FY 2017 STATUS OF CONTRACTS - REPORT FOR STAKEHOLDER

REGULAR INFRA - Central Office-Implemented


As of 28 February 2022

REGION: CENTRAL OFFICE


IMPLEMENTING OFFICE: BRIDGES MANAGEMENT CLUSTER
%
CONTRACT CONTRACT EFFECTIVIT EXPIRY
CONTRACT DESCRIPTION CONTRACTOR ACCOMPLISHMEN
ID COST Y DATE DATE
T
17Z00007 BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) ALGON ENGINEERING 208,879,999.98 02/21/2018 04/10/2020 56.36
I, DESIGN AND BUILD BRIDGES FOR (REGION IV-A), CONSTRUCTION
CONTRACT PACKAGE 4 CORPORATION (16724) / M.E.
SICAT CONSTRUCTION, INC.
(FORMERLY M.E. SICAT
(16724) / ALGON
ENGINEERING
CONSTRUCTION
CORPORATION (00270) / M.E.
SICAT CONSTRUCTION, INC.
(FORMERLY M.E. SICAT
(00270)
17Z00026 BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP ALGON ENGINEERING 181,134,301.51 03/23/2018 01/13/2020 20.43
II), CONTRACT PACKAGE 12, KAY TIALO BRIDGE (BRGY. CONSTRUCTION
STO CRISTO, DEL MONTE NORZAGARAY ROAD, SAN JOSE CORPORATION (00270) / M.E.
DEL MONTE, BULACAN, REGION III SICAT CONSTRUCTION, INC.
(FORMERLY M.E. SICAT
(00270) / ALGON
ENGINEERING
CONSTRUCTION
CORPORATION (16724) / M.E.
SICAT CONSTRUCTION, INC.
(FORMERLY M.E. SICAT
(16724)
17Z00028 PROPOSED DESIGN AND BUILD FOR THE FREY-FIL CORPORATION 164,855,271.30 06/01/2018 08/24/2019 4.23
REHABILITATION/RETROFITTING OF THE QUIRINO BRIDGE (FORMERLY:FREYSSINET
IN COTABATO CITY, REGION XII FILIPINA (31521)

PCMA 2/28/2022 12:04:40 AM [The slippage indicated herein are not conclusive but subject to verification from the Implementing Office] Page 1 of 9
REGION: CENTRAL OFFICE
IMPLEMENTING OFFICE: BUREAU OF CONSTRUCTION
%
CONTRACT CONTRACT EFFECTIVIT EXPIRY
CONTRACT DESCRIPTION CONTRACTOR ACCOMPLISHMEN
ID COST Y DATE DATE
T
17Z00009 DESIGN AND BUILD SCHEME FOR THE COMPLETION OF NATIONSTAR 443,737,737.77 02/27/2018 12/10/2019 100.00
RETROFITTING/RESTORATION OF PRESIDENTIAL DEVELOPMENT
MANAGEMENT STAFF (PMS) BUILDING, PHASE II, ARLEGUI CORPORATION (FOR:
ST., SAN MIGUEL, MANILA CASMOR CONSTRUCTION
CORPORATION) (9608) / J.D.
LEGASPI CONSTRUCTION
(9608) / NATIONSTAR
DEVELOPMENT
CORPORATION (FOR:
CASMOR CONSTRUCTION
CORPORATION) (26876) / J.D.
LEGASPI CONSTRUCTION
(26876)
17Z00027 CONSTRUCTION OF THE SUPPLEMENTAL WORKS (E.G. HAIDEE CONSTRUCTION 15,139,609.71 10/02/2017 02/28/2018 100.00
CONSTRUCTION OF BRS LABORATORY BUILDING, CAR AND DEVELOPMENT CORP.
PORT, SITE DEVELOPMENT, VOICE AND DATA WORKS, (10365)
MERALCO POWER PERMANENT CONNECTION AND MANILA
WATER SUPPLY PERMANENT CONNECTION) FOR THE
THREE (3) STOREY BUREAU OF RES

