You are on page 1of 24

Submittal Transmittal

Detailed, Grouped by Each Number

LC3 (R-15-085-BF-0) Project # RUH-CP-1502


Tel: Fax:

Date: 3/15/2016 Reference Number: 0514

Transmitted To: Hadi Omar Harb Transmitted By: Paul Teague


SSEM AECOM
P.O. Box 6341 P.O. Box 58806
Al Rashid Tower, 5th Floor 4 Floor, Tower 4, Tatweer Tower
Al Ma'athar Street 11515 Riyadh
11442 Riyadh Tel:
Tel: 4625511 Fax:
Fax: 4627804

Qty Submittal Package No Description Due Date Package Action


1 0119 - Special Conditions - 1 Method Statement for Shoring Work Reviewed -
Exceptions Noted

Transmitted For Delivered Via Tracking Number


Action Hand

Items Qty Description Notes Item Action


001 1 Method Statement for Shoring Reviewed - Exceptions
Work Noted

Cc: Company Name Contact Name Copies Notes

Remarks
Reviewed Exceptions Noted, Resubmission Required.

1. Please see attached.

Best Regards,

Signature Signed Date

Prolog Converge Printed on: 3/16/2016 Prolog KKIA Page 1


KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

METHOD STATEMENT FOR


SHORING WORK

Project Quality Manager: Project Manager:

ENGR. Amr Ibrahim Metwally ENGR. HADI OMAR HARB

Page 1 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

Table of Contents
1.0 Purpose ………………………………………………………………………………….. 03
2.0 Scope …………………………………………………………………………………….. 03
3.0 References and Standards …………………………………………………………… 03
4.0 Permits and Licenses …………………………………………………………………. 03
5.0 Equipment ………………………………………………………………………………..04
6.0 PPE Materials …………………………………………………………………………… 04
7.0 Resources and Manpower ……………………………………………………………. 04
8.0 Responsibilities of Key Personnel ………………………………………………….. 05
9.0 Methodology- Shoring Works ……………………………………………………….. 06
10.0 Health and Safety ………………………………………………………………………. 08

Appendices
Appendix 1.0- Job Risk Assessment ………………………………………………..09
Appendix 2.0- Related ITPs ……………………………………………………………11
Appendix 3.0- Checklist ………………………………………………………………. 12
Appendix 4.0- Pro forma Work Permit ………………………………………………23

Page 2 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

1.0 PURPOSE

The purpose of this method statement is to provide description of procedure and method for the
construction and installation of shoring works when working in areas of loose and unstable soil
condition. Also included are the necessary procedure to ensure health and safety of employees
with the requirement stipulated in the Contract Documents, as well as those in Saudi Construction
Specifications (ASTM and SASO-ISO)

2.0 SCOPE

This method statement covers the analysis, design and implementation of shoring structures to
support loose soil during excavation works for the foundation of LC3 Building and the different
trenches for underground utilities as part of the contract.

3.0 REFERENCES AND STANDARDS

Excavation works will be executed in accordance to the following references & standards:
a. Saudi Arabia Construction Specification.
b. Employers requirements, Materials Specification
c. Geotechnical Report, Material and Workmanship Specifications for Earthworks.
d. Master Plan. Contractor shall provide the following:
1. Specific code and standards to be used for this for the above
e. Approved with Comments (AWC) construction drawings. mentioned works.
f. Approved ITP for excavation works. 2. Where are supposed to be survey and geotechnical report
which are part of the due diligence of the contractor?
g. SSEM HSE plan and Job Safety Analysis. 3.Contractor to provide the copy of the approval of all mentioned
documents that is already been approved.
h. SSEM excavation works procedure and OHSA standards. 4. Contractor shall provide reference number of the SSEM HSE
i. Approved Quality Control & Quality Assurance. plan aubmitted or approved.
5. Contractor shall provide copy of all the drawings submiital with
ENGINEER approval and comments.
4.0 PERMITS AND LICENCES "ALL" work related shall be 6. Contractor shall provide copy of submitted ITP and its
approval.
define and identified by the 7. Contractor shall provide the copy of the mentioned "Master
a. Work Permit contractor. Then it shall be Plan"
b. Excavation Permit submitted and secure an All the above comments shall be provided by the contractor with
the copy of the approval before it can be used as a reference
c. Entrance Permit approval from the Authority and standard documents.
Having the Jurisdiction prior
d. Barricade Permit
to any work implementation
e. Equipment Permit on-site.

