Professional Documents
Culture Documents
Remarks
Reviewed Exceptions Noted, Resubmission Required.
Best Regards,
Page 1 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3
Table of Contents
1.0 Purpose ………………………………………………………………………………….. 03
2.0 Scope …………………………………………………………………………………….. 03
3.0 References and Standards …………………………………………………………… 03
4.0 Permits and Licenses …………………………………………………………………. 03
5.0 Equipment ………………………………………………………………………………..04
6.0 PPE Materials …………………………………………………………………………… 04
7.0 Resources and Manpower ……………………………………………………………. 04
8.0 Responsibilities of Key Personnel ………………………………………………….. 05
9.0 Methodology- Shoring Works ……………………………………………………….. 06
10.0 Health and Safety ………………………………………………………………………. 08
Appendices
Appendix 1.0- Job Risk Assessment ………………………………………………..09
Appendix 2.0- Related ITPs ……………………………………………………………11
Appendix 3.0- Checklist ………………………………………………………………. 12
Appendix 4.0- Pro forma Work Permit ………………………………………………23
Page 2 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3
1.0 PURPOSE
The purpose of this method statement is to provide description of procedure and method for the
construction and installation of shoring works when working in areas of loose and unstable soil
condition. Also included are the necessary procedure to ensure health and safety of employees
with the requirement stipulated in the Contract Documents, as well as those in Saudi Construction
Specifications (ASTM and SASO-ISO)
2.0 SCOPE
This method statement covers the analysis, design and implementation of shoring structures to
support loose soil during excavation works for the foundation of LC3 Building and the different
trenches for underground utilities as part of the contract.
Excavation works will be executed in accordance to the following references & standards:
a. Saudi Arabia Construction Specification.
b. Employers requirements, Materials Specification
c. Geotechnical Report, Material and Workmanship Specifications for Earthworks.
d. Master Plan. Contractor shall provide the following:
1. Specific code and standards to be used for this for the above
e. Approved with Comments (AWC) construction drawings. mentioned works.
f. Approved ITP for excavation works. 2. Where are supposed to be survey and geotechnical report
which are part of the due diligence of the contractor?
g. SSEM HSE plan and Job Safety Analysis. 3.Contractor to provide the copy of the approval of all mentioned
documents that is already been approved.
h. SSEM excavation works procedure and OHSA standards. 4. Contractor shall provide reference number of the SSEM HSE
i. Approved Quality Control & Quality Assurance. plan aubmitted or approved.
5. Contractor shall provide copy of all the drawings submiital with
ENGINEER approval and comments.
4.0 PERMITS AND LICENCES "ALL" work related shall be 6. Contractor shall provide copy of submitted ITP and its
approval.
define and identified by the 7. Contractor shall provide the copy of the mentioned "Master
a. Work Permit contractor. Then it shall be Plan"
b. Excavation Permit submitted and secure an All the above comments shall be provided by the contractor with
the copy of the approval before it can be used as a reference
c. Entrance Permit approval from the Authority and standard documents.
Having the Jurisdiction prior
d. Barricade Permit
to any work implementation
e. Equipment Permit on-site.
5.0 EQUIPMENT
The contractor (SSEM) will provide the following equipment in the implementation of Shoring
activities alongside excavation works.
Type of Equipment Units (No.)
Excavator 1
Crow Bars 6
Steel mallet, 2 kg. 2
Carpenter’s Basic Tools 1 lot
Personal Protective Equipment (PPE) should be provided in order to perform all works in
accordance with the safety procedures and taking into consideration the importance of proper
preventive measures to ensure safety in the performance of work.
Type of Equipment
Safety Helmet
Safety Boots
Safety Glasses
Safety Masks
Coveralls
High Visibility Vests
Hand Gloves
The workforce including foremen and technicians are all with sufficient qualification and
experience. Equipment operators possesses applicable party certificates wherever
applicable/relevant.
Sub-contractor will be employed if there is need to catch up shortfalls or to accelerate progress.
List of subcontractor manpower will be made available once there company is
prequalified/accepted by the Engineer.
Any person required to undertake work associated with shoring works is accountable for:
Complying with the requirements of risk assessment management plan, any permits for work
Using personal protective equipment and safety equipment provided
Assisting in assessing risk
Attending training when required.
Only undertaking tasks they are competent to undertake (or are in training to Page 4 of 23
undertake with appropriate supervision)
Following reasonable instructions related to work associated with shoring
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3
CONTRACTOR (SSEM)
Construction Manager
Site Engineer
Safety Engineer
Equipment Operators
Carpenters
Laborers
First Aiders
The Construction Manager must mobilized the required materials, equipment and manpower
to do the job as required, and will monitor the activities. He must take note existing shortfall
and problems and discuss the same with the Project Manager. Corrective solutions must be
identified and applied to compensate for the shortfalls.
change to "shall"
8.2 QA/QC Engineer
The QA/QC Engineer will be responsible for the quality aspects of the works. He will assure
that the QA and QC plan will be implemented. The required SIR, WIR shall be submitted to
The Engineer. All required procedure in shoring works shall be followed to have a safe
working condition and quality requirements attained. He will proactively coordinate with the
site engineer and issue appropriate internal SOR when he see that performance of works
deviate from the approved.
