Crashing Assignment
Crashing Assignment
CRASHING
ASSIGNMENT
B 8 250 5 400
C 2 100 2 100
D 6 300 3 600
E 3 150 2 300
F 4 275 3 300
G 9 700 8 900
1. Perform the activities crashing until it can no longer be crashed. What is the total
cost?
2. If there is a bonus of $125 per day for finishing early, what activities would be crashed,
and how fast would the project be completed?
QUESTION 1: Perform the activities crashing until it can no longer be crashed.
What is the total cost?
1
Run 3 on crash on B and D with total cost of 2350.
QUESTION 2 : If there is a bonus of $125 per day for finishing early, what
activities would be crashed, and how fast would the project be completed?
Based on the Figure 2 Crashing Activities Table, crashing activities as per mentioned
in the table in red. They are B,B,F,B,D,G,D,E,D.