other work related permits should be


identified by the contractor.
Page 3 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

5.0 EQUIPMENT

The contractor (SSEM) will provide the following equipment in the implementation of Shoring
activities alongside excavation works.
Type of Equipment Units (No.)
Excavator 1
Crow Bars 6
Steel mallet, 2 kg. 2
Carpenter’s Basic Tools 1 lot

Table I. Equipment Intended for Excavation and Shoring Works.

6.0 PPE MATERIALS and Safety Equipment

Personal Protective Equipment (PPE) should be provided in order to perform all works in
accordance with the safety procedures and taking into consideration the importance of proper
preventive measures to ensure safety in the performance of work.
Type of Equipment
Safety Helmet
Safety Boots
Safety Glasses
Safety Masks
Coveralls
High Visibility Vests
Hand Gloves

Table II. Personal Protective Equipment Intended for Excavation

7.0 RESOURCES AND MANPOWER

The workforce including foremen and technicians are all with sufficient qualification and
experience. Equipment operators possesses applicable party certificates wherever
applicable/relevant.
Sub-contractor will be employed if there is need to catch up shortfalls or to accelerate progress.
List of subcontractor manpower will be made available once there company is
prequalified/accepted by the Engineer.
Any person required to undertake work associated with shoring works is accountable for:
Complying with the requirements of risk assessment management plan, any permits for work
Using personal protective equipment and safety equipment provided
Assisting in assessing risk
Attending training when required.
Only undertaking tasks they are competent to undertake (or are in training to Page 4 of 23
undertake with appropriate supervision)
Following reasonable instructions related to work associated with shoring
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

CONTRACTOR (SSEM)
Construction Manager
Site Engineer
Safety Engineer
Equipment Operators
Carpenters
Laborers
First Aiders

Table III. Manpower for Shoring Works

8.0 RESPONSIBILITIES OF KEY PERSONNEL

8.1 Construction Manager

The Construction Manager must mobilized the required materials, equipment and manpower
to do the job as required, and will monitor the activities. He must take note existing shortfall
and problems and discuss the same with the Project Manager. Corrective solutions must be
identified and applied to compensate for the shortfalls.
change to "shall"
8.2 QA/QC Engineer

The QA/QC Engineer will be responsible for the quality aspects of the works. He will assure
that the QA and QC plan will be implemented. The required SIR, WIR shall be submitted to
The Engineer. All required procedure in shoring works shall be followed to have a safe
working condition and quality requirements attained. He will proactively coordinate with the
site engineer and issue appropriate internal SOR when he see that performance of works
deviate from the approved.
Contractor shall include in the QA/QC Engineer scope " That workmanship shall not compromise the health and safety of the worker."

8.3 Site Engineer

The Site Engineer will be in charge for the supervision and implementation of all activities as
required in the specifications and drawing, especially in giving orders to Site foremen. Site
engineer is also in charge for the preparation and filing of reports.
Contractor shall include to the Site Engineer responsibility the submission and secure the approval of all site work related permits. Prior to the
implementation of works on-site.
8.4 Site Foreman
change to "shall"
The Site Foreman will be in charge for the supervision and implementation of various steps in
shoring works, as instructed by the Site engineer. The Site Foreman shall also keep record of
all work schedules, work production and daily safety issues.

Page 5 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

8.5 Safety Engineer

 Conduct the safety induction course to all personnel involved in the work.
 Monitor and supervise the risk assessment.
 Ensure that necessary Permit to Work is available.
 Ensure that the project’s method statement and risk assessment are understood and
understood, complied and applied in the worksite.
 Ensure that all workers are provided with sufficient information regarding workplace
hazards and planned control measures.

8.6 Safety Officer

 Supervision of equipment handling, oversee the installation of shoring.