Contractor shall include in the QA/QC Engineer scope " That workmanship shall not compromise the health and safety of the worker."
The Site Engineer will be in charge for the supervision and implementation of all activities as
required in the specifications and drawing, especially in giving orders to Site foremen. Site
engineer is also in charge for the preparation and filing of reports.
Contractor shall include to the Site Engineer responsibility the submission and secure the approval of all site work related permits. Prior to the
implementation of works on-site.
8.4 Site Foreman
change to "shall"
The Site Foreman will be in charge for the supervision and implementation of various steps in
shoring works, as instructed by the Site engineer. The Site Foreman shall also keep record of
all work schedules, work production and daily safety issues.
Page 5 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3
Conduct the safety induction course to all personnel involved in the work.
Monitor and supervise the risk assessment.
Ensure that necessary Permit to Work is available.
Ensure that the project’s method statement and risk assessment are understood and
understood, complied and applied in the worksite.
Ensure that all workers are provided with sufficient information regarding workplace
hazards and planned control measures.
The Professional Engineer will be in charge for the design in compliance with project
specification and standards.
The engineer may designate an experienced person on the worksite to conduct a regular
inspection.
The designated person should adhere his comments (if any) to the contractor for
immediate rectification prior for final inspection. The engineer then issues an inspection
report and certification.
9.1.3 For trench excavation which needs shoring, install shoring at side of once initial
excavation starts.
Page 6 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3
9.1.3.2 Once the desired depth is attained stabilize the side slope to provide
collapse.
9.1.4 For open excavation, fix the shoring if required once the desired depth is reached.
9.1.5 Proceed with construction when the side slope has been stabilized or if needed
install the shoring.
9.1.6 After completion of work, slowly remove the shoring and proceed with backfilling
work.
9.2 The hazards posed to workers working in excavation pit and trenches are potentially fatal.
Excavation failures can, however, be largely avoided by installing an adequately designed
support system. No worker should be permitted to work in an unsupported trench if the
existing soil structure is loose. Other precautions include the avoidance of external load from
construction vehicles and excavated spoil being stockpiled too close to the trench.
9.3 The use of adequate shoring, benching and side sloping is essential to control the risk of a
collapse or failure of open excavation. Construction of shoring system should consider the
following:
9.4 Shoring of trench excavation should be constructed and implemented strictly in accordance
with the design and contract specifications.
9.4.1 In ground composed of moderately firm to firm soil, vertical trench sides may stand
unsupported for a considerable period of time, and hence installing of shoring may
be disregarded. However, moderate side slope must be provided to make the
excavation wall stable.
Page 7 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3
9.4.2 When the ground condition is poor and has little or no “free-standing” time,
shoring/trench wall support should be installed in such a way that the trench wall
will not collapse.
9.4.3 After excavation works has been completed, proceed with next activities while
checking the integrity of shoring from time to time.
9.4.4 Where existing services crossing a trench or excavation line are encountered, timber
board support should be provided the services to prevent possible collapse or
damage.
9.4.5 After the works are completed, the support system will be extracted / dismantled in
the reverse order of its installation. Persons performing the work in the excavation
will not work outside the protection of the ground support system
During the process of shoring and excavation works, the necessary welfare facilities shall be
provided at the project site. The workers shall be provided with safe drinking water, toilets, place to
eat their food and place to store their clothes.
Tower lights will be used during night time works and is essential for the safety of workers, the
equipment and the proper execution of work. Barriers around excavation area shall be installed.
All work related training and safety induction for this specific work shall be identified and define in this document by the contractor.
10.1 Issues
The HSE Engineer has the responsibility for providing help advice to the supervisor who is
responsible for the work safety.
No one shall enter an excavation unless it has been inspected and considered a safe
place to work in by immediate supervisor.
Ensure that there is safe access to and from all excavation.
Beware of slipping when using ladders in wet conditions.
All employees must wear the appropriate personnel protective equipment.
No person is allowed under loads handled by power shovels/excavators. Banks men must
be assigned to monitor the activities.
Prior to start shoring/excavation, it must be determined whether underground utilities i.e.,
electric, telephone, sewer lines, etc. will be encountered.
Proper slopes to be provided at sides of excavation.
Provide protective barriers, shield systems complying with applicable standards.
Support of shoring must be periodically checked to assure integrity of the system.
