Professional Documents
Culture Documents
Number:
RISK ASSESSMENT & HOT WORK PERMIT
Specific Hot Work The hot work is to be solely undertaken by a contracted party OR BAC personnel Attach documentation &
and a detailed work method statement / risk assessment has been previously proceed to Section 2 on the
Issues: following page.
prepared, reviewed by BAC & is attached to this Form.
(tick appropriate)
The hot work is to be solely undertaken by BAC personnel as per the specific hot Complete the Risk
work issues detailed below. Assessment below.
The work area will require specific cleaning, purging, ventilating or pre-
work atmospheric monitoring (due to flammable/explosive vapours, dusts,
liquids or solid residues in the work area / location)
Version 1 – Page 2 of 3
HOT WORK WI ANG 58 P.T.W. Number:
RISK ASSESSMENT & HOT WORK PERMIT
Section 3 – Implementation
Hot Works Authorisation (Work Coordinator in Direct Control):
The procedures, control measures and precautions appropriate for the safe execution of hot work have been implemented and the persons required to
work have been advised of and understand the requirements of the Risk Assessment & Hot Work Permit.
Name: Signature: Date: Time:
Constraints: This Authorisation is valid until the following occurs, or the date and time shown:
Date: Time:
Version 1 – Page 3 of 3