GOVT. OF ODISHA
Name Of Beneficiary
Year : 2020-21
Work code :
AAP Sl No in Block :
REPORT
GP. The project has been approved under MGNREGS Action plan
for the year 2016-17 having AAP sl no
As per the site condition the estimate has been framed with the necessary
items as follows:-
1 Earthwork in hard soil.
2 Dry stone masonary or rough stone dry masonary for well steining
3 K.B.Brick masonary in CM (1:6)
4 Provision of a crèche at site for Childs.
5 Cost of Transporting Board and etc.
6 cess 1%
The estimate has been prepared as per current schedule of rate with labour
rates of minimum Rs.174/- per day. 10% O.H.C. has been excluded as the work is to
The Orissa detailed standard specifications will be followed during execution of the
work.
Name of Beneficiary -
Sl Activity Code Detail of Activity / Items Unit Cost Unit Quantity Total
No. Amount
1 2 3 4 5 6 7
Earth work excavation in hard soil or gravelly soil in
open well within 50m iniial lead and 1.50m initial lift
1 including rough dressing and breaking clods to
maximum 5 cm to 7 cm and laying in layers not
exceeding 0.30m depth and as per the direcion of
the Engineer-in-charge.
ODACT207 (i) 1st depth 5'-0"(1.50m) 259.89 Cum 12.839 3336.74
ODACT206 (ii) 2nd depth 5'-0"(3.00m) 343.69 Cum 12.839 4412.60
ODACT209 (iii) 3rd depth 5'-0"(4.500m) 464.53 Cum 11.127 5168.85
ODACT210 (iv) 4th depth 5'-0"(6.00m) 585.38 Cum 1.300 760.99
ODACT211 (v) 5th depth 5'-0"(7.50m) 958.88 Cum 0.000 0.00
ODACT212 (vi) 6th depth 5'-0"(9.00m) 1121.84 Cum 0.000 0.00
16 ODACT012 16 mm thick cement plaster [1:6] over Brick 171.78 Sqm 15.04 2583.59
masonary.
17 ODACT262 Filling in foundation and plinth with excavated 0.00 Cum -5.788 0.00
materials including watering and ramming.
18 ODACT91 #NAME? #NAME? Hour #NAME? #NAME?
19 ODACT140 #NAME? #NAME? Nos #NAME? #NAME?
20 ODACT085 #NAME? #NAME? Nos 1 #NAME?
21 ODACT073 Cost of Display Board 0.00 Nos 1 0.00
22 ODACT88 #NAME? #NAME? Nos 1 #NAME?
Provision for Child Care Taker for supply of Drinking
23 ODACT098 Water 0.00 Day 0 0.00
I 1st depth of 1.5 mt. [ 0 to 1.5 mt] Cum 0.786 3.300 1.500 12.839
@ Rs. 259.891 Per 1Cum = Rs. 3337.00
II 2nd depth of 1.5 mt. [ 1.5 to 3.0 mt] Cum 0.786 3.300 1.500 12.839
@ Rs. 343.687 Per 1Cum = Rs. 4413.00
III 3rd depth of 1.5 mt.[ 3.0 to 4.5 mt] Cum 0.786 3.300 1.300 11.127
@ Rs. 464.532 Per 1Cum = Rs. 5169.00
IV 4th depth of 1.5 mt. [ 4.5 to 6.0 mt] Cum 0.786 3.300 0.000 1.300
@ Rs. 585.376 Per 1Cum = Rs. 761.00
b) Depth : 6 to 9.00 mt in stoney earth
V 5th depth of 1.5 mt. [ 6.0 to 7.5 mt] Cum 0.786 3.300 0.000 0.000
@ Rs. 958.883 Per 1Cum = Rs. 0.00
VI 6th depth of 1.5 mt. [ 7.5 to 9.0 mt] Cum 0.786 3.300 0.000 0.000
@ Rs. 1121.838 Per 1Cum = Rs. 0.00
3 KB Bricks23X11X8cm By Truck 5 Km
1st 5 Km 404.32
next [up to 50 km] 0 Km @ 16.56 /Km 0.00
next [above 50 km] 0 Km 13.28 /Km -
404.32 per Cum
PREPARED BY CHECKED BY
ANALYSIS OF RATES
2 Earth work in stoney earth and gravels mixed with stone and boulder not
exceeding 0.014cum in volume within 50m. Initial lead and 1.5m initial lift
including rough dressing and breaking clods to maximum 5cm to 7cm and
laying in layer not exceeding 0.3m in depth.
