.
Above line ‘AB’ is the direct runoff and below this line is the base flow. The
volumes of direct runoff and base flow (i.e. area under the curve) can be
calculated by any suitable method.
The Straight Line Method for separation of hydrograph has the advantage of
producing an extremely long time base for the direct runoff hydrograph. The time
base varies from storm to storm depending on the flow at the point of rise. It is a
computationally easy method.
150
b. Fixed Base Length Method
Let us have the hydrograph shown in figure 6.4. From point ‘A’ (existing prior to
the storm) extend the curve to point ‘B’ which is vertically below the peak. Now
draw a line from point ‘B’ to point ‘C’ on the hydrograph equal to a distance on
X-axis given by equation below:
N=Ad0.2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 6.1
Where,
N = Length of time in days, and
Ad = Drainage area in square miles
This line will meet the falling limb at, say point ‘C’. Join the point ‘B’ to ‘C’ by a
line ‘BC’. Area below ‘ABC’ is the base flow and that above it is the direct
runoff.
151
c. Variable Slope Method
This method is based on the fact that if water rises in the stream the water level in
the stream becomes greater than the adjoining ground water table level. As a
result the flow occurs from the stream to the groundwater and is stored there as
bank storage.
Refer to figure 6.5, below. Take a point ‘A’ on the previous recession curve, and
the line ‘AE’ by extending the previous recession curve. Point ‘E’ is under the
peak. Now take a point ‘B’ on the recession curve and extend it backward. Take a
point ‘C’ on recession
curve where the recession curve is changing slope, this point is called the point of
inflexion. Draw a vertical line from the point ‘C’. It cuts the line drawn backward
from point ‘B’, at point ‘D’. Join point ‘E’ and point ‘D’. The area under the line
‘AEDB’ shows the base flow component.
This method is not a well defined one. It depends upon experience, so it may vary
from one expert to another.
In general, Straight Line Method is the simplest and easiest but also the least
accurate. Fixed Base Method is widely used and gives practically good results.
152
Whereas Variable Slope Method is not commonly used and is difficult but can
give better results depending upon the expertise of the person using it.
The recession side of the hydrograph is formed of the surface recession, interflow
recession and base flow recession. Although the interflow, because of similar
characteristics, is taken as part of the surface runoff in the hydrograph analysis;
there are means to separate the three components on the basis of the exponential
recession equation of the form.
– t
Q = Q0 e δ - - - - - - - - - - - - - - - - - - - - - - - - - - 6.2
Where,
Q0 = initial discharge
Q = discharge a time interval afterwards
δ = recession constant
The equation can be written in a general form.
Q t+1 = Q t e -δt
Taking log on both sides
log ( Qt+1) = log (Q t e -δt)
log Qt+1 = log Qt - δt log e - - - - - - - - - - - - - - - - - - - 6.3
Graph of this equation for different recession constants ‘δ’ will give the
components of hydrograph.
153
A. Storm Characteristics
a. Intensity of Rainfall
The intensity of rainfall has a predominant effect on the shape of the hydrograph.
If other conditions remain the same, a higher intensity storm will produce a rapid
rise in the hydrograph and a higher peak than that in case of a low intensity
rainfall. Such floods give little warning time and so are dangerous.
b. Duration of Rainfall
c. Weather
B. Catchment Characteristics
a. Size of Catchment
The catchment area affects the stream-flow in a variety of ways. Even if the
intensity and depth of precipitation is assumed to be constant, the hydrograph of a
smaller catchment rises to its peak and then recedes more rapidly than that for a
larger catchment, because for the latter, it takes longer for the runoff to reach the
gauging station. The hydrograph of a larger catchment area, therefore, has broader
base than that of a smaller one. Moreover, the larger the area, the greater will be
the heterogeneity in soil and vegetation cover, with a consequent effect on the
stream-flow of each part of the catchment. The vegetation cover increases the time
of concentration.
154
b. Shape of the Catchment Area
The shape of the catchment area affects stream-flow by altering the time of
concentration and the pattern of drainage tributaries. If the length of the catchment
along the main stream is less than the width across the same stream, separate
runoff peaks generated by a heavy rainfall are likely to reach the gauging station at
the same time from the tributaries, with the result that the flood peak in the main
stream increases. Thus a hydrograph with a high peak and narrow base is
obtained.
