LTVR Calculations of the Existing 250KVA DTC

0.027 0.0041 0.0212 0.02655 0.00355 0.00113

35 40 38 32 30 30
10
(Note: All the load in HP)

Sl.no Load at Nodes Distance from load to load


1 30 0.00113 0.0339
2 60 0.00355 0.213
3 102 0.02655 2.7081
4 140 0.0212 2.968
5 180 0.0041 0.738
6 215 0.027 5.805
Total 12.466

12.466 x 42.305
LTVR =
1.5 x 100

527.3741
=
150

LTVR = 3.52 %
LTVR Calculations of the Existing 100KVA DTC

0.057 0.0231 0.02412 0.02265 0.04555 0.05313

18 20 15 10 15 18
5
(Note: All the load in HP)

Sl.no Load at Nodes Distance from load to load


1 18 0.05313 0.95634
2 33 0.04555 1.50315
3 48 0.02265 1.0872
4 63 0.02412 1.51956
5 83 0.0231 1.9173
6 101 0.057 5.757
Total 12.74055

12.74055 x 42.305
LTVR =
1.5 x 100

538.989
=
150

LTVR = 3.59 %
LTVR Calculations of the Existing 63KVA DTC

0.0657 0.0511 0.0212 0.03655 0.0455 0.0613

4 5 6 5 8 5
25
(Note: All the load in HP)

Sl.no Load at Nodes Distance from load to load


1 5 0.0613 0.3065
2 38 0.0455 1.729
3 43 0.03655 1.57165
4 49 0.0212 1.0388
5 54 0.0511 2.7594
6 58 0.0657 3.8106
Total 11.21595

11.21595 x 42.305
LTVR =
1.5 x 100

474.4908
=
150

LTVR = 3.16 %
LTVR Calculations of the Existing 25KVA DTC

0 0 0 0 0.4555 0.3313

0 0 0 0 5 15

(Note: All the load in HP)

Sl.no Load at Nodes Distance from load to load


1 15 0.3313 4.9695
2 20 0.4555 9.11
3 20 0 0
4 20 0 0
5 20 0 0
6 20 0 0
Total 14.0795

14.0795 x 42.305
LTVR =
1.5 x 100

595.6332
=
150

LTVR = 3.97 %