 Ensure that relevant work permit is secured prior to start of work.
 Ensure that equipment is operational and certified.
 Ensure that all drivers/operators are qualified to operate the machines/equipment.
 Regular inspection and maintenance of the equipment.
 Perform other duties as instructed by the safety engineer.
shall
8.7 Professional Engineer (Deep Excavation Shoring)

 The Professional Engineer will be in charge for the design in compliance with project
specification and standards.
 The engineer may designate an experienced person on the worksite to conduct a regular
inspection.
 The designated person should adhere his comments (if any) to the contractor for
immediate rectification prior for final inspection. The engineer then issues an inspection
report and certification.

9.0 METHODOLOGY-SHORING WORKS

9.1 Sequence of Work

9.1.1 Design of proposed shoring, if needed against load to be supported.

9.1.2 Fabricate shoring, if needed according to drawing, height of excavation.

9.1.3 For trench excavation which needs shoring, install shoring at side of once initial
excavation starts.

Page 6 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

9.1.3.1 Push the shoring down as the excavation become deeper.

9.1.3.2 Once the desired depth is attained stabilize the side slope to provide
collapse.

9.1.4 For open excavation, fix the shoring if required once the desired depth is reached.

9.1.5 Proceed with construction when the side slope has been stabilized or if needed
install the shoring.

9.1.6 After completion of work, slowly remove the shoring and proceed with backfilling
work.

9.2 The hazards posed to workers working in excavation pit and trenches are potentially fatal.
Excavation failures can, however, be largely avoided by installing an adequately designed
support system. No worker should be permitted to work in an unsupported trench if the
existing soil structure is loose. Other precautions include the avoidance of external load from
construction vehicles and excavated spoil being stockpiled too close to the trench.

9.3 The use of adequate shoring, benching and side sloping is essential to control the risk of a
collapse or failure of open excavation. Construction of shoring system should consider the
following:

 The size and strength of the component members of the shoring


 Existing and changing ground conditions
 The loads and types of ground or soil conditions to be shored
 Static loads near excavation, e.g. spoil pile, buildings and structures
 Dynamic loads near excavation, e.g. traffic and excavation equipment
 Ground vibration, e.g. heavy traffic, mobile plant, and other activities.
 Difficulties or risks that other services may pose i.e. existing or proposed underground
services
 Location of utility services
 Safety during installation and removal.

9.4 Shoring of trench excavation should be constructed and implemented strictly in accordance
with the design and contract specifications.

9.4.1 In ground composed of moderately firm to firm soil, vertical trench sides may stand
unsupported for a considerable period of time, and hence installing of shoring may
be disregarded. However, moderate side slope must be provided to make the
excavation wall stable.

Page 7 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

9.4.2 When the ground condition is poor and has little or no “free-standing” time,
shoring/trench wall support should be installed in such a way that the trench wall
will not collapse.

9.4.3 After excavation works has been completed, proceed with next activities while
checking the integrity of shoring from time to time.

9.4.4 Where existing services crossing a trench or excavation line are encountered, timber
board support should be provided the services to prevent possible collapse or
damage.

9.4.5 After the works are completed, the support system will be extracted / dismantled in
the reverse order of its installation. Persons performing the work in the excavation
will not work outside the protection of the ground support system

10.0 HEALTH AND SAFETY

During the process of shoring and excavation works, the necessary welfare facilities shall be
provided at the project site. The workers shall be provided with safe drinking water, toilets, place to
eat their food and place to store their clothes.
Tower lights will be used during night time works and is essential for the safety of workers, the
equipment and the proper execution of work. Barriers around excavation area shall be installed.
All work related training and safety induction for this specific work shall be identified and define in this document by the contractor.
10.1 Issues

 The HSE Engineer has the responsibility for providing help advice to the supervisor who is
responsible for the work safety.
 No one shall enter an excavation unless it has been inspected and considered a safe
place to work in by immediate supervisor.
 Ensure that there is safe access to and from all excavation.
 Beware of slipping when using ladders in wet conditions.
 All employees must wear the appropriate personnel protective equipment.
 No person is allowed under loads handled by power shovels/excavators. Banks men must
be assigned to monitor the activities.
 Prior to start shoring/excavation, it must be determined whether underground utilities i.e.,
electric, telephone, sewer lines, etc. will be encountered.
 Proper slopes to be provided at sides of excavation.
 Provide protective barriers, shield systems complying with applicable standards.
 Support of shoring must be periodically checked to assure integrity of the system.
Emergency and rescue procedures or strategy
incident or accidents related to shoring works.
monitoring and evaluation frequency of inspections
Risk Assessment Page 8 of 23
Risk control
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

JOB RISK ASSESSMENT:


Contractor shall identify and define all the work related risk on the shorin works.