However, if the length of the catchment along the main stream is larger than
width, the tributaries will be of shorter length and contribution from each tributary
area is likely to reach the gauging stations at intervals. After an intense storm
over the whole of the catchment area there will be some lag between the times at
which the peak from each tributary reaches the gauging station. The hydrograph
will therefore, have a low peak and broader base, because the remote tributaries
will continue contributing for some time even after the rainfall has stopped.
The elevation of the catchment also plays an important role in some hydrologic
characteristics of hydrograph, particularly due to variation in temperature and
precipitation. The temperature reduces with the increase in elevation with the
result that above a certain elevation, the temperature becomes so low that all
precipitation falls as snow. In the Indo-Pakistan Sub-continent, contribution from
areas at altitude 15,000 ft. above the mean sea level, is mainly due to snowmelt.
The floods from snowmelt are of usually low peak and broader base.
d. Catchment Slope
The slope of the catchment affects stream-flow by reducing the rate of infiltration
due to increased speed of water-movement towards drainage channels. The
steeper the slope, the faster will be the flow and rise in the hydrograph. The
hydrograph in such a situation will have higher peak and smaller base.
155
RATE OF RUNOFF
While designing hydraulic structures such as, we are mostly interested in
estimating maximum probable rate of runoff. Various methods of estimating
maximum probable rate of runoff are as under:
a. Frequency Analysis
b. Empirical Formulae
c. Flood Routing
Of the four methods of estimating maximum probable rate of runoff, the unit
hydrograph method is being discussed in detail in this chapter.
UNIT HYDROGRAPH
The T-hour unit hydrograph may be defined as a hydrograph of direct runoff
resulting from unit rainfall-excess of a duration ‘T’ hours having occurred
uniformly all over the catchment and having a constant rate of occurrences.
156
The unit hydrograph theory is based on principles of linearity of runoff to rainfall-
excess and superposition. This is a linear process applied to a non-linear situation.
a. Rainfall Duration
The volume under unit hydrograph is always the same for a given catchment and
is equal to one unit, say one inch of runoff ( note that volume of one inch of runoff
means that one inch of rainfall excess over the whole catchment. The actual
volume will be the catchment area multiplied by one ). Peak value for a lesser
duration unit hydrograph is higher and is sharp, but the peak value for a higher
duration unit hydrograph is lower with larger base length.
The unit hydrograph is based upon uniformly distributed rainfall over whole of the
catchment. So the actual flood hydrograph has to be estimated accordingly from
the unit hydrograph taking into account the effect of areal distribution of rainfall.
1. Select an isolated storm, for which reliable rainfall and runoff data are
available.
157
2. Separate the base flow from the total runoff hydrograph and calculate the
volume of direct runoff.
3. Divide the ordinates of direct runoff by the effective rainfall. The resulting
hydrograph is a unit hydrograph for the catchment area for the given
duration of rainfall-excess. Estimation of rainfall-excess is illustrated in
numerical Example No. 6.1, below.
A unit hydrograph derived from a single storm may have some error, and it is
desirable to average the unit hydrograph from several storms of the same duration.
This should not be an arithmetic average of concurrent coordinates; since, if peaks
do not occur at the same time, the average peak will be lower than many of the
individual peaks. The proper procedure is to compute the average of the peak
flows and times to peak. The average unit hydrograph is then sketched to conform
to those of the other graphs, passing through the computed average peak, and
having a volume of one-inch.
Example 6.1
From the data given in Table 6.1 below, derive a 6-hour unit hydrograph if this
data is obtained from a six-hour duration storm and the catchment area is 3,200
square kilometers.
159
Derivation of Hydrograph from a Unit Hydrograph
Example 6.2
Given the unit hydrograph of 4-hour duration (Table 6.3), calculate the ordinates
of total runoff hydrograph of same duration from an excess precipitation of 10 cm.
Assume constant Base Flow of 14 m3/sec.
160
Table 6.3: Data for unit hydrograph and derivation of total runoff hydrograph.
Solution
The rainfall-excess has been reported as 10 cm. The ordinates of unit hydrograph
are simply multiplied by excess rainfall to get ordinates of Direct Runoff (DRO).
Once the ordinates of DRO are obtained, base flow is added to it to get Total flow
ordinates. These computations are given in Table 6.4.
