Maintenance Schedule of Electrical Point Detector (EPD)
Index New to SEM Similar (Not mentioned Explicitly in Earlier edition) Schedule Code changed (Periodicity changed) Periodicity Schedule Code Fortnightly ED1 Monthly ED1 Quarterly ED1 Half Yearly ED2 Yearly ED2 Schedule Code: ED1 Same as Periodicity: Technician(Signal): Fortnightly, earlier Sectional SSE/JE(Signal): Monthly, SSE(Signal)/Incharge : Quarterly S.No. Check the following: 1. The contacts to Make or break at same time. Monthly (ED2) 2. The cross-protection contact makes only after concerned detection contact open. For Non- Monthly RE area. (ED2) 3. Normal detection opens then only normal shunt contact make and vice-versa. For Non-RE Monthly area. (ED2) 4. Shunt contacts – For Non-RE area. Monthly (ED2) 5. Sleepers are packed well. Monthly (ED2) 6. Entire contact of ED free from rust & pitting. NA 7. Pressures of contact of ED. NA 8. Tightening of all nuts and screws and nuts on lugs. Wires are neat and tidy. Monthly (ED2) 9. Slides are having free movement. Same as earlier 10. Oiling the slides & rollers with the axle oil Grade Medium to IS: 1628. Same as earlier 11. Testing and adjusting–for normal and reverse setting of point by obstruction test to ensure Same as with 1.6 mm test piece detector contracts just make, with 3.25 mm test piece by fictitious earlier locking contacts just break and with 5 mm test piece point is not locked and detector contacts not make and point lever should not latch. 12. Weeding out of bushes/clearing of ballast in and around working/moving parts. NA
Schedule Code: ED2
Periodicity: Sectional SSE/JE(Signal): Half-yearly SSE(Signal)/Incharge: Yearly 1. Testing of point cable from K Board in N & R position of point with 100 V megger. Same as earlier