PCMA 2/28/2022 12:04:40 AM [The slippage indicated herein are not conclusive but subject to verification from the Implementing Office] Page 2 of 9
REGION: CENTRAL OFFICE
IMPLEMENTING OFFICE: FLOOD CONTROL MANAGEMENT CLUSTER
%
CONTRACT CONTRACT EFFECTIVIT EXPIRY
CONTRACT DESCRIPTION CONTRACTOR ACCOMPLISHMEN
ID COST Y DATE DATE
T
16O00049 VALENZUELA-PUMPING STATIONS IN VALENZUELA TRIPLE 8 CONSTRUCTION & 91,773,188.54 03/05/2018 09/30/2018 100.00
WAWANG POLO AND COLOONG PUMPING STATIONS SUPPLY, INC. (FORMERLY
(COLOONG PUMPING STATION ACCESS ROAD), COLOONG TRIPLE 8 CONST. & SUPPLY)
VALENZUELA CITY (10684)
16Z00020 CONSTRUCTION OF RETARDING POND, KAINGIN BUKID, R.U. AQUINO 942,726,770.24 02/08/2018 01/12/2023 11.51
BRGY. APOLONIO SAMSON, QUEZON CITY 6TH LD CONSTRUCTION AND
DEVELOPMENT CORP. (FO
(23507)
17C00053 CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION R.U. AQUINO 192,977,262.75 10/26/2017 01/05/2019 100.00
STRUCTURES AND DRAINAGE SYSTEMS, FLOOD CONTROL CONSTRUCTION AND
WORKS - ABACAN RIVER DIKING AND SLOPE PROTECTION DEVELOPMENT CORP. (FO
WORKS, MEXICO, PAMPANGA (23507)
17C00054 CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION TOKWING CONSTRUCTION, 144,628,503.84 11/30/2017 06/27/2018 100.00
STRUCTURES AND DRAINAGE SYSTEMS, REHABILITATION CORP.(FOR; TOKWING
OF PAMPANGA RIVER BASIN, BARANGAY STA. CRUZ, SAN CONSTRUC (9650)
SIMON, PAMPANGA
17C00065 REHABILITATION OF PAMPANGA RIVER BASIN, BARANGAY D.L CERVANTES 144,295,571.48 11/24/2017 12/30/2018 100.00
SAN NICOLAS, SAN SIMON, PAMPANGA CONSTRUCTION
CORPORATION (FORMERLY:
(4965) / FERDSTAR
BUILDERS CONTRACTORS
(4965) / D.L CERVANTES
CONSTRUCTION
CORPORATION (FORMERLY:
(13799) / FERDSTAR
BUILDERS CONTRACTORS
(13799)
17CA0069 CONSTRUCTION OF LAYAC DIVERSION CHANNEL, ORANI CONSTRUCTION AND 62,390,928.15 11/24/2017 04/09/2020 100.00
DINALUPIHAN, BATAAN SUPPLY CORPORATION
(FORMERLY:ORANI
BUILDERS & SUPPLY) (5349)
17CG0082 REHABILITATION/RESTORATION OF DETERIOTED ST. GERRARD 92,034,400.00 01/25/2018 12/06/2019 100.00
DIKES/ERODED PAMPANGA RIVERBANKS ALONG CONSTRUCTION GEN.
PAMPANGA RIVER INCLUDING CANDABA CUT-OFF CONTRACTOR &
CHANNEL: SLOPE PROTECTION STA. 0+450.08--STA. 0+406 DEVELOPMENT CORP.
LEFT & RIGHT DIKE AND SAN SIMON (BRGY. SAN PEDRO), (FORMERLY:ST. GERRARD
STA. 0+070-STA.0+151.20 RIGHT CONSTRUCTION) (31762)