3 Dry stone masonary or rough stone dry masonary for guard walls and retaining
walls with hard granite stones. Per 1 cum
Materials Component
Rough stone granite 1.00 cum 478.40 478.40
Total
Labours Component
Masson 2nd class 0.52 No. 247.20 128.54
Semiskilled 0.52 No. 227.20 118.14
M.Mulia 0.52 No. 176.00 91.52
W.Mulia 0.35 No. 176.00 61.60
878.21
Total = 878.21
For stone masonary in well stening add extra towards labour and scaffolding = 58.50
936.71
i) 1ST depth 1.50m to 3.00m
15 % of labour 878.21 15% 131.73 131.73
Total rate / cum 1068.44
HYSD bars including 5 percent overlaps and wastage 1.05 MT 45324.00 /qtl 47590.20
Binding wire 8.00 Kg 79.00 /kg 632.00
Labour for cutting ,bending, shifting to site, tying and placing in position:
PREPARED BY CHECKED BY
/cum
/cum
CALCULATION OF LABOUR & MATERIAL RATIO
Sl.
Description of Work Unit Quantity Rate Amount
No.
A LABOUR COMPONENT
1 Earth Work in excavation of foundation on open well excavation with lead up to 50 mt.
a Depth : 0 to 1.5 mt in hard soil
I 1st depth of 1.5 mt. [ 0 to 1.5 mt] Cum 12.839 149.26 1916.35
b Depth : 6 to 9.00 mt in stoney earth
II 2nd depth of 1.5 mt. [ 1.5 to 3.0 mt] Cum 12.839 321.65 4129.66
III 3rd depth of 1.5 mt.[ 3.0 to 4.5 mt] Cum 11.127 432.44 4811.76
IV 4th depth of 1.5 mt. [ 4.5 to 6.0 mt] Cum 1.300 543.22 706.19
V 5th depth of 1.5 mt. [ 6.0 to 7.5 mt] Cum 0.000 654.00 0.00
VI 6th depth of 1.5 mt. [ 7.5 to 9.0 mt] Cum 0.000 764.79 0.00
Dry stone masonary or rough stone dry masonary for well steining with
2
hard granite stones. Per 1 cum
(i) 1st depth 5'-0"(1.50m) Cum
(ii) 2nd depth 5'-0"(3.00m) Cum
(iii) 3rd depth 5'-0"(4.500m) Cum
(iv) 4th depth 5'-0"(6.00m) Cum
(v) 5th depth 5'-0"(7.50m) Cum
(vi) 6th depth 5'-0"(9.00m) Cum
6 Earth work in hard soil or gravelly soil Cum 5.643 149.26 842.27
7 Filling in foundation & plinth with sand watered and rammed. Cum 1.175 21.75 25.56
8 CC [1:4:8] with 4 cm.HG metal in foundation & Plinth work. Cum 1.175 686.40 806.52
Masonary Work With Fly Ash Bricks Having Crushing Strength Between
9 Cum 2.594 557.92 1447.24
75Kg / Sq. cm With Dimensional Tolerance +-8 percent in C.M. 1:6 in F& P
10 20 mm thick cement plaster [1:6] over stone masonary Sqm 15.040 42.24 635.29
12 Filling in foundation and plinth with excavated materials including watering and Cum -5.788 82.92 -479.94
13 ramming.
Conveyance by Head load for Cement Qntl 22.909 8.30 190.15
14 Conveyance by Head load for Sand Cum Err:509 33.00 Err:509
15 Conveyance by Head load for Metal Cum 1.128 33.00 37.22
16 Conveyance by Head load for Chips Cum 0.847 33.00 27.95
17 Conveyance by Head load for Stone Cum 0.000 33.00 0.00
18 Conveyance by Head load for M.S.Bar Qntl 0.532 8.30 4.42
19 #NAME? MD #NAME? #NAME? #NAME?
Total Labour Component Err:509
Total Mandays Err:509
B MATERIALS COMPONENT
1 Cement excluding Conveyance Charges Qntl 22.91 620.00 14203.82
2 Sand excluding Conveyance Charges Cum Err:509 53.00 Err:509
3 4 cm Metal excluding Conveyance Charges Cum 1.13 740.00 834.72
4 12 mm chips excluding Conveyance Charges Cum 0.85 1,098.00 929.90
5 H.G.Stone excluding Conveyance Charges Cum 0.00 3,700.00 0.00
6 M.S.Bar excluding conveyance charges Qntl 0.53 4,490.00 2390.25
7 Binding Wire Kg 0.41 79.00 32.04
8 Transportation Charges of sand Cum Err:509 340.40 Err:509
9 Transportation Charges of Chips, Stone & metal Cum 1.97 404.32 798.49
10 Transportation Charges of Cement & M.S.Bar Qntl 23.44 34.10 799.36
11 Semi-skilled Labour MD 48.78 220.00 10732.12
12 2nd Class Mason (Mason, carpenter, painter, blacksmith etc.) MD 6.56 240.00 1574.25
13 1st class mason (Special mason, carpenter, painter, blacksmith etc.) MD 0.91 260.00 236.05