Page 9 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0

Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

Page 10 of 23
CONSTRUCTION OF LOAD CENTER 3 (LC-3) AT KING KHALED INTERNATIONAL AIRPORT (KKIA)
INSPECTION TEST PLAN FOR CIVIL WORKS
CONTRACTOR: SAUDI SERVICES ELECTRO MECHANICAL WORKS. CO. (SSEM) (Close Joint Stock Company) ITP Ref. No.: ISSUANCE: 01
CONTRACT NO.: R-15-085-BF-0 Sec No.: REVISION: 00
TITLE: CIVIL WORKS Sec Title.: Date: October 2015
Method of
Activity Inspection / Test Requirements Reference Documentation Demonstrated Evidence
Activity Description Verification
No. Report/Checklist
Test or Inspection Performed Stage / Frequency Test Required Code/Spec/Etc. Acceptance Criteria SSEM AECOM
2.0 EXCAVATION AND BACKFILLING
2.1 EXCAVATION
Prior to Proceed for
2.1.1 Availability of permit Verification of Permit SSEM CHECK Tender Requirements Valid Permit H R Checklist Form IC-C-002
Excavation
Check Approved Survey Data Prior to Proceed for Approved Construction
2.1.2 Location and Layout of area to be excavated SSEM CHECK Technical Specification H W Checklist Form IC-C-002
Layout Excavation Drawings
Checking and grading and elevation for Prior to Proceed for Technical Specification Approved Construction
2.1.3 Visual Inspection/Survey SSEM CHECK H W Checklist Form IC-C-002
conformity to drawing Excavation Civil Works Drawings
Check the excavated area for freedom from Prior to Proceed for Technical Specification
2.1.4 Visual Inspection SSEM CHECK Project Specification W S Checklist Form IC-C-002
extraneous materials and water Excavation Civil Works
Technical Specification Approved Designated
2.1.5 Disposal of excavated materials Visual Inspection During Excavation SSEM CHECK W S Checklist Form IC-C-002
Civil Works Disposal Area
2.2 BACKFILLING
Check fill materials for conformity to Technical Specification Test Result Compliance w/
2.2.1 Soil Classification Approved Stock File Third Party Test H R Checklist Form IC-C-002
specifications Civil Works A9010 Part I Sec.2.1 the Project Specification
Check foundation for Bitumen coating for Technical Specification
2.2.2 Visual Inspection Before Backfilling SSEM CHECK Project Specification H W Checklist Form IC-C-002
polyethylene covering Civil Works
Field Density Test (ASTM
Check thickness of Backfill layer and 4 Random FDT at least Technical Specification
2.2.3 D1556) Nuclear Density Test Third Party Test Project Specification S/H W Checklist Form IC-C-002
Compaction per lot of 2,500 sq.m. Civil Works A9010 Part I Sec.2.1
(ASTM D2922)
TRENCHING AND BACKFILLING OF
3.0
PIPELINES
3.1 TRENCHING
Prior to Proceed for
3.1.1 Availability of permit Verification of Permit SSEM CHECK Tender Requirements Valid Permit H R Checklist Form IC-C-003
Trenching
Approved Construction
Location and Layout of area to be trenched and Prior to Proceed for Technical Specification
3.1.2 Visual Inspection/Survey SSEM CHECK Drawings/Client As-Built H W Checklist Form IC-C-003
mark the routing of existing underground utilities Trenching Civil Works
Drawings
Checking grading and elevation for conformity to Prior to Proceed for Technical Specification Approved Construction
3.1.3 Visual Inspection/Survey SSEM CHECK H W Checklist Form IC-C-003
drawing Trenching Civil Works Drawings
Ensure proper care to avoid damages to existing Technical Specification Client Engineering
3.1.4 Visual Inspection During Trenching SSEM CHECK S W Checklist Form IC-C-003
utilities Civil Works Standard
Check the excavated area for freedom from Technical Specification
3.1.5 Visual Inspection During Trenching SSEM CHECK Project Specification H W Checklist Form IC-C-003
extraneous materials and water Civil Works
Technical Specification Approved Designated
3.1.6 Disposal of excavated materials Visual Inspection After Excavation SSEM CHECK S/H S Checklist Form IC-C-003
Civil Works Disposal Area

