Addendum No. 04
Country: INDIA
Name of Work: Design and Construction of Civil and Building Works including Testing and Commissioning on Design Build Lump Sum Price Basis for
Double Line High Speed Railway involving Viaduct & Bridges, Crossing Bridges, Maintenance Depot and Station (Anand/Nadiad), between Vadodara
(MAHSR Km. 401.898) and Ahmedabad (MAHSR Km. 489.467), excluding Works for 01 No. PSC Bridge and 04 No. Steel Truss Bridges, in the State of
Gujarat for the Project for Construction of Mumbai-Ahmedabad High Speed Rail
Date: 27.12.2019
Loan Agreement No.: ID-P277 & ID-P279
IFB Number: Package No. MAHSR-C-6
Following are to be considered:
Item
Refer Para No. Original/As Existing Revised
No.
1. Bidding Documents, Design and Construction of Civil and Building Works including Design and Construction of Civil and Building Works including
Name of the Works Testing and Commissioning on Design Build Lump Sum Price Testing and Commissioning on Design Build Lump Sum Price
Basis for Double Line High Speed Railway involving Viaduct Basis for Double Line High Speed Railway involving Viaduct
& Bridges, Crossing Bridges, Maintenance Depot and Station & Bridges, Crossing Bridges, Maintenance Depot and Station
(Anand/Nadiad), between Vadodara (MAHSR Km. 401.898) (Anand/Nadiad), between Vadodara and Ahmedabad from
and Ahmedabad (MAHSR Km. 489.467), excluding Works for MAHSR Km. 401.898 to MAHSR Km. 489.467, excluding
01 No. PSC Bridge and 04 No. Steel Truss Bridges, in the State Works for 01 No. PSC Bridge and 04 No. Steel Truss Bridges,
Employer shall provide eight (8) user license(s) from its system
to the Contractor for communication and for storing the
documents. Employer may consider Contractor’s request for
additional license(s) on case by case basis and Contractor shall
bear the cost of additional license(s). All the licenses provided
to the Contractor shall be continued up to the Completion of the
Contract. The Contractor shall be responsible to maintain
periodical backup of data/documents for his record.
5. Part 2, Section VI-1, Division
8 Installation of C-6 T-3 T-3 T-3 T-3 shall 8 Installation of C-6 T-3 T-3 T-3 T-3 shall
04000, Appendix 04000-1,
rail for gantry design, rail for gantry design,
Chapter III, 4. C-6 and T-3, C-6 C-6 C-6
crane in procure crane in procure
Page 10 of 19
maintenance materials and maintenance materials and
depot install rail for depot install rail for
gantry crane gantry crane
6. Part 2, Section VI-1, <Item No. 6 has been modified in the Interface table between
Division 04000, Appendix C-6 and E-1.
04000-1, Chapter III, C-6 Three new items 30, 31 and 32 have been added in the Interface
and E-1, Page 12 of 19 table between C-6 and E-1>
Refer Attachment No. 10 of this Addendum.
7. Part 2, Section VI-1, Division <Add the following item after item 7 in Sub-Clause 1.6>
05000, Sub-Division 05020,
“8) The Contractor shall be responsible for strictly abiding by
Sub-Clause 1.6, Page 9 of 43
the criteria and method specified in the Employer’s
Requirements for verification of running safety of Bridges and
Viaduct of mainline (other than span arrangement which have
been fixed in the DRC in the Employer’s Requirements).”