PCMA 2/28/2022 12:04:40 AM [The slippage indicated herein are not conclusive but subject to verification from the Implementing Office] Page 3 of 9
17CG0083 LAHAR CONTROL WORKS IN PASIG-POTRERO/GUGU RIVER HAIDEE CONSTRUCTION 95,008,819.30 10/31/2017 10/25/2018 100.00
STA. 0+188-STA. 2+100 GUGU RIVER STA. 2+300-STA.2+700 AND DEVELOPMENT CORP.
MINALIN TAIL DIKE, STA. 2+125.24-STA. 0+715 WEST MEGA (10365)
DIKE, BACOLOR, PAMPANGA
17CH0078 FLOOD CONTROL PROJECTS IN CENTRAL LUZON-FLOOD 11-16 CONSTRUCTION 60,323,432.53 09/14/2017 09/08/2018 100.00
CONTROL WORKS IN PORAC-GUMAIN RIVER, LUBAO, (29646) / FERDSTAR
SASMUAN AN BUILDERS CONTRACTORS
(29646) / 11-16
CONSTRUCTION (4965) /
FERDSTAR BUILDERS
CONTRACTORS (4965)
17CK0032 DIKING WITH SLOPE PROTECTION SACOBIA-BAMBAN 11-16 CONSTRUCTION 96,097,777.28 09/14/2017 12/11/2018 100.00
RIVER, PAMPANGA AND TARLAC (29646)
17O00020 UPGRADING OF LONGOS PUMPING STATIONS 1 & 2, BRGY. E. F. CHUA CONSTRUCTION, 96,422,308.52 12/15/2017 08/11/2018 100.00
LOGOS, MALABON CITY INC. (37826)
17O00021 CONSTRUCTION OF NAVOTAS COASTAL DIKE, NAVOTAS E.M. CUERPO, INC. (30963) 183,904,615.66 12/18/2017 01/11/2019 100.00
CITY, STA. 0+000 - STA. 0+(-425) (NAVOTAS TERMINAL)
17O00022 VALENZUELA-OBANDO MEYCAUAYAN FLOOD CONTROL PETER G. CHUA BUILDERS 89,770,023.96 12/18/2017 06/19/2020 96.61
PROJECT NAVOTAS-PROVISION OF TWO (2) PUMPING (25367)
STATIONS ALONG NAVOTAS COASTAL DIKE
(CONSTRUCTION OF PUMPING STATION WITH BOX
CULVERT ALONG COASTAL DIKE), NAVOTAS CITY
17OB0417 REVETMENT AND DREDGING WORKS ALONG SALAPAN L.R. TIQUI BUILDERS, INC. 91,670,580.16 01/30/2018 07/12/2019 100.00
CREEK (RIGHT BANK, STA. 0+020.000 TO STA. 0+500.000) (13810)
17OB0418 DREDGING AND REVETMENT WORKS ALONG SAN JUAN L.R. TIQUI BUILDERS, INC. 91,670,123.63 01/28/2018 02/04/2019 100.00
RIVER (LEFT BANK, STA. 3+638.903 TO STA. 4+700.000) (13810)
17OB0419 REVETMENT AND DREDGING WORKS ALONG SALAPAN AKN CONSTRUCTION 93,271,058.04 01/30/2018 10/19/2020 78.44
CREEK, REVETMENT LEFT AND RIGHT BANK (STA. CORPORATION (11845)
1+633.977 TO STA. 1+834.710) DREDGING (STA. 1+700 TO
STA. 1+800 AND STA. 1+900 TO STA. 2+300)
17Z00003 AGNO RIVER BASIN FLOOD CONTROL PROJECT (PHASE1)- MSB VITUG CONSTRUCTION 363,217,253.32 07/20/2017 03/02/2019 100.00
CONSTRUCTION OF PROTECTION WORKS USING GABIONS (33019)
AND MATTRESSES. BRGY. DORONGAN SAWAT, STA. 2+840
TO STA.3+140 AND STA. 3+140 T0 STA. 3+640, DORONGAN
KETAKET, STA 1+592 TO STA. 2+840 MANGATAREM; (PHASE
II-A)-R
17Z00004 REHABILITATION OF DIKE SYSTEM ALONG MADONGAN TOKWING CONSTRUCTION, 862,857,754.67 09/11/2017 12/23/2020 100.00
RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT CORP.(FOR; TOKWING
BANK), LAOAG RIVER BASIN FLOOD CONTROL AND SABO CONSTRUC (9650)
PROJECT