N/A – NOT
ABBREVIATIONS: W- WITNESS PONT S– SURVEILLANCE AECOM- Consultant
APPLICABLE
SSEM-
Note: H– HOLD POINT RR – REVIEW OF REPORT Page 11
Contractor of 23
Page 1 of 1
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
EXCAVATION, BACKFILLING and SPOILING CHECKLIST
Project: Construction of New Load Center-3 IC Checklist No.: 085-IC-C-002
Contract No.: R-15-085-BF-O ITP Ref. No.: 085-ITP-C-2.0
Facility Name: Sec.:
Drwg. No. / Line No.: Area/Location:
Work / item for Inspection:

Item Activity SSEM SSEM GACA/AECOM Corr. Remark


Engr. QC Representative Sign s
A R N/A Off
1 EXCAVATION
1.1 Excavation Permit
1.2 Location, Layout of area to be
excavated
1.3 If any existing service lines,
utilities & utility structures which
are to remain in service are
uncovered or encountered
during operations, they shall be
safeguard, protected from
damage and supported
1.4 Provide bracing, shoring,
sheeting, sheet piling,
underpinning or other retaining
structures necessary to protect
against any movement or
settlement of existing structure
or utilities near the excavation
area
1.5 Line and grade of excavated
area is as per plan &
specification
1.6 Rock, loose rock, boulders and
other material unacceptable for
subgrade shall be excavated to
an extra depth of minimum 250
mm below the top of the
subgrade (the formation level)
or as instructed by the
Engineer.
1.7 The extra depth, that results
due to rock removal or
excavation of other
unacceptable material, shall be

Page 12 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
refilled with approved fill
material, obtained from the
specified excavation and shall
be compacted as specified.
1.8 All loose or protruding rocks on
the back slopes of the cuts
shall be barred loose, or
otherwise removed to the line
of finished grade or slope.
1.9 Blasting, when necessary, will
be permitted only when the
operations are approved by the
Engineer, all permissions are
obtained (appropriate
authorities) and proper
precautions have been taken
for the protection and safety of
all persons, the work and the
property. All damage done to
the work or property shall be
repaired at the contractor’s
expense. Any approval given
will not relieve the contractor of
his responsibility in blasting
operations.
1.10 Areas within the airport
property where borrow
excavation takes place shall be
indicated in the drawings. They
will only be available after a
written agreement from the
Engineer has been obtained.
1.11 When source for borrow
excavation are outside the
airport property, it shall be the
contractor’s responsibility to
locate the source and obtain
the required permits, subject to
the approval of the Engineer.
1.12 The Contractor shall notify the
Engineer sufficiently in advance
of the beginning of borrow
excavation so that the
necessary measurements and
test can be made.

Page 13 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
1.13 All borrow pits shall be opened
up to expose the vertical face of
various strata of acceptable
material, to enable obtaining a
uniform product. All work
involved with clearing, stripping
and removal of unacceptable
materials from borrow pits shall
be excavated to regular lines to
permit accurate measurements
and shall be drained and left in
a neat and presentable
condition with all slopes
dressed uniformly.
1.14 All suitable material from
drainage excavation shall be
placed in specified fill areas
and unsuitable material shall be
used, for topsoiling purpose of,
as instructed.
2 BACKFILLING
2.1 Material for backfilling approved
2.2 For structure, check first the
foundation for bitumen coating
or polyethylene cover before
backfilling
2.3 Compaction of finish surface to
receive fill material is in
accordance with the
specification
2.4 Fill structures shall be
constructed with acceptable
material, as specified, placed in
successive horizontal layers of
not more than 200 mm in loose
depth, for the full width of the
cross section, unless otherwise
approved by the Engineer.
2.5 The grading operations shall be
conducted, to produce a soil
structure as shown on the
typical cross section or as
directed. Material such as
brush, hedge, roots, stumps,
grass and other organic matter,

