CIVIL

MOBILE POWER PLANT & FIXED TYPE GAS


MECHANICAL
ENGINE POWER PLANT PACKAGE III (FIXED R
POWER PLANT) E ELECTRICAL
PLTMG BIAK 15 MW V I&C
CONTRACTOR DOCUMENT REVIEW I
E SUPPORT
DATE W
LOG
IN COMM. NO.

A □ APPROVED
B □ APPROVE AS NOTED CONTRACTOR
D RECORD
C □ NOT APPROVED
I
S WORKING
I □ INFORMATION
T DOCUMENT

APPROVAL DOES NOT RELIEVE R


CONTRACTOR FROM RESPONSIBILITY FOR I
ERRORS AND DEVIATIONS FROM B
CONTRACT REQUIREMENTS U
T
BY: DATE: I
O
LOG DATE:
N
OUT COMM. No. :
OWNER
PT. PERUSAHAAN LISTRIK NEGARA (PERSERO)
UNIT INDUK PEMBANGUNAN PAPUA

ENGINEER
PT. PLN ( PERSERO ) PUSAT ENJINEERING KETENAGALISTRIKAN

CONTRACT NO. :
PLN DOC. NO.
1 1 0 2 6 B 3 . 4 - - - - - -

TITTLE :
METHOD OF STATEMENT ACCES ROAD
PURPOSE :
ISSUED FOR APPROVAL
REV Description Prepared Checked Approved Date

ISSUED FOR
0 AW YG KD 20-January-22
APPROVAL
CONTRACTOR DOC. NO. :

CONSULTANT ENG-DED-BIK-CV-13-MTD-150
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 2 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

REVISION HISTORICAL SHEET

Rev No Date Description


0 20/1/2022 ISSUE FOR APPROVAL

INTERNAL
Rev No Date Description
0 20/1/2022 ISSUE FOR APPROVAL
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 3 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

TABLE OF CONTENTS

1. GENERAL 4

2. SCOPE OF WORK 4

3. CONSTRUCTION EQUIPMENT 4

4. MANPOWER PLAN 4

5. METHOD OF WORK 4
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 4 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

1. GENERAL
This method statement highlight the work sequence for access road so that target and planning can
be done properly and on time.

2. SCOPE OF WORK
Scope of work Implementation of access road concrete work with a width of 8 M

3. CONSTRUCTION EQUIPMENT
 Excavator + Breaker (1 Unit)
 Mixing Concrete Cap. 0,6m3 (2 Unit)
 Vibrator concrete (1 Unit)
4. MANPOWER PLAN
Direct manpower Plan :
 Operator (1)
 Surveyor (1)
 Workers (25)
5. METHOD OF WORK
 PREPARATION
The preparatory work carried out is by cleaning the work site area from grass and plants that
affect the work location.
Mobilization of heavy equipment to the site according to job requirements.
Making a work plan from the existing layout, so that it can be determined where the method of
implementing the work begins so that the mobilization of fuel cars that supply fuel to the power
plant can continue without being disturbed.
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 5 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

 EXCAVATION WORK
Excavation work is carried out using the breaker method which sees the soil condition at the
location of the access road as hard rock.
This excavation work is carried out at a level or rock position that is too high, until the level is
close to the level according to the actual site conditions in the field (FGL).

 LEVELLING WORK
Leveling work in this case is to do FGL leveling which will be adjusted to the actual site
elevation conditions, this process is done by leveling the former hard rock excavation by placing
it in a low elevation position then leveling it using an excavator in order to adjust to the actual
condition of the existing site elevation.
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 6 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

After the smoothing is done, data is collected or a survey is carried out for the FGL elevation
according to the actual site conditions and the coordinates of the road boundary to be worked on.

 FORMWORK
Formwork work can be carried out after the FGL work is completed by installing formwork
according to the planned size, namely 60Mx4M, where every 20M a separator will be installed as
a deletion of the road.
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 7 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

 INSTALLATION POLYTHELINE SHEET


Installation Polytheline sheet work can be carried out simultaneously with formwork installation
work, Polytheline sheet can be carried out according to the casting plan that was planned at the
beginning, which will start from the front of the Biak 1 PLTMG power plant fence and so on up
to the district road boundary.
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 8 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

 Wiremesh Installation
After the installation of the formwork and cast platik is complete, the iron is installed using
Wiremsh M6-150 in a position that is ready to be installed.

 POURING CONCRETE
After the installation of the wiremesh is complete, cleaning is carried out to prepare for pouring
concrete.
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 9 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

 JOINT INSPECTION
CONSORTIUM OF PT. WIJAYA KARYA &
PT. WIJAYA KARYA REKAYASA KONSTRUKSI
ENGINEERING DOCUMENT

PLTMG PACKAGE 3
Page 10 of 10
ENG-DED-BIK-CV- METHOD STATEMENT OF ACCES ROAD
13-MTD-150

Submit Request for Inspection Form for joint inspection and record joint measurement with
client / client’s representative. On completion of joint inspection, request client / client’s
representative to sign on the Request for Inspection Form and file as per Project Filing Index.