PCMA 2/28/2022 12:04:40 AM [The slippage indicated herein are not conclusive but subject to verification from the Implementing Office] Page 4 of 9
17Z00005 REHABILITATION OF DIKE SYSTEM ALONG CURA- TOKWING CONSTRUCTION, 862,000,881.74 10/13/2017 11/25/2020 100.00
LABUGAON RIVER (BREACHED AND ERODED DIKE, LEFT CORP.(FOR; TOKWING
AND RIGHT BANK) LAOAG RIVER BASIN FLOOD CONTROL CONSTRUC (36719) / FR
AND SABO PROJECT ESPIRITU BUILDERS AND
DEVELOPMENT CORP.
(FORMERLY: FR ESPIRITU JR
BUILDERS) (36719) /
TOKWING CONSTRUCTION,
CORP.(FOR; TOKWING
CONSTRUC (9650) / FR
ESPIRITU BUILDERS AND
DEVELOPMENT CORP.
(FORMERLY: FR ESPIRITU JR
BUILDERS) (9650)
17Z00006 REHABILITATION OF DIKE SYSTEM ALONG SOLSONA RIVER E.M. CUERPO, INC. (30963) 669,333,130.83 10/13/2017 04/25/2021 100.00
(BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK),
LAOAG RIVER BASIN FLOOD CONTROL AND SABO
PROJECT
17Z00010 RAISING OF FOLDER DIKE INCLUDING SLOPE PROTECTION E.M. CUERPO, INC. (30963) / 284,469,575.08 05/08/2018 05/06/2020 98.71
WORKS (PHASE 4: STA 2+030 TO STA. 2+530, PHASE 5: STA. G.G. UY CONSTRUCTION
5+720 TO STA. 5+200, PHASE 6) BRGY. DAMPALIT, (30963) / COCO
MALABON CITY TECHNOLOGIES
CORPORATION (30963) / E.M.
CUERPO, INC. (32319) / G.G.
UY CONSTRUCTION (32319) /
COCO TECHNOLOGIES
CORPORATION (32319) / E.M.
CUERPO, INC. (35673) / G.G.
UY CONSTRUCTION (35673) /
COCO TECHNOLOGIES
CORPORATION (35673)
17Z00011 REHABILITATION OF NAPINDAN HYDRAULIC CONTROL A.M. ORETA & CO., INC. (108) 849,082,205.37 04/02/2018 03/11/2022 94.82
STRUCTURES THROUGH DESIGN AND BUILD SCHEME, / E. F. CHUA
BRGY. BUTING, PASIG CITY CONSTRUCTION, INC. (108) /
A.M. ORETA & CO., INC.
(37826) / E. F. CHUA
CONSTRUCTION, INC.
(37826)
17Z00012 CONSTRUCTION OF GENERAL TRIAS RETARDING BASIN I R.U. AQUINO 948,256,206.34 02/06/2018 09/05/2022 39.89
(RIO GRANDE RIVER) UNDER THE FLOOD RISK CONSTRUCTION AND
MANAGEMENT FOR YLANG-YLANG RIVER AND RIO DEVELOPMENT CORP. (FO
GRANDE RIVER IN THE PROVINCE OF CAVITE INCLUDING (23507)
ROW