161
The unit hydrograph, DRO hydrograph and total hydrograph is shown in fig. 6.7
S Curve
Example 6.3
Given is a unit hydrograph of 2 hour duration (column 2 of Table 6.5). Derive the
2 hours duration ‘S’ curve.
162
Table 6.5: Ordinates of 2 -Hour Unit Hydrograph
Time (Hours) Flow (m³/s)
0 0
2 95
4 164
6 121
8 91
10 54
12 18
14 0
SOLUTION
First, we derive ‘S’ curve: The calculations are shown in Table 6.6. In this table
ordinates of unit hydrograph of 2-hour duration are given in column 2. Column 1
is time in hours. Other columns have ordinates in m³/s. Columns 3 to 14 show
lagged unit hydrographs. Column 15 is the addition which is the ‘S’ curve.
163
Table 6.6:
Unit hydrograph data and derivation of S curve.
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)
0 0 0
2 95 0 95
4 164 95 0 259
6 121 164 95 0 380
8 91 121 164 95 0 471
10 54 91 121 164 95 0 525
12 18 54 91 121 164 95 0 543
14 0 18 54 91 121 164 95 0 543
16 0 18 54 91 121 164 95 0 543
18 0 18 54 91 121 164 95 0 543
20 0 18 54 91 121 164 95 0 543
22 0 18 54 91 121 164 95 0 543
24 0 18 54 91 121 164 95 0 543
26 0 18 54 91 121 164 95 543
28 0 18 54 91 121 164
30 0 18 54 91 121
32 0 18 54 91
34 0 18 54
36 0 18
38 0
164
Derivation of Any Duration Unit Hydrograph
The procedure for derivation of any required duration unit hydrograph from a
given-duration unit hydrograph is described below:
Example 6.4
Given is unit hydrograph of 2-hours duration (Column (2), Table 6.5 of Example
6.3). Find 6-hours unit hydrograph for the same catchment.
Solution
The derivation of S curve is given in Example 6.3. Using that S curve the
derivation of 6 hours unit hydrograph is given below in Table 6.7.
Table 6.7: Derivation of 6 hours unit hydrograph from 2 hours unit hydrograph.
165
The given 2-hr hydrograph and developed 6-hr hydrographs are shown in Figure
6.9. It may be noted that increasing the duration of unit hydrograph has decreased
peak flow.
Composite Hydrograph
The stream-flow hydrograph may be due to more than one storm. In that case we
have to separate the effect of each storm. This is composite hydrograph
separation. Here the analogy is used that ordinates of composite hydrograph are
proportional to intensity of rainfall.
Example 6.5
Given is hydrograph resulting from two storms each of 6-hours duration (Table
6.8). The rainfall intensity of first storm is 0.8 cm and that of second storm is 0.6
cm each of 6-hr duration. Separate the hydrograph of both storms and find 6 hr
unit hydrograph for each storm.
166
Solution
i. Total rainfall is 0.8 + 0.6 = 1.4 cm. The contribution of second storm
relative to the first storm is 0.6 / 0.8 = 0.75. The ordinates of first
hydrograph are, therefore obtained by subtracting effect of second
hydrograph from composite hydrograph. Since second storm occurs 6
hours later than the first one, the first ordinate of composite hydrograph is
due to contribution of first storm. Therefore first ordinate of first
hydrograph is 750 - 0 = 750.
ii. The second ordinate is obtained by subtracting (0.6 / 0.8) x 750 = 562.50
from second ordinate of composite hydrograph i.e. 1400 - 562.50 =
837.50. The third ordinate of first storm hydrograph is obtained by
subtracting 0.75 x 837.50 = 628.12 from third ordinate of composite
hydrograph i.e. 1671.88 and so on. The calculations are shown in table 6.9.
iii. The ordinates of second hydrograph are obtained simply by subtracting
ordinates of first hydrograph from composite hydrograph.
iv. For unit hydrograph ordinates of each hydrograph are divided by their
respective rainfall intensities.
Table 6.8.
