Professional Documents
Culture Documents
REVIEW
LOG DATE ELECT
IN COMM NO. I&C
A APPROVED SUPORT
B APPROVED AS NOTE CONTRACTOR
C NOT APPROVED RECORD
I INFORMATION WORKING DOCUMENT
DISTRIBUTION
APPROVAL DOES NOT RELIEVE
CONTRACTOR FROM APPROVED BY
RESPONSIBLE FOR ERROR OR
DEVIATIONS FROM CONTRACT
REQUIREMENTS ( )
BY : DATE :
LOG DATE
OUT COMM NO.
PROJECT :
KALSELTENG 2 CFSPP(2x100MW)
DATE
METHOD STATEMENT FOR LIGHTING SYSTEM INSTALLATION
QAQC CONSORTIUM
PLN IKCP0-YYD-E-05-112-08 1
OWNER PROJECT CONTRACTOR DOC. NO.
KALSELTENG 2 CFSPP(2x100MW) IKCP0-YYD-E-05-112-08
CONTRACTOR TITLE ISSUED DATE
13 AGUSTUS 2018
METHOD STATEMENT FOR LIGHTING SYSTEM
INSTALLATION REVISION
1 OF 7
1
Table of Contents
1. PURPOSE............................................................................................................... 2
2. SCOPE.................................................................................................................... 2
3. REFERENCES DOCUMENT...................................................................................2
6. WORK PROCEDURE..............................................................................................3
6.3 HANDLING & STORAGE...............................................................................................4
6.4 PREPARATION............................................................................................................ 4
6.5 INSTALLATION............................................................................................................ 4
7. INSPECTION...........................................................................................................6
8. HSE STATEMENT...................................................................................................6
9. QUALITY PLAN...................................................................................................... 6
10. DOCUMENTATION.................................................................................................7
1. PURPOSE
The purpose of this Method Statement is to provide the work methods for installation of
Lighting and Receptacle to assure compliance with applicable specification and drawing for
KALSELTENG 2 CFSPP-2x100MW.
2. SCOPE
The scope of this Method Statement covers the objective and requirement of Lighting and
Receptacle for KALSELTENG 2 CFSPP-2x100MW.
3. REFERENCES DOCUMENT
This method statement should be read in conjunction with the latest approved revisions of
following documents:
Issued for Construction Drawings
Project Quality Plan
Project HSE Plan
6. WORK PROCEDURE
6.2 GENERAL
The applicable drawings and requirements shall be reviewed before installation of
lighting and receptacle. If any deviations are occurred in the result of the drawing
review, it shall be informed to manufacturers and engineering department to clear this
matter.
6.5 PREPARATION
6.4.1 Ensure that the work area is ready and safe to start the installation of lighting and
receptacle.
6.4.2 Check and ensure that shop drawings and materials ready to use for installation
are latest and approved for construction.
6.4.3 Ensure that the materials and accessories received from site store for the
installation of lighting and receptacle complete with accessories are free of rusty
parts and damages.
6.4.4 The correct type of lighting, receptacle & accessories shall be ascertained from
the approved shop drawings prior to installation.
6.5 INSTALLATION
LIGHTING FIXTURES, RECEPTACLE/POWER SOCKET
6.5.1 The approved work plan should be followed.
6.5.2 Fields supervisors shall provide the plans for verification of any critical dimension
and portion/locations before proceeding the work.
6.5.3 Careful handling of lighting fixtures and receptacles upon installation must be
properly implemented to avoid damages.
6.5.4 Installed lighting fixtures and receptacles shall be aligned and levelled properly. It
must be free of dirt or any chemical impurities.
6.5.5 Prior to installation, check lighting fixtures accessories and make sure internal
connection are completed.
6.5.6 Unless otherwise shown, mounting heights of lighting fixtures shall be generally
as follows:
A) I) Low bay lighting fixture in general indoors areas of industrial plants shall
be 3500mm from bottom to finish.
II) Medium bay lighting fixture shall be 3500mm to less than 7000mm from
bottom to finished floor.
III) High bay lighting fixture shall be 7000mm and above from bottom to
finish floor.
B) Light over door openings shall be 300mm bottom of fixture above top of
opening.
6.5.10 AC & DC shall not be run in the same conduit and junction box. Circuit fed from
different transformer and different batteries (DC source) shall not be run through
same conduit and junction boxes.
6.5.11 Receptacle circuits shall be kept separate and distinct from lighting circuit.
6.5.12 For classified hazardous area having flammable gases and vapors only, all
items and accessories of illumination system shall be explosion proof.
6.5.13 The lighting and small power system will meet the requirements established in
Applicable standard for the appropriate hazard classification.
6.5.14 All outdoor lighting located in wet locations and small power circuits will use
ground-faults circuit interrupter (GFCI) protection for safety.
6.5.15 Elevation of lighting fixtures shall be in accordance with AFC.
6.5.16 Correct rated voltage of power supply shall be check prior for energizing.
6.5.17 Continuity & Insulation resistance test for each circuit shall performed prior for
energizing. It must be recorded. Refer value continuity is 0,5Ω and Insulation
megger > Over limit or 10 GΩ.
6.5.18 Illumination test shall be performed during energizing and must be recorded.
that all requirements are met. All inspection and testing shall be in accordance
with inspection plan.
6.5.28 Dielectric test ensures no leakage current induced from ground panel or neutral
to phase.
6.5.29 Fit up drawing diagram inside panel for guidance
6.5.30 Tighten check connection of termination and identification.
6.5.31 The Emergency lighting is Essential Lighting, refer to Distribution panel different
with Normal Lighting have another Panel Essential for backup power from
Essential Low Voltage UPS battery system. wire and number marking group
refer to drawing Distribution panel to Essential Panel.
7. INSPECTION
Upon completion of the installation, construction engineer shall notify QC engineer for the
required inspection to assure correct erection & installation as per the requirements.
All inspection and testing shall be performed in accordance with the inspection and test plan
and the results shall be documented on the inspection and test report.
8. HSE STATEMENT
In the lighting and receptacle works, the following statements shall be implemented to
ensure safe completion of the works.
Where required, ensure PTW requirement and conditions are satisfied.
Personnel health, safety and environment protection shall take priority over all
activities.
Adequate and appropriate PPEs shall be provided for all personnel.
Illumination/ventilation shall be provided, if required.
Housekeeping shall be done.
Suitable access shall be provided to work site.
If any work activity is unsafe, do not start, whereby it has started already, do not
continue.
Compliance with all project HSE procedure.
9. QUALITY PLAN
Competent QA/QC inspectors shall carry out/witness inspection and testing of all installation
work and also conduct a final inspection upon completion of the installation in accordance
with the ITP for Lighting and Receptacle.
10. DOCUMENTATION
All reports and other documents resulting from the inspection and other checks as applicable
during the process of this installation work shall be prepared, controlled, maintained and
formally issued upon work’ completion.