PCMA 2/28/2022 12:04:40 AM [The slippage indicated herein are not conclusive but subject to verification from the Implementing Office] Page 5 of 9
17Z00013 CONSTRUCTION OF GENERAL TRIAS RETARDING BASIN II MSB VITUG CONSTRUCTION 353,565,171.41 02/06/2018 10/17/2021 27.92
(YLANG-YLANG RIVER) UNDER THE FLOOD RISK (33019)
MANAGEMENT FOR YLANG-YLANG RIVER AND RIO CHICO
GRANDE RIVER IN THE PROVINCE OF CAVITE INCLUDING
ROW
17Z00018 PASIG MARIKINA RIVER CHANNEL IMPROVEMENT AKN CONSTRUCTION 294,084,711.33 02/08/2018 07/09/2022 83.65
PROJECT, PHASE V, CONTRACT PACKAGE 5 - RIVER CORPORATION (11845)
IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER
(UPSTREAM OF MARIKINA BRIDGE) STA. 16+050 TO STA.
17+450, LEFT BANK, MARIKINA CITY
17Z00019 PASIG MARIKINA RIVER CHANNEL IMPROVEMENT TOKWING CONSTRUCTION, 688,349,273.69 02/13/2018 11/07/2022 73.80
PROJECT, PHASE V, CONTRACT PACKAGE 6 - RIVER CORP.(FOR; TOKWING
IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER CONSTRUC (9650)
(UPSTREAM OF MARIKINA BRIDGE) STA. 17+450 TO STA.
18+130, LEFT AND RIGHT BANKS, MARIKINA CITY
17Z00020 PASIG MARIKINA RIVER CHANNEL IMPROVEMENT R.U. AQUINO 596,793,617.27 02/19/2018 05/03/2021 63.87
PROJECT, PHASE V, CONTRACT PACKAGE 8 - RIVER CONSTRUCTION AND
IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER DEVELOPMENT CORP. (FO
(UPSTREAM OF MARIKINA BRIDGE) STA. 18+650 TO STA. (23507) / FERDSTAR
19+350, LEFT AND RIGHT BANKS, MARIKINA CITY BUILDERS CONTRACTORS
(23507) / R.U. AQUINO
CONSTRUCTION AND
DEVELOPMENT CORP. (FO
(4965) / FERDSTAR
BUILDERS CONTRACTORS
(4965)
17Z00021 PASIG MARIKINA RIVER CHANNEL IMPROVEMENT J.D. LEGASPI 399,492,148.24 04/11/2018 05/25/2022 85.90
PROJECT, PHASE V, CONTRACT PACKAGE 9 - CONSTRUCTION (9608) / S.A.
CONSTRUCTION OF MALANDAY PUMPING STATION AND PLEYTO CONSTRUCTION
ASSOCIATED WORKS, MARIKINA CITY CORPORATION (9608) / J.D.
LEGASPI CONSTRUCTION
(33269) / S.A. PLEYTO
CONSTRUCTION
CORPORATION (33269)
17Z00022 PASIG MARIKINA RIVER CHANNEL IMPROVEMENT MSB VITUG CONSTRUCTION 714,732,784.62 02/08/2018 10/31/2021 91.61
PROJECT, PHASE V, CONTRACT PACKAGE 2 AND 3 - RIVER (33019)
IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER
UPSTREAM OF MARIKINA BRIDGE) STA. 14+100 TO STA.
15+450, LEFT BANK, MARIKINA CITY

PCMA 2/28/2022 12:04:40 AM [The slippage indicated herein are not conclusive but subject to verification from the Implementing Office] Page 6 of 9
17Z00023 METRO CEBU FLOOD CONTROL PROJECT AND DRAINAGE MSB VITUG CONSTRUCTION 142,148,174.81 02/08/2018 01/07/2020 100.00
IMPROVEMENT PROJECT - SUBANG DAKU, LAHUG, (33019) / M.E. SICAT
GUADALUPE AND BULACAO RIVER BASINS, CEBU CITY CONSTRUCTION, INC.
(FORMERLY M.E. SICAT
(33019) / MSB VITUG
CONSTRUCTION (16724) /
M.E. SICAT CONSTRUCTION,
INC. (FORMERLY M.E. SICAT
(16724)

