You are on page 1of 4

QA/QC

Quality Assurance
in Surveying &
ssential to client service
and long-term profession-
al and business success
is your commitment to
Mapping, Part 2
producing quality work
that is in accordance with
industry and client mandated standards, >> By Fred Henstridge, LS
on schedule, and within budget. It is
also, in my opinion, a means to raise our
surveying profession to the professional
and business status we constantly strive
to achieve.
In a recent edition of CNN Money there
was a report on the value of a proper
boundary survey to a homeowner or
buyer provided by a qualified licensed
land surveyor. I was appalled at the
CNN reporter’s comments and mention
of the price to pay. The report stated that
a proper boundary survey made under
the direction of a qualified licensed
land surveyor should be priced at from
$500 to $1,500. First of all the reporter
should not have stated any price, since
boundary surveys — depending on
locale, conditions, research and field
work required — cannot be priced
across the board. This gives the public
a false sense of expectations of what
the professional surveyor does. In
today’s economic environment the cost QC When making a GPS control survey, make sure to record everything about the
to equip a field survey crew can run as station in the field, including weather conditions.
high as $80,000. This is the case if you
consider the cost of the vehicle, total and client service for surveying and established. These review and checking
station, digital level, GPS receivers and mapping professionals. My approach to procedures may require modifications for
miscellaneous survey equipment. When QA is based on the management of the specific projects and will require periodic
you consider your capital, labor and processes rather than accepting or reject- updating, primarily by the project or
overhead costs it would take an awful ing results at the end of the project. This survey manager.
lot of $500 boundary surveys to stay in assures a total quality approach thus
business. This is why we must continue saving time and money and meeting the 5 Steps to Quality
to improve our technical skills, quality expectations of the client. In order to Assurance
and client service. assure the accuracy and completeness In accordance with Deming’s 14 points
As mentioned in my previous article of project deliverables and documents, [see previous article] I believe there are
[May 2006], I have formulated a five- specific quality assurance review five basic steps to insure quality and
point plan for Quality Assurance (QA) and checking procedures should be outstanding client service in surveying

30 Displayed
July/August with
2006 permission
The American• Surveyor
The American Surveyor • July/August • Copyright 2006 Cheves Media • www.TheAmericanSurveyor.com
Unless a specific plan is required by the
contract, at a minimum the following
should be considered as appropriate
quality assurance measures:
Detailed statement of work and scope
of required services
Schedules, budgets and milestone
points
Precise definition of required
deliverables, contract standards, client
imposed standards, and/or industry
standards to be used
The use of advanced technology
Tasks and responsibilities
Adherence to established industry and
professional standards
Forms and reporting documents that
will be required
Compliance with client-mandated stan-
dards and deliverable requirements
Statements of safety procedures for
QA Take pencil rubbings of the station mark, copy to a PDF file, and fieldwork
store with the project data.
The Project Delivery Plan should
and mapping. These steps may be Project Delivery Planning include time and budget allowances for
defined as: Quality assurance begins with Project reviews and checking — Quality Control,
Project Delivery Planning Delivery Planning. Technical standards or QC — that are a part of the QA
Adherence to Established Standards and specifications, defining of deliverable program. A few examples of your QC
Clear Assignments of Tasks and items, and milestone schedules will be plan might include the following:
Responsibilities identified at the project planning stage. Survey or mapping criteria
Tracking and Documentation A written quality assurance plan is an Definition of standards and/or agency
The Use of Qualified Staff element of all work plans. These plans or client manuals to be used
vary widely by service and tasks being Survey or mapping criteria review and
performed. The following guidelines checking forms
can be used as a general checklist for the Drafting and CAD standards to be
main elements of any project work plan. used
Computer calculation
review forms
Field survey forms
required for the project
Internal review forms and
checklists