Data of Composite Hydrograph
Date Time Composite Date Time Composite Date Time Composite
Hydrograph Hydrograph Hydrograph
(Hours) (cumecs) (Hours) (cumecs) (Hours) (cumecs)
167
Table 6.9 Separation of Component Hydrographs
Date Time Composite First 6 Hour Second 6 6 Hour Unit 6 Hour Unit
Hydrograph Hydrograph Hour Hydrograph Hydrograph
Hydrograph (First Storm) (Second
Storm)
(Hours) (cumecs) (0.8 cm) (0.6 cm)
22-04-65 0 - - - -
6 750.00 750.00 - 937.50 -
12 1,400.00 837.50 562.50 1,046.88 937.50
18 2,300.00 1,671.88 628.13 2,089.84 1,046.88
23-04-65 24 3,000.00 1,746.09 1,253.91 2,182.62 2,089.84
30 7,000.00 5,690.43 1,309.57 7,113.04 2,182.62
36 13,000.00 8,732.18 4,267.82 10,915.22 7,113.04
42 23,000.00 16,450.87 6,549.13 20,563.58 10,915.22
24-04-65 48 29,700.00 17,361.85 12,338.15 21,702.31 20,563.58
54 25,000.00 11,978.61 13,021.39 14,973.27 21,702.31
60 19,100.00 10,116.04 8,983.96 12,645.05 14,973.27
66 15,000.00 7,412.97 7,587.03 9,266.21 12,645.05
25-04-65 72 11,400.00 5,840.27 5,559.73 7,300.34 9,266.21
78 9,300.00 4,919.80 4,380.20 6,149.74 7,300.34
84 7,800.00 4,110.15 3,689.85 5,137.69 6,149.74
90 6,300.00 3,217.38 3,082.62 4,021.73 5,137.69
26-04-65 96 5,700.00 3,286.96 2,413.04 4,108.70 4,021.73
102 4,800.00 2,334.78 2,465.22 2,918.47 4,108.70
108 4,000.00 2,248.92 1,751.08 2,811.14 2,918.47
114 3,700.00 2,013.31 1,686.69 2,516.64 2,811.14
27-04-65 120 3,300.00 1,790.02 1,509.98 2,237.52 2,516.64
126 2,900.00 1,557.49 1,342.51 1,946.86 2,237.52
132 2,600.00 1,431.88 1,168.12 1,789.85 1,946.86
138 2,100.00 1,026.09 1,073.91 1,282.61 1,789.85
28-04-65 144 1,700.00 930.43 769.57 1,163.04 1,282.61
150 1,300.00 602.17 697.83 752.72 1,163.04
156 900.00 448.37 451.63 560.46 752.72
162 600.00 263.72 336.28 329.65 560.46
29-04-65 168 - - - - -
Composite hydrograph along with component hydrograph is shown
in Figure 6.10.
Example 6.6
Develop a complex hydrograph for the following data given in Table 6.10, Take R2 / R1 =
1.2
Table 6.10
Time 0 1 2 3 4 5 6 7 8 9 10
q1 0 200 400 1000 2800 1400 900 700 480 200 0
Solution
169
Table 6.11 Hydrograph Data
TIME q1 Ordinates of Discharge Q of
q2=(R1/R2)xq1(n-1). complex
hydrograph
0 0 0
1 200 0 200
2 400 240 640
3 1000 480 1480
4 2800 1200 4000
5 1400 3360 4760
6 900 1680 2580
7 700 1080 1780
8 480 840 1320
9 200 576 776
10 0 240 240
11 0 0
Figure 6.11
170
Example 6.7
Repeat example 6.6 for the case when ordinates of Q are given (as shown in Table
6.12 below) for its separation into its components q1 & q2 with R1/R2 =1.2
171
Example 6.8
Develop a complex hydrograph for the following data given in Table 6.13, Take
R2 / R1= 1.2 and R3/ R1= 1.5
Solution
Table 6.14 below gives calculations for determination of q2, q3 and Q, in which
ordinates of q2 and q3 have been calculated by using modified but simple formulae
given in the table.
172
Figure 6.13 shows complex hydrograph.
Table 6.15 Calculations for Separation of Complex hydrograph (see Fig. 6.14)
N Time Discharge Ordinates of Ordinates of Ordinates of
Q of q1 = Qn - q2 = (R1/R2)x q1(n-1). q3=(R1/R3)x q1(n-2).
complex (R1/R2)xq1(n-1) -
hydrograph (R1/R3)xq1(n-2).
