Professional Documents
Culture Documents
Practical guidelines
for qualifying purified
vvjater systems
Purified water (PW) plays a pivotal role in
pharmaceutical processing. This article describes the
steps required to qualify and validate PW systems at
different stages of the project phase.
Annelie Hultqvist urified water (PW) is used in the pharmaceutical industry as a raw
P material in production or to clean equipment. It is, therefore,
important that the water meets the set standards and constantly
provides the specified quality and quantity to ensure there is no
contamination of the product or equipment. Depending on quality, raw
water can be difficult to purify, and can require various processing stages
to obtain PW quality. Raw water quality can also change with the
seasons so conducting regular inspections, tests and samples is
imperative to ensure that the installation complies with regulations and
the user's requirements on a continuing basis.
product (e.g., water quality} should be tested under an installation inspections, approval, project
performed before compiling the URS. qualification (IQ) or an operation execution, organization,
The requirements relating to the safety qualification (OQ). To find and select responsibility and authorizations. This
of plant operators must be part of the the typical Q requirements for the guarantees that activities are
risk analysis that occurs for CE marking system, the ISPE's Baseline Guide performed according to the
ofthe installation, according to the Volume4, Woter&SteamSystems^^ requirements set within the agreed
machinery directive. and FDA's Guide to Inspection of High- framework, it is also useful to write
Purity Water Systems^ "^ can provide down practical details of project
assistance. execution that are not dealt with in
The easiest way to create the URS. This would define:
A well-devised QPR which has been traceability in the project Is to write • How communication is performed.
agreed on and signed by both parties, the requirement specification in table • How the information will be
format, with the requirements delivered to the project manager,
saves time and makes it easier to divided into C and Q requirements, • Exceptions to the agreed protocols.
complete activities such as design, which can then be given to the • Thedocument approval process.
installations and tests. supplier as a Word document for • The people responsible for
further processing and completion of reviewing and approving the
the references to design documents documents.
and tests. The supplier can then • The number of days assigned to
it is an advantage to divide the create a traceability matrix from the the review process.
requirement specification into'C'and file, or copy the requirements to an • in which form comments must be
'Q' requirements with the help of the Excel table. This avoids having to returned.
risk analysis performed. This is write the requirements in the matrix • The amount of time allocated for
described in the ISPE Baseline Guide again, thus eliminating a possible amendments and updates, and
Volume 5, Commissioning & source of errors and saving time. how the conclusions and approvals
Qualification.''^ C stands for are obtained.
commissioning and the requirement Quality and project plan Comments should be specified
will then be tested under a factory A quality and project plan (QPP) is in writing and compiled in one
acceptance test (FAT) or a site devised at the beginning of a project. document clarifying who has
acceptance test (SAT). Q stands for The purpose of this is to establish commented on what For fast-track
qualification and the requirement is parameters for quality control (QC), projects, these approval routines are
particularly important and must be
established at the beginning of the
project, it is also recommended that
Figure 1 V-model: verification of the system according to the design. the number of approving parties is kept
to a minimum. The user should specify
which routine applies to change
Concept and basic design
Consurtancy requests in the project and from when
URS by Christ it is applicabie. A well-devised QPP,
which has been agreed on and signed
by both parties, saves time and makes
Quality and project it easier to complete activities such as
plan design. Installations and tests. An
interface agreement should also be
issued early in the project and wiil
OQ
Functional specifications clarify details regarding tie-in points,
Sysrem acceptance test
control system interfaces and media.
Volume4 Water & Steam Systems^^ Design verification the factory, it is quick and efficient to
from ISPE is essential. The design is verified in relation to the make any changes to eliminate any
user's requirements, ensuring they will deviations.
