COST ESTIMATION FOR BUILDING CONSTRUCTION

Item Description Unit Quantity Rate (Rs.) Amount

1 Site cleaning Item 1 8,000.00 8,000.00

2 Manual excavation for trenches Cube 5 5,200.00 26,000.00

3 Gr(15) screed concrete Cube 0.75 52,000.00 39,000.00

4 RRM (6' X9') IN 1:5 Cement:Sand masonry Cube 8 45,000.00 360,000.00

5 D.P.C. in 1:3 Cement:Sand Masonry Sqr 2.3 10,200.00 23,460.00

6 4" thk block wall of 1:5 Cement:Sand masonry Sqr 16 17,200.00 275,200.00

7 4 1/2' x 6" Lintols Lf 190 625.00 118,750.00

8 Approved laterite soil filling and compaction upto 95% P.C. Cube 5 7,000.00 35,000.00

9 5/8 Thick 1:5 wall plastering and skim coat (Internal) Sqr 19 13,000.00 247,000.00

10 5/8 Thick 1:5 wall plastering (External) Sqr 11 13,500.00 148,500.00

11 1:2:4 Floor concrete Cube 1.4 57,000.00 79,800.00

1:1/2:3 Concrete for column foundation, Columns upto 1st


12 floor level and first floor slab Cube 3.9 72,000.00 280,800.00
TOTAL 1,641,510.00