Adherence to
Standards
Three types of established
standards should be
considered for each project:
industry or discipline
standards, client-imposed
standards, and your firm’s
standards. Industry stan-
dards may be considered the
minimum level of standards
for a given project. These
are the common standards
used throughout the
industry or discipline and
are generally based on
liability and protection of
QC Verify the station and monitor the the public. Client standards
data collection during the survey. are those unique standards

32 Displayed
July/August with
2006 permission
The American• Surveyor
The American Surveyor • July/August • Copyright 2006 Cheves Media • www.TheAmericanSurveyor.com
subcontractors involved with this project.
Management of these elements and
insuring their compliance with the work
plan, standards, schedule, budget and
high quality results will be the major task
of the project manager. To insure quality
and adherence to the project standards
the project manager should schedule site
visits within the scope of the project and
should:
1. Provide a complete project briefing
prior to commencement of any work.
The briefing should include all staff and
subcontractors assigned tasks on the
project.
2. Provide all team members or
subcontractors with a written work
plan including a description of tasks,
schedule, budget and specifications for
the work involved.
3. Have the subcontractors transmit
weekly situation reports to the project
QC When taking digital photos of a monument, make sure to capture a vicinity view, manager via e-mail
a medium close view showing the area immediately adjacent to the monument, and 4. Manage all milestone events on an
a close-up view of the monument showing any markings or tags. individual basis, i.e., the team members
or subcontractors should not begin a
new set of tasks until the milestone for
the previous set of tasks has been met
and accepted for quality and adherence
to the stated project standards.

Tracking and
Documentation
Cost control is synonymous with quali-
fied staff, technical excellence, quality
assurance and good project manage-
ment. For any assignment you should
consider the use of the following:
QC Medium close view QC Macro view Qualified, licensed professional survey-
ors who are in responsible charge of
required by the client for the project. select the checking program and review the work, and technical experts whose
They may include CADD standards, forms applicable to a particular project. qualifications are specific to the task.
drafting styles, and the level of confi- They may add additional review forms All work should be carried out under
dence (sigma) required for the data. Your and checking program items that are the direct supervision of a locally
firm’s standards are those developed unique for that project. licensed land surveyor.
by you for your local conditions or On a specific project, the project State-of-the-art survey equipment,
in-house operations. These standards manager takes responsibility for the survey software, desktop and
focus on client service, communication, implementation of a QA Program for notebook computers, communications
reporting, documentation, and the use the entire project. This includes making equipment, and the Internet access for
of advanced technology, such as GPS, sure that the project team has a clear transmittal of data and reports.
LIDAR, Ground Penetrating Radar and understanding of the latest scope of work Quality control provided at all phases
safety. When preparing a work plan you and contract conditions, and has the of the work.
will need to consider all three types of available staff and resources to perform Hands on survey, mapping, imagining,
standards and communicate these evalu- quality work. The survey managers or GIS, modeling and photographic
ations and decisions to the client prior to project surveyors take responsibility for supervision and project management.
approval of the plan or acceptance of the the detailed standards, checking, and Time and cost reporting accounting
assignment. reviews required. systems. These costs should be traced
on a weekly basis; on smaller projects
Tasks and Responsibilities Resource Management you may want to track labor costs
During the project planning and start-up A major part of the assignment of tasks on a daily basis. You should have a
phase, you will need to work with the and responsibilities will be the manage- standard time reporting method for all
technical managers and office staff to ment of the various team members and employees.

34 Displayed
July/August with
2006 permission
The American• Surveyor
The American Surveyor • July/August • Copyright 2006 Cheves Media • www.TheAmericanSurveyor.com