0 1 0 0
1 2 200 200 0
2 3 640 400 240 0
3 4 1780 1000 480 300
4 5 4600 2800 1200 600
5 6 6260 1400 3360 1500
6 7 6780 900 1680 4200
7 8 3880 700 1080 2100
8 9 2670 480 840 1350
9 10 1826 200 576 1050
10 11 960 0 240 720
11 12 300 0 300
12 13 0 0
173
Figure 6.14 Complex Hydrograph
Synthetic Hydrograph
a. Bernard’s method
b. McCarthy’s Method
c. Snyder’s Method
d. Taylor and Schartz Method
Of these, Snyder’s Method is the most commonly used method, which is briefly
described here.
Snyder’s method
174
Following are the steps involved in unit hydrograph construction according to
Snyder’s method.
Step (i)
tp = C1 Ct (L Lc)0.3 - - - - - - - - - - - - - - - - - - - - - - - - - (6.5)
Where,
tp = Basin Lag in Hours. Basin Lag is the time between centre of mass of
unit rain and peak flow (See Figure 6.15).
L = Distance from gauging station to catchment boundary.
Lc = Distance in kilometers between gauging station and cancroids of
catchment. It is measured from gauging station along the main stream to the point
nearest to cancroids of catchment.
Ct = A coefficient determined from the gauged catchment in same or
similar region. Its value ranges from 1.35 to 1.65.
C1 is a constant whose value in MKS system of units is 0.75.
Step (ii)
176
qPR - Peak Discharge from unit hydrograph derived for similar catchment.
If,
tPR = 5 tR then tR = tr
Else,
tPR = tp and qPR = qP
By back substitution, ‘Ct’ and ‘Cp’ can be determined from Equations (6.5) and
(6.6).
If,
tPR ≠ 5.5 tR , then the standard basin lag is
tP = tPR + tr-tR - - - - - - - - - - - - - - - - - - - - - - - - - - - (6.7)
4
Also, tp = 5.5 tr - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - (6.8)
Equations (6.7) and (6.8) are solved simultaneously for ‘tr’ and ‘tP’. ‘Ct’ and ‘Cp’
are then found from Equations (6.5) and (6.6) with conditions qPR = qP and tPR =
tp. (Figure 6.17)
Step (iii)
177
The Peak Discharge of required hydrograph is found using equation 6.9.
qPR = qP tp - - - - - - - - - - - - - - - - - - - - - - - - - - - - - (6.9)
tPR
Step (iv)
Step (v)
Width of Hydrograph ‘W’ is given by equation 6.11. The coefficient ‘Cw’ defines
value of peak discharge where width of hydrograph is required. For example,
width at discharge which is 75% and 50% of Peak discharge is to be calculated:
W = Cw qPR-1.08 - - - - - - - - - - - - - - - - - - - - - - - - - - (6.11)
For qPR = 75%, Cw = 1.22
For qPR = 50%, Cw = 2.14
(See Figure 6.7)
Example 6.10
Develop 3-hour and 6-hour unit hydrographs for a catchment area measuring
135.8 Sq. miles with following data:
Ct = 1.50, Cp = 0.60 L = 29.5 miles Lc = 15 miles
Also calculate total run-off in inches for the catchment in each case.
Solution
Step-1
tR = 3 hours > tr
Plot unit hydrograph using above calculated values. The graph is shown
in Fig 6.18 below. It has been plotted using definitions given in Figs. 6.16
and 6.17 above.
From Fig. 6.18, tabulate the values of discharge against equal time
interval of any length say at 6 hours interval (17*6 = 102 close to 101).
These values have been shown in Table 6.16
179
Fig. 6.18 Synthetic Hydrograph
180
Total run-off = [14690 x 6 x 60 x 60]
[24 x 60 x 60]
= 3672.50 sfd
= 3672.50 / 26.90
= 136.52 inches-mile
Run-off = 136.52 / 135.8
= 1.00 inch
tR = 6 hours > tr
Basin Lag, tPR = tP + [tR – tr]/4
= 9.33 + [6-1.70]/4
= 10.41 hours
Peak discharge, qPR = 640 x Cp x A /tPR
= 640 x 0.60 x 135.8/10.41
= 5009.34 cfs
Time base, TR = 3 x (1 + tPR /24)
= 3 x (1 + 10.41/24)
= 4.30 days
= 103 hours
50% of qPR = 2504.67 cusecs
W50 = 770 / [qPR / A ]1.08 = 770 / [5009.34 / 135.8 ]1.08
= 15.64 hours
75% of qPR = 3757.00 cusecs
W75 = 440 / [qPR / A ]1.08 = 440 / [5009.34 / 135.8 ]1.08
= 8.94 hours
Plot unit hydrograph using above calculated values. The graph is shown
in Fig 6.19 below. It has been plotted using definitions given in Figs. 6.16
and 6.17 above.