PCMA 2/28/2022 12:04:40 AM [The slippage indicated herein are not conclusive but subject to verification from the Implementing Office] Page 7 of 9
REGION: CENTRAL OFFICE
IMPLEMENTING OFFICE: ROADS MANAGEMENT CLUSTER I (BILATERAL)
%
CONTRACT CONTRACT EFFECTIVIT EXPIRY
CONTRACT DESCRIPTION CONTRACTOR ACCOMPLISHMEN
ID COST Y DATE DATE
T
17B00060 ASSET PRESERVATION CONTRACT-PREVENTIVE R.D. INTERIOR JUNIOR 206,607,204.73 03/01/2018 03/08/2019 100.00
MAINTENANCE (APC) COMPONENT, JICA LOAN CONSTRUCTION (6483)
AGREEMENT NO. PH-247 PM 01: CABAGAN-SAN PABLO
ROAD SECTION (DAANG MAHARLIKA), K0444+000.00 TO
K0460+752.00 W/ EXCEPTIONS, CABAGAN-SAN PABLO,
ISABELA
17F00085 PREVENTIVE MAINTENANCE-ASPHALT OVERLAY OF LIBON- WCS CONSTRUCTION, INC. 188,991,870.06 05/11/2018 01/06/2019 100.00
PANTAO-PIODURAN ROAD SECTION ALONG ALBAY WEST (6516)
COAST ROAD, LIBON, ALBAY PROVINCE
17K00422 AWP 3/PM,KIBUNGSOD-STA. CRUZ SECT.K1283+000- EQUI-PARCO 172,414,095.60 03/12/2018 09/22/2018 100.00
K1293+086,MIS.OR.ASP.OVERLAY,REBLOCKING OF PCCP & CONSTRUCTION COMPANY
MISC. (14332) / TRIPARCO
DEVELOPMENT
CORPORATION (14332) /
EQUI-PARCO
CONSTRUCTION COMPANY
(23327) / TRIPARCO
DEVELOPMENT
CORPORATION (23327)
17K00423 AWP 3/PM, STA. CRUZ-TALISAYAN SECT.,K1293+086- EQUI-PARCO 172,509,591.69 03/12/2018 09/22/2018 100.00
K1303+000,MIS.OR.,ASPH. OVERLAY,REBLOCKING OF PCCP CONSTRUCTION COMPANY
&M (23327) / TRIPARCO
DEVELOPMENT
CORPORATION (23327) /
EQUI-PARCO
CONSTRUCTION COMPANY
(14332) / TRIPARCO
DEVELOPMENT
CORPORATION (14332)
17K00424 AWP/3/PM-13,DALWANGAN-PATPAT-SAN JOSE M. MONTESCLAROS 182,379,429.13 03/14/2018 07/29/2018 100.00
SECT.,K1496+800-K1510+100,BUKIDNON ENTERPRISES, INC. (6506)
17L00200 AWP3/PREVENTIVE MAINTENANCE, ALONG DAVAO- ALGON ENGINEERING 149,715,312.41 04/23/2018 11/10/2018 100.00
COTABATO RD,DAVAO CITY JCT. DIGOS SECT. K1525+(-)100 CONSTRUCTION
-K1532+ CORPORATION (00270)

PCMA 2/28/2022 12:04:40 AM [The slippage indicated herein are not conclusive but subject to verification from the Implementing Office] Page 8 of 9
17L00221 PRE-FIXED PREVENTIVE MAINTENANCE (PM),ROAD ULTICON BUILDERS, INC. 484,814,792.67 07/02/2018 06/26/2019 100.00
UPGRADING & PRESERVATION PROJECT(RUPP) UNDER (7249) / MAC BUILDERS
JAPAN INT'L. (7249) / ULTICON BUILDERS,
INC. (17267) / MAC BUILDERS
(17267)
17Z00008 UI-3, CONTRACT PACKAGE VA: MAMBURAO ROAD FREY-FIL CORPORATION 217,849,631.78 05/23/2018 03/10/2022 0.00
SECTION, MINDORO WEST COAST ROAD IMPROVEMENT (FORMERLY:FREYSSINET
PROJECT (K0399+800.00-K0402+990.00), UNDER ROAD FILIPINA (31521)
UPGRADING AND PRESERVATION PROJECT (RUPP),
UPGRADING/ IMPROVEMENT (UI) COMPONENT, JICA LOAN
AGREEMENT NO. PH-P247
TOTAL NUMBER OF CONTRACTS: 43