Cable layout for PSC I girder of Cable layout for PSC I girder of Cable layout for PSC I girder of Cable layout for PSC I girder of
Bridge Length 25m and 30m Bridge Length 35m Bridge Length 25m Bridge Length 30m and 35m
Figure 1.1.4: PC cable layout given in Standard Design Figure 1.1.4: PC cable layout given in Standard Design
Table 1.1.7: Modification for PC cable Table 1.1.7: Modification for PC cable
Nos. of PC Nos. of PC
Target Bridge Cable to be Initial Tensile Stress Target Bridge Cable to be Initial Tensile Stress
cables to be cables to be
Length (m) omitted (N/mm2) for all cables Length (m) omitted (N/mm2) for all cables
omitted omitted
21 1 C1 1200 21 1 C1 1200
22 1 C1 No change 22 1 C1 No change
23 1 C1 No change 23 1 C1 No change
27 1 C1 No change 27 1 C1 1100
28 1 C1 No change 28 1 C1 1200
31 1 C1 No change 31 1 C1 No change
32 1 C1 No change 32 1 C1 No change
33 1 C1 No change 33 1 C1 No change
34 1 C1 No change 34 1 C1 No change
32. Part 2, Section VI-2, b. The Ultimate Bearing Capacity of bearing stratum shall be b. The Unconfined Compressive Strength (UCS) of bearing
Division 02000, Attachment 6000 kN/m2 or greater. stratum shall be 20 MPa or greater; and Nj (Empirical
5, Sub-Division 02020, Sub- coefficient depending on the spacing of discontinuities, refer to
IS12070 Clause 6.2) shall be greater than or equal to 0.1.
Clause 2.2.1.2,
1. Item b),
2. Figure 2.2.1
Page 93 of 165
36. Part 2, Section VI-2, Division 3) Duct arrangement at OHE mast foundation 3) Duct arrangement
02000, Attachment 5, Sub- The angle of LCX duct diverting around OHE mast foundation
The diverting angle of ducts for power supply; signal and
Division 02010, Sub-Clause shall be set less than or equal to 4.0º degree for both
telecommunication cables shall not be greater than 30º.
1.3.3.1, Item 3) Page 14 of horizontal and vertical direction.
<This change shall be applicable for all the Standard Design
165
drawings showing the duct arrangements.>
58. Part 2, Section VI-2, <Sub-Clause 3.3.2.1 is modified. Refer Attachment No. 06 of
Division 02000, Attachment this Addendum.>
5, Sub-Division 02050, Sub-
Clause 3.3.2.1, Page 151 of
165
59. Addendum No. 3, Item No. <Sub-Clause 4.3.1.2 and 4.3.1.3 are modified. Refer
78, Part 2, Section VI-2, Attachment No. 07 of this Addendum.>
Division 02000, Attachment
5, Sub-Division 02050, Sub-
Clause 4.3.1.2 and 4.3.1.3
73. Part 2, Section VI-2, Division <Add the following Item i) after existing Item h)>
05000,
Sub-Division 05040, Sub- i) Essential power load for Platform Screen Doors (to be
Clause 6.10.2, Page 12 of 73 provided in future) shall be included in the design @
48kVA/Track side with PSD as below:
Indicative PSD
S. Stations No. of Track
Elect Load @
No. Name sides with PSD
48kVA/Track
Anand/N 02 96 kVA
1
adiad
74. Part 2, Section VI-2, Division
07000, Sub-Division 07010, Table 3: Design parameters for air-conditioned spaces Table 3: Design parameters for air-conditioned spaces
Sub-Clause 2.2.5, Page 07 of
39 Items Specification/ Applicable Standard Items Specification/ Applicable Standard
Range Range
Noise 35-40 dB(A) NBC 2016, Vol-2, Part-8, Noise 45-50 dB(A) NBC 2016, Vol-2, Part-8,
Level Section-4, Table-4 Level Section-4, Table-4
75. Part 2, Section VI-2, Division The structure shall be designed for service life as stipulated The structure shall be designed for service life as
07000, Sub-Division 07010, below: stipulated below:
Sub-Clause 3.1 d), Page 10 of
39 i) Concrete Structure – 100 years i) Concrete Structure – 60 years
ii) Structural steel Structure / Shed – 60 years ii) Structural steel Structure / Shed – 60 years
4.1.4 For the design parameters for the non air-conditioned 4.1.4 For the design parameters for the non air-conditioned
spaces, the Contractor shall refer to Clause 2.2.3, Tables spaces, the Contractor shall refer to Clause 2.2.5, Tables
4 and item c), in this Sub-Division. Roof extractor units 4 and item c), in this Sub-Division. Roof extractor units
and exhaust fans shall be provided in the Maintenance and exhaust fans shall be provided in the Maintenance
Depots and Safety Confirmation Car Shed. Refer Basic Depots and Safety Confirmation Car Shed. Refer Basic
Design drawings. Design drawings.