Emergency and rescue procedures or strategy
incident or accidents related to shoring works.
monitoring and evaluation frequency of inspections
Risk Assessment Page 8 of 23
Risk control
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3
Page 9 of 23
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
CONSTRUCTION OF LOAD CENTER -3
Page 10 of 23
CONSTRUCTION OF LOAD CENTER 3 (LC-3) AT KING KHALED INTERNATIONAL AIRPORT (KKIA)
INSPECTION TEST PLAN FOR CIVIL WORKS
CONTRACTOR: SAUDI SERVICES ELECTRO MECHANICAL WORKS. CO. (SSEM) (Close Joint Stock Company) ITP Ref. No.: ISSUANCE: 01
CONTRACT NO.: R-15-085-BF-0 Sec No.: REVISION: 00
TITLE: CIVIL WORKS Sec Title.: Date: October 2015
Method of
Activity Inspection / Test Requirements Reference Documentation Demonstrated Evidence
Activity Description Verification
No. Report/Checklist
Test or Inspection Performed Stage / Frequency Test Required Code/Spec/Etc. Acceptance Criteria SSEM AECOM
2.0 EXCAVATION AND BACKFILLING
2.1 EXCAVATION
Prior to Proceed for
2.1.1 Availability of permit Verification of Permit SSEM CHECK Tender Requirements Valid Permit H R Checklist Form IC-C-002
Excavation
Check Approved Survey Data Prior to Proceed for Approved Construction
2.1.2 Location and Layout of area to be excavated SSEM CHECK Technical Specification H W Checklist Form IC-C-002
Layout Excavation Drawings
Checking and grading and elevation for Prior to Proceed for Technical Specification Approved Construction
2.1.3 Visual Inspection/Survey SSEM CHECK H W Checklist Form IC-C-002
conformity to drawing Excavation Civil Works Drawings
Check the excavated area for freedom from Prior to Proceed for Technical Specification
2.1.4 Visual Inspection SSEM CHECK Project Specification W S Checklist Form IC-C-002
extraneous materials and water Excavation Civil Works
Technical Specification Approved Designated
2.1.5 Disposal of excavated materials Visual Inspection During Excavation SSEM CHECK W S Checklist Form IC-C-002
Civil Works Disposal Area
2.2 BACKFILLING
Check fill materials for conformity to Technical Specification Test Result Compliance w/
2.2.1 Soil Classification Approved Stock File Third Party Test H R Checklist Form IC-C-002
specifications Civil Works A9010 Part I Sec.2.1 the Project Specification
Check foundation for Bitumen coating for Technical Specification
2.2.2 Visual Inspection Before Backfilling SSEM CHECK Project Specification H W Checklist Form IC-C-002
polyethylene covering Civil Works
Field Density Test (ASTM
Check thickness of Backfill layer and 4 Random FDT at least Technical Specification
2.2.3 D1556) Nuclear Density Test Third Party Test Project Specification S/H W Checklist Form IC-C-002
Compaction per lot of 2,500 sq.m. Civil Works A9010 Part I Sec.2.1
(ASTM D2922)
TRENCHING AND BACKFILLING OF
3.0
PIPELINES
3.1 TRENCHING
Prior to Proceed for
3.1.1 Availability of permit Verification of Permit SSEM CHECK Tender Requirements Valid Permit H R Checklist Form IC-C-003
Trenching
Approved Construction
Location and Layout of area to be trenched and Prior to Proceed for Technical Specification
3.1.2 Visual Inspection/Survey SSEM CHECK Drawings/Client As-Built H W Checklist Form IC-C-003
mark the routing of existing underground utilities Trenching Civil Works
Drawings
Checking grading and elevation for conformity to Prior to Proceed for Technical Specification Approved Construction
3.1.3 Visual Inspection/Survey SSEM CHECK H W Checklist Form IC-C-003
drawing Trenching Civil Works Drawings
Ensure proper care to avoid damages to existing Technical Specification Client Engineering
3.1.4 Visual Inspection During Trenching SSEM CHECK S W Checklist Form IC-C-003
utilities Civil Works Standard
Check the excavated area for freedom from Technical Specification
3.1.5 Visual Inspection During Trenching SSEM CHECK Project Specification H W Checklist Form IC-C-003
extraneous materials and water Civil Works
Technical Specification Approved Designated
3.1.6 Disposal of excavated materials Visual Inspection After Excavation SSEM CHECK S/H S Checklist Form IC-C-003
Civil Works Disposal Area
N/A – NOT
ABBREVIATIONS: W- WITNESS PONT S– SURVEILLANCE AECOM- Consultant
APPLICABLE
SSEM-
Note: H– HOLD POINT RR – REVIEW OF REPORT Page 11
Contractor of 23
Page 1 of 1
Page 12 of 23
Page 13 of 23
Page 14 of 23
Page 15 of 23
Page 16 of 23
Page 17 of 23
Page 18 of 23
Page 19 of 23
Page 20 of 23
Page 21 of 23
Page 22 of 23
SSEM-HSE/PERMIT/002/M07-11, Rev0.1, July2011
DESCRIPTION OF WORK:_________________________________________________________________________________