Page 14 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
shall not be incorporated or
buried in the fill structure
2.6 Stones or fragmentary rocks
larger than 100 mm in their
greatest dimensions shall not
be allowed in the top 150 mm
of the fill structure.
2.7 The material in the layers shall
be within ±2% of the optimum
moisture content before rolling
to obtain the specified
compaction. Wetting or drying
of the material and
manipulation to secure a
uniform moisture content
throughout the layer may be
required. Should the material
be too wet to permit proper
compaction or rolling, all work
on all of the affected portions of
the fill structure shall be
delayed until the material has
dried to the required moisture
content. Sprinkling of dry
material to obtain the proper
moisture content shall be done
with the approved equipment
that will satisfactory distribute
water. Sufficient equipment to
furnish the required water shall
be available at all times.
2.8 Compaction areas shall be kept
separate and no layer shall be
covered by another layer until
the proper density shall be
obtained. Rolling operations
shall be continued until all
layers are compacted to not
less than the specified
compaction.
2.9 Any areas inaccessible to a
roller shall be compacted by
mechanical tampers.
2.10 During construction of fill the
Contractor shall route his

Page 15 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
equipment at all times, both
when loaded and when empty,
over the layer as they are
placed and shall distribute the
traffic evenly over the entire
width of the fill.
2.11 Fill operations shall be
suspended at any time when
satisfactory results cannot be
obtained because of adverse
weather or other unsatisfactory
conditions in the field.
2.12 Tests shall be taken at
specified intervals. Based on
this tests the Contractor shall
make corrections and
adjustments in work method or
moisture content in order to
achieve the specified
compaction.
2.13 Any area found to lack the
required compaction shall be
further compacted or watered
and/or scarified, or otherwise
manipulated as the Engineer
may instruct, until the specified
compaction is obtained.
2.14 Rock fill shall be brought up in
layers not exceeding 0.60 mm
and every effort shall be made
to fill the voids with the finer
material to form a dense,
compact mass.
2.15 Each (rock) layer shall be
levelled and smoothed with the
suitable grading equipment and
by distribution of spalls and
finer fragments of rock.
2.16 Rock fill shall not be applied in
the top 1.2 meters of the
finished subgrade.
2.18 Density requirements will not
apply to portions of fill structure
constructed of materials which
cannot be tested in accordance

Page 16 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
with specified methods (like
rock fill).
2.17 Proceed backfilling to another
layer if preceding layer is in
accordance with the required
density, lines and grade
3 SPOILING
3.1 The Contractor shall during his
Site inspection in the tender
period, contact the employer to
obtain information regarding the
destination of unacceptable
materials and surplus materials.
These materials remain the
property of the Employer unless
the Employer transfers his
ownership to the Contractor.
3.2 Unacceptable materials and
surplus materials that are
released by the Employer, shall
become the property of the
Contractor. They shall not be
spoiled or stockpiled on site
and shall be removed off the
airport property.
3.3 The Contractor shall make his
own arrangements with other
public agencies, the
municipality or private
companies or landowners for
the spoiling of unacceptable
and surplus materials that
became his property.
3.4 The surface elevation of spoil
areas shall not extend above
the surface elevation of
adjacent areas. The spoil
material shall be placed/spoiled
and compacted to a reasonable
density as instructed by the
Engineer. All spoil areas shall
be graded to allow positive
drainage of the area itself and
of adjacent areas. If required,
the spoil area and adjacent

Page 17 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
areas shall be put into condition
acceptable for seeding or
planting.
4 TOLERANCES
4.1 In those areas upon which any
pavement construction is to be
placed, the top of the subgrade
shall not vary from the design
levels by more than 15 mm.
The finished levels shall be
determined by taking level in a
grid of 10 by 10 percent of the
measurements exceed the
specified tolerance, but are less
than 20 mm.
4.2 In areas outside pavement
constructions the top of the
formation shall not vary from
the design levels shall be
determined by taking levels in a
grid of 20 x 20 meters or less. A
lot will be accepted for grade if
not more than 10 percent of the
measurements exceed the
specified tolerance, but are less
than 40 mm.
4.3 The size of a lot shall be
between 2,500-5,000 m2.
4.4 Any deviation in excess of the
above tolerances shall be
corrected by reshaping and
compaction of the material.
GACA/AECOM Representative Remarks: Legend: A=Acceptable; R=Rejected; N/A=Not
Applicable