77. Part 2, Section VI-2, Division 4.2.1 VAC system shall be designed by the Contractor 4.2.1 VAC system shall be designed by the Contractor
07000, Sub-Division 07010, considering the following: considering the following:
Sub-Clause 4.2.1, Page 21 of
39 e) The Contractor shall refer to Room Data Sheet, e) The Contractor shall refer to Room Data Sheet,
in Clause 2.2.3 in Table3, Table 4 and Clause in Clause 2.2.5 in Table3, Table 4 and Clause
c) of this Division. c) of this Division.
f) The Contractor shall design the VAC system f) The Contractor shall design the VAC system
for the Sheds, rooms and spaces of for the Sheds, rooms and spaces of
Maintenance Depot as per Clause 2.2.3 and Maintenance Depot as per Clause 2.2.5 and
submit the same to the Engineer for obtaining submit the same to the Engineer for obtaining
approval. The Contractor shall submit his approval. The Contractor shall submit his
VAC design as the output obtained from VAC design as the output obtained from
commercially available/proven VAC software. commercially available/proven VAC software.
Figure 12 On-site Road (Case of width=10m) Figure 12 On-site Road (Case of width=10m)
Figure 13 <Deleted>
8.4.3.2. Control of Position and Alignment 8.4.3.2. Control of Position and Alignment
The permissible tolerances with respect to position and The permissible tolerances with respect to position and
inclination, alignment shall conform to Sub-Clause 8.1.4.2, inclination, alignment shall conform to Sub-Clause 8.1.4.2,
except “Cut-off-Level” which shall be read as “top level” and except “Cut-off-Level” which shall be read as “top level” and
7) The colouring pigment shall be Bayerfox Germany or 7) The colouring pigment shall be in compliance with DIN 53
equivalent. 237.
100. Part 2, Section VI-3. Sub- 5) Fixing: Sheets shall be fixed to roof purlins and side runners 5) Fixing: Sheets shall be fixed to roof purlins and side runners
Division 05010 Sub- at crest as per manufacturer´s recommendation and water at crest as per manufacturer´s recommendation and water
Clause 10.1.2, Item 5) tightness provisions using polymer coated galvanized hexa tightness provisions using polymer coated galvanized hexa
Bullet points, Page 41 of 75 head self-drilling self-tapping (SDST) screws with sealing head self-drilling self-tapping (SDST) screws with sealing
tapes and screw fasteners with the following properties: tapes and screw fasteners with the following properties:
Case Hardener Carbon steel AISI11018/10B21 Case Hardener Carbon steel AISI11018/10B21
Screw diameter 5.5 mm (In case of Stitching 4.8 mm) Screw diameter 5.5 mm (In case of Stitching 4.8 mm)
Metal Bonded EPDM Washer 2-3 mm width 16MM Metal Bonded EPDM Washer 2-3 mm width 16mm
Diameter (In case of stitching 14mm diameter) Diameter (In case of stitching 14mm diameter)
Organic/Geomet/Dorken/Xylin coating insuring 1000- Organic coating ensuring 1000-hour salt spray life
hour salt spry life EOTA approved.
EOTA approved. The sheets shall be bent to required curved profile and fixed
The sheets shall be bent to required curved profile and fixed with rib & flute.
with Trimdek or equivalent rib & flute.
109. Part 2,
<The following notes shall be read in conjunction with all the
Section VI-4,
Maintenance Depot drawings>
Drawings,
Division 12000 Note: Provision for the Crushed Stone Pavement of thickness
100mm shall stand deleted in the drawings of Maintenace
Depot. Instead of Crushed Stone Pavement of 100mm
thickness, the finished ground level shall be achieved with
backfill duly compacted (refer TS 03000).
110. Part-2, Section VI-4, <The following notes shall be read in conjunction with all the
Drawings drawings>