Professional Documents
Culture Documents
ABSTRACT : This paper summarizes recent developments in the design and built Al
Bustan Bridge and Highway Project as part of the Qatar Expresway Programme and the
lessons learned from it.
The Al Bustan South Project comprises design and construction of an expressway to the
north of Doha with grade separated junctions, four- lanes dual deck to form a 1,946 meter
long bridge structure, including 863 of on/off ramp bridges. The project include drainage
system, extra highvoltage-highvoltage cables, street lighting, substations, irrigation
tranmission pipelines, water pipelines, foul sewer, landscape, intellegient transportation,
artscaping design and construction.
The Qatar Expressway Programme is a very large road infrastructure projects that connects
Doha with other cities through a set of advanced highways, roads, and flyovers. The scope is
expected to deliver about 800 km of safe and efficient roads. The programme also includes
the construction and development of an integrated infrastructure network equipped with state-
of-the-art, reliable underground utilities, including storm water networks, electrical services,
and intelligent transport systems. Al Bustan Corridor, Orbital Highway, North Road, Al
Rayyan Road and Lusail Expressway part of this programme.
Design and building of highways and bridges in urban areas with very tight schedules are
always big challenges to contractors as well as to the employers. The contractor must
manage the busy existing traffic to provide work zones to the bridge construction works. The
existing utilities and relocation of them have been major issues in the structural design to
accomodate the foundations.
Consideration of utility relocations and traffic diversion management may change the entire
concept of bridge‘s design and construction.To improve life around the city and have
aesthetic harmony in these structures, the employer had to make important provisions.
1 INTRODUCTION
Public Works Authority, Qatar Expressway Programme is the World‘s largest road and
infrastructure Programme brings together around 60 road projects, 800 km of safe efficient
roads, and 240 major interchanges.
Al Bustan Corridor is very important alternative to existing expressway named 22nd February
corridor in national expressway which crosses free flow traffic length 14 km from North of
Central Doha to South consists of 4 Contracts. Moreover, Al Bustan South project is one of
the contracts which was previously only a built scheme with a (-1) level underpass structure
on mainline section. During the tender stage of the built only scheme, Public Works Authority
issued an addendum to the Tenderers to propose an alternative design-built for mainline
1
alignment in order to reduce the construction cost and to have sustainable structure design.
The project was then awarded on this basis as design-built with the detailed design to be
resubmitted on the basis of the (+1) bridge structure. Project location is shown in Figure 1 and
Figure 2.
2 OVERVIEW OF SCOPE
Al Bustan project upgraded to a dual carriageway with minimum of 4 lanes in each direction
from South of Rayyan Road Junction R6 to South of Al Waab Street ( Figure 3). Within the
project limit the mainline Al Bustan Street at Junction B1, where Al Waab Street intersects
with Al Bustan Street: a three level interchange shall be constructed with a signalized at-grade
junction. At Junction B2 where Al Khufoos Street (Al Rasheeda) intersects with Al Bustan
Street : a two level interchange shall be constructed with a signalized at grade.
N
2
Furthermore to maintain East-West local accessibility, a mid block crossing underpass shall
be constructed between junction R6 and Junction B2 ( Figure 3 and 4 ). The total length of
the improvement scheme is approximately 5 km with associated service roads, minor
junctions and structures . Project Estimated cost 1.58 bn Qatar Riyal ( $434 Million ) and
Construction duration from October 2017 to January 2020.
3 DESIGN CONSIDERATIONS
3.1 Highway Details
Al Bustan Street is classified as an Urban Expressway. It is out of the Classified High Load
Route of Qatar. Permitted Traffic Speed as following;
The highway cross section on the Al Bustan street bridges comprises four lanes of traffic in
each direction. A typical highway cross section is shown in Figure 5 and dimensions given in
Table 1.
3
Figure 5. Al Bustan South Corridor Highway Cross Section
4
The abutments for both main and ramp bridges are wall-type abutments retaining the backfill
behind the wall. The Piers for both main and ramp bridges are single tapered reinforced
concrete piers with mechanical bearings.
All structures of main bridges and ramps are designed in accordance with the ‗Design Criteria
for Highway Structures Interim Advice Note 009 (IAN009), Revision A2‘ and the
requirements for bearing and expansion joints IAN 006 and IAN 031 respectively produced
by Public Works Authority. As per the criteria, design carried out using relevant British
Standards, Design Manual for Roads and Bridges and UK‘s Highway Agency Technical
Memoranda. Seismic loading designed in accordance with AASHTO LRFD 2014 with a peak
ground acceleration of 0.15g.