14 Centering and Shuttering Sqm #NAME? #NAME? #NAME?
15 Dewatering charge Hours #NAME? #NAME? #NAME?
16 First aid box No. #NAME? #NAME? #NAME?
17 Photography No. #NAME? #NAME? #NAME?
18 Cost of Display Board No. 0 - 0.00
19 Gram Sanjojak/ Mate Wage MD 0 220.00 0.00
20 Rest Shed No. #NAME? 1,275.07 #NAME?
21 Work Facilities/ Creche/Drinking water / First aid No. 1 - 0.00
Total Materials Component Err:509
Total Estimated Cost [A+B] Err:509
Total 116001.00
LABOUR & MATERIAL STATEMENT
LABOUR COMPONENT MATERIAL COMPONENT
Unskilled High FLY ASH
SS Skilled Mortar Metal 40 Chips 20 Chips 10 Binding
Sl. Mulia Per Skilled Cement Filling Chips 12 Stone M.S.Bar Bricks25X
Items Qnty. Unit Mulia Mulia Sand mm mm mm Wire Remarks
No. day Mulia (Qntl) Sand mm (Cum) (Cum) (Qntl) 12X8cm
(Cum) (Cum) (Cum) (Cum) (Kg)
303.40 348.00 398.00 358.00 (Nos)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Earth Work in excavation of foundation on open
1 (a)
well excavation with lead up to 50 mt.
I 1st depth of 1.5 mt. [ 0 to 1.5 mt] 12.839 Cum 10.889
II 2nd depth of 1.5 mt. [ 1.5 to 3.0 mt] 12.839 Cum 14.400
III 3rd depth of 1.5 mt.[ 3.0 to 4.5 mt] 11.127 Cum 16.868
IV 4th depth of 1.5 mt. [ 4.5 to 6.0 mt] 1.300 Cum 2.483
Stoney Soil
V 5th depth of 1.5 mt. [ 6.0 to 7.5 mt] 0.000 Cum 0.000
VI 6th depth of 1.5 mt. [ 7.5 to 9.0 mt] 0.000 Cum 0.000
6 Earth work in hard soil or gravelly soil 5.64 Cum 3.974
Masonary Work With Fly Ash Bricks Having
Crushing Strength Between 75Kg / Sq. cm With
10
Dimensional Tolerance +-8 percent in C.M. 1:6 in
2.594 Cum 7.678 2.724 0.908 1.743 0.726 907.900
F& P
16 mm thick cement plaster [1:6] over Brick
11
masonary.
15.040 Sqm 3.610 2.406 0.647 0.271
I 1st depth of 1.5 mt. [ 0 to 1.5 mt] 12.839 cum 259.891 3337.00
II 2nd depth of 1.5 mt. [ 1.5 to 3.0 mt] 12.839 cum 343.687 4413.00
III 3rd depth of 1.5 mt.[ 3.0 to 4.5 mt] 11.127 cum 464.532 5169.00
IV 4th depth of 1.5 mt. [ 4.5 to 6.0 mt] 1.300 cum 585.376 761.00
V 5th depth of 1.5 mt. [ 6.0 to 7.5 mt] 0 cum 958.883 0.00
VI 6th depth of 1.5 mt. [ 7.5 to 9.0 mt] 0 cum 1121.838 0.00
3 Earth work in hard soil or gravelly soil within
50m.initial lead and 1.5m initial lift including rough 5.643 cum 215.791 1218.00
dressing and breaking clods to maximum 5 cm to 7
cm and laying in layers not exceeding 0.3m in depth.
4 Masonary Work With Fly Ash Bricks Having Crushing
Strength Between 75Kg / Sq. cm With Dimensional 2.594 cum 3851.068 9990.00
Tolerance +-8 percent in C.M. 1:6 in F& P
5 16 mm thick cement plaster [1:6] over Brick
15.04 Sqm 171.781 2584.00
masonary.
6 Filling in foundation & plinth with sand watered and
rammed. 1.175 cum 366.610 431.00
Deduction
Labour Cess1% 1161.00
G.Total deduction 1161.00
Net Payable 116075.00 - 1161.00 114914.00
(II) CERTIFICATE AND SIGNATURE