Yarmouk University

Hajjawi Faculty of Engineering and Technology

Industrial Engineering Department

project management (IE 361 )

MINI PROJECT
DONE BY
• MOMEN AL-JAMAL 2020986118
• MARYAM RAED 2019986114
• OBAIDA EMAD 2020986117
• MOHAMMAD HAZAIMEH 2018986058
• OYES MAHAFZAH 2020986012
• MORAD MOMANI 2019986188
INTRODUCTION

• Our project will follow a specific plan to build a house


equipped with good equipment and materials, commensurate
with the demands of its owner, and in which there will be a
double effort to prevent earthquakes and natural disasters in the
shortest possible time
• Our project will follow a specific plan to build a house
equipped with good equipment and materials,
commensurate with the demands of its owner, and in
which there will be a double effort to prevent earthquakes
and natural disasters in the shortest possible time.

• We will follow a specific work sequence (in the next


slide)to design and create the house.
TASK NAME ES EF LS LF SLACK (LS-ES)

a 0 9 0 9 0
b 0 12 1 13 1
c 0 10 8 18 8
d 9 17 12 20 3
e 9 14 9 14 0
f 14 23 14 23 0
g 12 17 13 18 1
h 17 22 18 23 1
i 17 20 20 23 3
k 23 30 23 30 0
• The probability of completing the project on time:
Critical path time (Te) = 30 days
Variance = 1.44
Standard deviation =1.2
Z= (30-30)/ (1.2) =0

The probability = 50%

• The probability of completing the project before 90% of its duration estimate
0.9*30 = 27 days
Z=(27-30)/(1.2)= -2.5
Z(-2.5)=0.0062

The probability =0.62%


Activity Duration, days (normal , Cost (normal ,
crash) crash) What should you do if you
1 start 0.0 0 are asked to complete the
2 site clearing 9,6 3000,4200
project in 75% of its
3. Plinth beam or slab 12,9 2000,2500
4 foundation 10,9 5500,6200
estimated duration
5 flooring 8,6 2000,2500 (crashing of activities)?
6 brick masonry 5,4 4000,4200
7 the lintel 9,7 2500,4000
8 superstructure 5,5 1000,1000
9 Electrical and 5,4 5000,5800
plumbing
10 exterior and interior 3,3 18000,18000
finishing
11 bricklaying 7,5.5 4000,6000
12 end 30,22.5 47000,54400
Activity Slope($/day)
1 start 0
2 site clearing -400
3. Plinth beam or slab -166.6
4 foundation -700 •If we want to complete the project
-250 in 75 % of activity
5 flooring
6 brick masonry -200 • reduce (a) by 2 day 1200$
7 the lintel -750 •reduce (e) by 1 day 200$
8 superstructure 0 •reduce (f) by 2 day 1500$
9 Electrical and plumbing -800 •reduce (k) by 1.5 day 2000$
10 exterior and interior 0
finishing
-1333.3 •Spend (47000$) the cost of
11 bricklaying project +1200$+200$+15000$
+2000$=51900$ to complete the
project in 22.5 days
D(8,4) I(3,0)

A(9,0)

E(5,0)

START B(12,0.4) F(9,0.4) K(7,1) END

G(5,1)

C(10,4)

H(5,1)