SSEM QC Representative GACA / AECOM Representative


Sign: Sign:
Name: Name:
Date: Date:

Page 18 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
TRENCHING AND BACKFILLING OF PIPELINES CHECKLIST

Project: Construction of New Load Center-3 IC Checklist No.: 085-IC-C-003


Contract No.: R-15-085-BF-O ITP Ref. No.: 085-ITP-C-3.0
Facility Name: Sec:
Drwg. No. / Line No.: Area/Location:
Work / item for Inspection:

Item Activity SSE SSE GACA/AECOM Corr.


Remarks
M M Representative Sign
Engr. QC A R N/A Off
1 TRENCHING
1.1 Obtaining permit of excavation
1.2 Location and layout of area to
be excavated
1.3 Trenches may be excavated
manually or with mechanical
trenching equipment. Walls of
trenches shall be essentially
vertical so that a minimum of
surfaced is disturbed.
1.4 Graders, scrapers or bulldozers
shall not be used to excavate
the trench.
1.5 The bottom surface of trenches
shall be essentially smooth and
free from coarse aggregate.
Unless otherwise specified,
trenches shall be excavated to
a design depth for the pipe
lines. Trenches for piping and
utilities shall not be less than
400 mm nor more than 600 mm
wider than the outside diameter
of the pipe to be laid therein.
Bottoms of the trenches shall
be accurately graded with bell
holes scooped out to provide
uniform bearing and support of
pipe and utilities on undisturbed
soil throughout their entire
length except where other
means of supporting pipe are
indicated. Rock materials shall
be excavated to 150 mm below

Page 19 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
pipe invert and bed backfilled
with fine sand and well tamped
in place.
1.6 When rock excavation is
encountered, the rock shall be
removed to a depth of at least
0.8 m below finished grade.
Rock excavation shall consist
of the removal of boulders and
detached rock ½ cubic meter in
volume or greater, and of all
rock in place in ledges or
masses which can be removed
only by the use of bars and
sledges or by blasting.
1.7 Before any rock is removed the
Engineer shall have the
opportunity to obtain the
necessary data to determine
the quantity.
1.8 The Contractor shall excavate
the trenches to a width not less
than 0.3 m.
1.9 At all times during the
construction, the trenches shall
be kept free of standing water.
1.11 Grading and elevation
conformed to drawing
1.10 Disposal of excavated material
2.0 EXCAVATION NEAR EXISTING FACILITIES
2.1 These trenches shall be
excavated manually in order to
avoid damages to existing
cables and utilities
2.2 Any damage to existing cables
or utilities shall be immediately
reported to the Engineer and
the relevant Authorities, and
shall be promptly repaired or
replaced by the Contractor at
his own expense and in a
manner and with materials as
required by the Engineer or the
Authorities.
2.3 If the Authorities required that

Page 20 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
the repair of damaged cables or
utilities shall be carried out by
their own workmen or by other
Contractors, then the Employer
shall be entitled to recover from
the Contractor the cost thereof
or may deduct the cost from
any payment due or that
become due to the Contractor.
2.4 Special attention shall be paid
to the sections of existing
cables, which have to remain in
use or be re-used for
intermediate power supply
upon completion of the works.
Therefore, the Contractor shall
determine the exact location of
these cables, whether indicated
on the drawings or not, before
staring any of his operation in a
particular area.
3 BACKFILL, PROTECTION AND DISPOSAL OF SURPLUS MATERIAL
3.1 Backfilling may proceed until all
required tests are performed &
until the piping systems, as
installed, comply with the
requirements in the
specifications
3.2 Bedding and fill materials
conformed to specifications
3.3 Pipes are in correct position
and restrained in place
3.4 Check thickness of backfill
layers & compaction and
compactness test
3.5 The tolerance of backfill is +25 /
-25 mm
4.2 CLEANING UP OF SITE
4.3 All areas disturbed by the
trenching, storing of dirt, and
other work shall be restored to
its original condition. The
restoration shall include any
necessary top soiling, seeding
or planting.