Design documents be complied with. This is easily done During FAT and SAT, typical
The following design documents by establishing a traceability matrix in C-defined requirements will be tested
are consulted for a water treatment table form from the URS (Table 1). according to good engineering
system: practice (GEP) as described in the
• piping and instrumentation diagram Design approval ISPE Baseline for Commissioning and
(P&ID) The design approval is an important Oualification.^^TheC requirements
• functional specification (FS) milestone in a project as it makes do not have a direct impact on the
• software design specification it possible to progress with product quality and it is an advantage
• hardware design specification (HDS) manufacturing and programming. to per-form as many of those tests
• electrical schematics To reach an approval it is necessary as possible in the factory. To get an
• layout drawing to review all design documents impression of process vaiues, product
• component list and drawings according to the quality and system capacity, these
• instrument list requirements (Figure 2). values can be recorded in the factory.
• valve list. The C requirements not tested during
The documents illustrate the set Acceptance tests EAT will be performed onsite within
installations and functions of the With today's tight time schedules, the SAT Protocol. The FAT and SAT
system. When the system is built, the a FAT is very useful for the new results will be presented in a FAT and
design specifications will be used for installation of a plant. The advantage SAT report respectively.
the verification of the system during is that premanufactured units are
commissioning and qualification. At the checked and tested as much as Installation qualification
end of the project, when all inspections possible before they are sent to This is performed by a number
and tests are performed and possible site. This is of absolute necessity, for of different verifications, such as
deviations are measured, it is important example, in a turn-key project where mechanical inspections, instrument
that the 'as built'design documents are lots of equipment shall be installed calibrations and documentation
included into the documentation of the and commissioned in a short time verifications. It is recommended
frame. If the skids/units are at to include a review of the FAT/SAT
system (Figure 1).
microbiolog
the specific
needs of pharmaceutical applications
Our range of gamma-irradiated, highly lilterable For genetic identification and characterisation,
culture media includes cold filterable Trvplone the fully automated DuPont Qualicon
Soya 8roth and its meat-free alternative, cold RiboPrinter* system provides important
filterable Vegetable Peptone Broth. strain-level information. Ready-to-use QC
micro-organisms include disposable
Environmiintal MDnitorin;}
bactertoiogical Culti-Loops^ and Ouanti-Cuil
Products indude tfie new Oxoid Air Sampler: Plus^' vials of known bacterial counts.
irradiated, triple wrapped (permeable or VHP
impermeable) contact anfl settle plates; and So when you need to talk microbiology,
triple-wrapped swabs, talk to Oxoid.
subscribe at www.ptemagazine.com 25
Hultqvist
reports at the start ofthe IQ to ensure according to the project schedule on critical deviations were identified, the
that all deviations have been closed. the iQ precisely, otherwise the IQ test OQ can begin.
The sequence of test performances could be open until both IQ and QQ
also needs to be considered. The slope are ready and the final Operation qualification
of the pipes must, for example, be documentation has been copied. A TheQQ will verify the operation of the
measured before the distribution pipe good way of performing document system according to the descriptions
is insulated — in the case of a hot inspections is to have a document in the FS highlighted as critical for
distribution system — which often schedule clearly indicating which the product. The acceptance criteria,
occurs before the IQ is started because documents must be completed by particularly for the QQ, must be
the instaiiation is ready. when in the project. When the IQ is carefully evaluated — which
Documentation verification is a test finished and reviewed, the result is conductivity and temperature must be
where the status must be checked presented in the IQ report and, if no complied with? Which flow? What are
the actual limits? What is acceptable
for the process and the product? The
product requirements depend on the
Table 1 bility matrix showing in which protocols and tests the reauirements will be met. water quality that the system has
Request number QC Description Protocol been designed to achieve.The process
engineer should also have evaluated
URS.2301-01 3.2,1 AH instrumental- FAT-50303-01 FAT03 suitable alert and action levels for the
mounting sites SAT-50303-04 SAT02 process, which form the basis for the
(measurements alarms generated by the system. When
sites) must be all tests are performed and reviewed,
marked with the the result of the OQ is presented in
TAG number, indicated the QQ report. If no critical deviations
in the P and I diagram. were identified, the PQ can start.
subscribe at www.ptemagazine.com