From Fig. 6.19, tabulate the values of discharge against equal time
interval of any length say at 6 hours interval (17*6 = 102 close to 101). These
values have been shown in Table 6.17
181
Fig. 6.19Synthetic Hydrograph
Table 6.17
Time (Hours) Q (cfs) Time (Hours) Q (cfs)
0 0 60 150.00
6 1880.00 66 110.00
12 4450.00 72 90.00
18 3800.00 78 80.00
24 1500.00 84 50.00
30 1050.00 90 30.00
36 600.00 96 20.00
42 350.00 101 (say 102) 0
48 250.00
Total 14610
54 200.00
182
QUESTIONS
1. Define Hydrograph and explain its significance in Hydrology.
3. Explain various methods for separating base flow from direct runoff in
hydrograph. Can a unit hydrograph used directly to forecast DRO and peak
of a flood, if the intensity of rainfall is not constant?
5. What is the practical significance of a unit hydrograph? What are the three
propositions of the unit hydrograph theory?
6. Explain the step by step procedure for deriving unit hydrograph from DRO
hydrograph and vice versa?
10. What is synthetic hydrograph? Explain the method employed for deriving
synthetic hydrograph. Comment on the merits and demerits of these
methods.
183
EXERCISE
Problem 6.1
Table P6.1 shows the ordinates at 24 hour intervals for a hydrograph. Separate the
base flow from the direct runoff. Compute the volume of DRO.
Problem 6.2
The hydrograph tabulated below in Table P6.2 resulted from a 6-hour period of
rainfall. Considering the base flow as 11 m³/s, find the 6-hour unit hydrograph for
the basin having 148 sq. km drainage area.
184
Problem 6.3
Given below in Table P6.3 is the data for the unit hydrograph resulting from a 4-
hours duration rainfall, for a certain basin. Derive the S-curve ordinates. Hence
derive the ordinates for unit hydrographs of 2-hours and 6-hours durations.
Problem 6.4
Table P6.4 shows the data for the hydrograph resulting from a 3-hours duration
rainfall for a catchment having area of 3,200 km². Derive the unit hydrograph.
Problem 6.5
185
Table P6.5 Discharge Data
Problem 6.6
The hydrograph of Table P6.6 resulted from three successive 6-hour period
rainfall, having runoff estimated as 1.5, 3.0 and 2.3 cm, respectively. The area of
the basin is 148.5 km². Assuming a constant base flow of 10 m³/s, derive the
ordinates of a 6-hour unit hydrograph for the basin.
Problem 6.7
The stream-flows due to three successive storms of 3.7, 6 and 2.7 cm of 6-hours
duration each on a basin are given in Table P6.7. The area of the basin is 51 km².
Assuming a constant base flow of 8.5 m³/s and index of 0.25 cm/hour, derive a
6 hour unit hydrograph.
186
Table P6.7 Discharge Data
Problem 6.8
Catchment A Catchment B
L = 39 km L = 45 km
Lca = 15 km Lca = 25 km
A = 250 km² A = 400 km²
For catchment A, a 2-h unit hydrograph was developed and was found to have a
peak discharge of 50 m³/s. The time to peak from the beginning of the rainfall
excess in this unit hydrograph was 9.0 h. Using Snyder’s method, develop a unit
hydrograph for catchment B.
Problem 6.9
A basin has 400 sq. km. of area, L=35 km and Lca = 10 km. Assuming Ct = 1.5
and
Cp = 0.70, develop a 3-hour synthetic unit hydrograph for this basin using
Snyder’s method.
187
Problem 6.10
Table P6.10 shows the ordinates of the 9-hour unit hydrograph for the entire
catchment of a river up to a dam site.
Use Snyder’s approach with necessary modifications for the shape of the
hydrograph.
Problem 6.11
Using Snyder’s method, derive the 6-hour unit hydrograph by using the following
data.
188