Page 21 of 23
 



CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL


AIRPORT
GACA/AECOM Representative Remarks: Legend: A=Acceptable; R=Rejected; N/A=Not
Applicable

SSEM QC Representative GACA / AECOM Representative


Sign: Sign:
Name: Nam
e:
Date: Date
:

Page 22 of 23
SSEM-HSE/PERMIT/002/M07-11, Rev0.1, July2011

SHORING WORK PERMIT


DATE: ______________________PERIOD: __________________TO:__________________PERMIT NO.:_______________

EQUIPMENTS: _______________________________________________________WORK AREA: ______________________

DESCRIPTION OF WORK:_________________________________________________________________________________

NAME OF THE ORIGINATOR:


COMPANY: DEPARTMENT: SIGNATURE:

PERFORMING AUTHORITY COMPLEMENTARY PERMITS YES NO N/A


DRIVING IN UNAUTHORISED AREAS
NAME: CLEARANCE FROM YERP AUTHORITY
SIGNATURE & DATE: CLEARANCE FROM ROYAL COMMISSION
CONTACT NO: CLEARANCE FROM OTHER DEPARTMENTS

RISK ASSESSMENT SAFETY PRECAUTUONS


YES NO N/A YES NO N/A
PERSONAL PROTECTIVE EQUIPMENT (P.P.E)
ELECTRICAL ISOLATION
BARRICADES AND WARNING SIGNS
METHOD STATEMENT / JSA AREA IS SUITABLE FOR CONCRETE REPAIR WORK
ENOUGH ACCESS/EGRESS ADDITIONAL ILLUMINATION
SUFFICIENT PROPER ACCESS
SCAFFOLDING/PLATFORMS ACCESS/EGRESS CLEAR FROM OBSTACLES
AREA CLEAR FROM COMBUSTIBLE FIRE EXTINGUISER / FIRE WATCHMAN
SUBSTANCES LIFE LINES/ SAFETY HARNESS
ANY OTHER WORKS ADJACENT BREATHING EQUIPMENT
EMERGENCY RESCUE TEAM AVAILABLE.
ISOLATION FROM OTHER WORKS SLOPING OR SHIELDLING PROVIDED
AREA CLEAR FROM TOXIC GASES NO MATERIAL KEPT NEAR THE EXCAVATION
EXISTING TEMPORARY OR GAS CYLINDERS KEPT OUT FROM THIS AREA
PERMANENT UTILITIES WORKERS AWARE OF HAZARDS AND PRECAUTUONS
SUITABLE EQUIPMENT AND TOOLS TO BE TAKEN
AVAILABLE

OTHER REQUIREMENTS (IF NECESSARY)

DECLARATION (to be filled by Performing Authority) And Competent Person


I, UNDERSIGNED HAVE CHECKED THE AREA AND COMPLIED TO ALL SAFETY PRECAUTIONS AND RISK ASSESSMENT AND WILL CARRY OUT ACTIVITY WITH
APPROVED METHOD STATEMENT
NAME: SIGN: NAME: SIGN:

PERMIT VALIDITY (to be filled by Site Manager/Engineer)


THE ABOVE WORK HAS BEEN APPROVED AND SHALL BE CARRIED OUT SAFELY. IT HAS TO BE ENSURED THAT THE EMPLOYEE EXECUTING THE JOB HAS A COPY
OF THE PERMIT AT ALL TIMES DURING THE WORK.
NAME: SIGNATURE: DATE:

PERMIT CLEARANCE (to be filled by HSE/Safety Representative)


I DECLARE THAT ALL WORK UNDER MY CONTROL HAS NOW BEEN COMPLETED AND THE AREA HAS BEEN CLEARED AND THAT ALL TOOLS AND OTHER
EQUIPMENT HAVE BEEN REMOVED
NAME: SIGNATURE: DATE:
PERMIT CLOSED (to be filled by Performing Authority)
THE ABOVE WORK WAS COMPLETED SAFELY AND THE WORK PERMIT SHALL BE CANCELLED
NAME: SIGNATURE : DATE:
SAFETY DEPARTMENT:
NAME: SIGNATURE: DATE:
Yellow- Site Blue - HSE office White - Client Office
Page 23 of 23

You might also like