Coordination and communications Field observers will be instructed to
are equally critical to quality and cost enter any unusual occurrences in the
control. remarks section of the observation
Communications within the team log.
should be conducted on a daily basis Observers will be instructed to
in person or via telephone, fax, verify station descriptions and to
and/or e-mail. Data files should be provide a station mark rubbing at
transmitted on a daily basis to the every station occupation.
project manager to be reviewed and Adherence to the Milestones as
archived. Client communications indicated on the project Schedule
should be focused through the and Task Order Statement of
project manager. Clients should Work.
be furnished with weekly status Internal team meetings on a
reports and information of any unique minimal weekly basis to monitor
situations requiring client input. progress.
Today most of this reporting can be Daily QA reviews and progress
transmitted via e-mail. meetings by the project manager.
Pencil rubbings will be taken at all
Qualified Staff  ll receivers will be dual frequency,
A stations occupied along with ample
Training is a critical element of a QA full-wavelength and have sufficient free digital photographs including area
program. Trained professional, technical memory to record project data. The views, station close-ups and witness
and administrative staff provide a basis necessary tracking data will be entered posts. All digital photographs will be
for all of your technical excellence, (i.e., tracking rate, minimum number checked for quality (color, brightness
development, innovation and client of satellites, elevation mask, HI and and contrast) prior to inclusion with
service. At a minimum you should 4-character ID). the project files. Photos not meeting
consider providing or participating in All antennas will be of geodetic qual- the quality standards will be retaken.
technical or management training on ity, have a suitable ground plane and Daily back up of all digital data on a
at least an annual basis. This training have an antenna calibration approved secure server site.
should include, but not be limited to: by the National Geodetic Survey. Again, the above is a sample checklist
Basic project management Antennas will be oriented to north for for a GPS control survey and should be
Advanced project management all station occupations. considered as a minimal list. You should
Technical training classes Data will not be deleted from the develop standard QC checklist for all
GPS receiver until it has been verified in the of your survey and mapping task, such
Remote sensing and imagining field and office/headquarters. a boundary surveys, ALTA surveys,
Geodesy Vectors shall be processed using a topographic surveys, etc. Once these
Uses of new field to office software 15-degree elevation mask. checklists have been developed, they
Client services and communications Where applicable, data from selected should be incorporated into your work
CADDs and computer modeling CORS stations will be incorporated plan and adhered to as part of your QA
training into the project. Contact will be made program. This will provide the basis for
Basic office tools with CORS operators to ensure that the consistency of purpose for improving
the selected stations will be operational your services and for remaining competi-
Typical Checklist during the planned project observa- tive while providing superior customer
For any survey task you should develop tions. service as stated by Deming.
a QC checklist as a part of your QA pro- A series of adjustments (both hori- In subsequent columns I will expand
gram. The following is a sample checklist zontal and vertical and both free and on each of these five basic steps and
for a typical GPS control survey. These constrained) of all project data will be provide some examples of real world
QC measures may include, but not be accomplished to ensure that all project situations.
limited to: data meet project accuracies.
Preparation of a Project QC Plan prior Repeat project station occupations (if Fred Henstridge has more than 50
to the commencement of any work. required) will be observed on different years of professional experience in
Project personnel will be fully trained days with a minimum of three hours geomatics engineering, surveying,
in all aspects of the GPS project. between the two times of day. mapping, transportation engineering,
All survey work is to be carried out Fixed-height tripods will be used for municipal engineering, and GIS man-
under the supervision of a local licensed all station occupations. All poles will agement. After 10 years with Caltrans,
land surveyor trained and qualified in be checked for plumb prior to the he started his own geomatics and civil
geodesy and in the use of the firm’s beginning of the project and after any engineering firm, which was acquired
GPS equipment and software. event that might impact the accuracy by Psomas and Associates in 1982.
Plot all existing geodetic stations and of plumb. Since that time, he has been a Princi-
proposed locations considered for the Sample observation logs will be pal of Psomas, and Corporate Director
project as an overlay on a topographic provided to ensure that all necessary of Geospatial Services and GIS. He is
map for use in reconnaissance and information is obtained during currently Director of Psomas’ Federal
GPS mission planning. tracking. Programs Development.

36 Displayed
July/August with
2006 permission
The American• Surveyor
The American Surveyor • July/August • Copyright 2006 Cheves Media • www.TheAmericanSurveyor.com

You might also like