5
Typical bearings articulation plan is shown below;
Ramp bridges follow a similar approach and supported on two mechanical bearings at each
column location and at abutments. The longitudinal fixation of the deck located at one internal
pier (central or near central) of each ramp bridge. The longitudinal fixation made through a
monolithic connection. The fixed pier designed for all longitudinal traffic loads and horizontal
seismic loads. One multi-directional bearing and one guided bearing – restraining the deck
transversally - located at all other columns and abutments.
Design lives are design service life (years) for mechanically Stabilized Earth Walls 120 years,
Non-replaceable expansion joint components 50 years, bearing devices 50 years, Asphalt
wearing course 20 years.
3.8 Materials
3.8.1 Structural Concrete Classes
The classes of concrete are based on 28-day minimum compressive cube strength, which is
estimated to be 1.25 times the cylinder strength. The classes of concrete is denoted as cube
strength/maximum aggregate size (MPa/mm) and specified for use as follow:
6
3.8.2 Reinforcement
All reinforcement are deformed round steel bars Grade B500B or B500C conforming to BS
EN 10080 and BS4449: 2005 and cut and bent in accordance with BS 8666: 2005. The
characteristic strength of reinforcement is 500 N/mm2 with a minimum modulus of elasticity
of 190 kN/mm2. Due to the significant inertia forces, a ductile design for built in piers has
been adopted with a maximum value of 2 for the response modification factor. AASHTO
detailing rules followed including the provision of closed stirrups and splicing of vertical
rebars outside plastic hinge zone.
Structures with external and unbonded prestressing comply with the requirements of BD58
and the guidance in BA58. Structures with external and unbonded prestressing designed with
provision for the replacement and re-stressing of tendons. The structure capable of
accommodating a range of prestressing force resulting from future tendon replacement, and
galleries are incorporated at abutments and intermediate piers expansion joints with sufficient
room to manoeuvre prestressing jacks. Concrete boxes housing external tendons have
adequate working space and means of access to facilitate replacement and restressing of
tendons. The proposed stressing arrangement for external tendons has been done considering
the above provision and all live end stressing has been proposed from inside the box
superstructure. Anchorage end at expansion joints will act as dead end anchorage; sufficient
space has been provided at abutment and intermediate pier expansion joint locations for
installation, inspection and maintenance of these dead end anchorages.
Structures with external and unbonded prestressing designed to permit future dead load or
deflection adjustment as outlined in Clause 5.14.2.3.8.c of AASHTO LRFD 2014. This
consist of provision for the future addition of external post tensioning located inside the box
structure and symmetrical about the structure center line. Anchorages and deviators provided
in addition to all necessary openings through concrete elements. These have the capacity to
allow an additional prestressing force to be introduced in the future of not less than 10% of
the positive moment and negative moment prestressing force provided at the time of
construction.
Ducts for unbonded tendons within the concrete section are made from High Density
Polyethylene (HDPE) with a minimum wall thickness of 2mm. Ducts waterproofed with
drainage holes at low points along their profile to release any water that may be trapped and to
facilitate inspection by means of an endoscope.
Unbonded tendons within ducts are corrosion protected with galvanising, painted in a light
colour to aid inspection which allows for tendon replacement and restressing.
7
3.8.4 Prestressing Ducts
Prestressing ducts consist of an electrically non-conductive and corrosion resistant durable
material such as high density polyethylene or polypropylene forming a double corrosion
protection system in combination with the grout. Ducts supported at a maximum spacing of
1000 mm.
4 GEOTECHNICAL SUMMARY
The ground materials and material properties encountered during the Al Bustan Street South
site investigations are typical of the Doha geology and no onerous or high risk geotechnical
materials have been encountered. In addition, detailed design Geophysical investigations
indicate that there is a low risk of subsurface cavities and voids at the Al Bustan Street South
site. A generalized ground profile encountered along the project site is included in below.
8
5 METHODS OF ANALYSIS PROPOSED FOR SUPERSTRUCTURE,
SUBSTRUCTURE AND FOUNDATIONS
Global Analysis
The bridges analyzed using independent models for superstructure and substructure:
5.1 Superstructure
Pre-cast segmental deck modeled using commercial software MIDAS Civil, a 3-dimensional
finite element ( FE ) software that models accurately also effects of prestressing, creep,
shrinkage and temperature. Two different models used for the analysis of the deck:
1. Longitudinal model: The model reflect the articulation of the bridge and will take into
consideration the erection methodology and the precast segmental construction history. The
deck units modelled using beam elements. Long term effects of the concrete are taken into
account considering the estimated casting and erection date of each individual segment.
Longitudinal models for the ramps and longitudinal models for the main bridges built to
calculate the longitudinal stresses. The columns modeled using linear elements restrained at
foundation level.
2. Transverse model. The model a 3D FE model using shell elements and limited to one span
from column to column including end diaphragms.
A 3D FE shell model built for single box bridges. The effects of the transverse model
combined to the effects of the longitudinal models for compatible load combinations.
5.2 Substructure
A different calculation model from the one used for the Superstructure, considering the effects
of the seismic load defined in following paragraphs in this paper,
Vehicular live load surcharge considered in the design in accordance with Clause 5.8.2 of BD
37/01 as HA Loading: 10kN/m2, HB 30 units: 12kN/m2, HB 45 units: 20kN/m2.
Live loads considered in accordance with section 6.3 of IAN009 and BD 37/01, BD 24/92.
The wind speeds are appropriate to a height above ground level of 10 meters in open level
country with an annual probability of being exceeded of 0.02 (50-yr return period).
9
Utilities: 2 kN/m (No major utilities are proposed on the structure, however a provisional load
of 2 kN/m is considered to cover lighting arrangements) ,
Bridge Barrier (1.5m high F shape): 17.0 kN/m, 0.5 kN/m allowance has been made for
Aluminium cladding.
Global analysis of the structure performed using MIDAS Civil finite element analysis
software. The superstructure idealized as spine beam and the piers/abutments connected to it
by means of joints.
The Pier columns modeled as frame elements and connected to the superstructure with the
joint conditions that reflect the articulation of the bridge bearings. Columns modeled up to the
top of the foundation, connected to raft foundation as plate element with springs considering
soil subgrade modulus.
For pile foundations, the ground condition/soil parameters introduced into the software by
means of horizontal Winkler spring modulus as stated in the geotechnical interpretative
report.
For Piers, foundations, and connections, design forces obtained from the analysis (RSA)
modified using response modification factor R corresponding to bridge operational category
―Essential‖. For single piers (wall type), response modification factor of 2 in weak direction
(longitudinal) and 1.5 in strong direction (transverse) is adopted. For portal piers, response
modification factor of 2 is adopted in weak direction (i.e. transverse seismic), whereas for
strong direction response modification factor is not applicable as the bearings are free in this
direction (longitudinal).
The elastic seismic forces thus obtained from analysis (RSA) in the two perpendicular
directions combined to form two load cases as follows:
10
Design forces for each structural component obtained by modifying the elastic forces
calculated from the above two load cases using the appropriate response modification factors
R as given above. Reinforcement detailing of substructure as per the seismic design
provisions given in clause 5.10.11 of AASHTO LRFD 2014.
Stability of foundations under seismic loading checked in accordance with AASHTO LRFD
2014.
6 CONCLUSIONS
Al Bustan South Project procurement stage opened to the Tenderers as to be only construction
project with complete and approved design as (-1) level underpasses. However, during the
Tender stage the Public Works Authority requested an alternative cost reduced design
proposal from the Tenderers providing the same mobility, accessebility and functional design
as to be Design-Built contract. A Contractor proposed an alternative design-built as to be (+1)
bridge instead of (-1) underpass design and the Procurement stage was ended with succes to
award the project as Design-Built with significant cost saving to the Public Works Authority.
The above information is given to demostrate the bridge design criteria along with methods of
analysis and appropriate design approach for sustainable bridge construction. Considering
state of art expansion joints and bearings standing extreme weather conditions, additional
post tensioing ducts for future use, special care for inspection to expansion joints, bearings
and post tensioning, highest containment level F shape concrete parapet, designing the deck as
single cell precast segmental box girder for typical spans construction by Balanced Cantilever
Construction Method and for the varying width deck consists of two cell post-tensioned box
girder, with cast-in-situ construction successfully achieved.
7 ACKNOWLEDGEMENT
The Authors wish to express their gratitude to Dr. Eng. Saad bin Ahmad Al Muhannadi for
his invaluable support on the preparation of this article.
11