You are on page 1of 2

NATIONAL POWER CORPORATION

Small Power Utilities Group

WEEKLY PROGRESS REPORT ON THE RESTORATION OF


NON-OPERATIONAL AND DEACTIVATED GENSETS
Period Covered: 06 Jan 2022, 1700H to 13 Jan 2022, 1700H

Division : PALAWAN OPERATIONS DIVISION


Plant Name : MANGSEE DPP
Plant-in-Charge : RON CEDRIC B. GARCIA

BOGGED DOWN UNIT/S UNIT NO. BRAND RATED CAP


Non-Operational Genset 2 AKSA 100 kW

DETAILS OF BREAKDOWN AND ACCOMPLISHMENTS AS OF TO DATE

NON - OPERATIONAL GENSET/S (1 & 2 of 2)


Unit No. Brand,
Unit No. 2, 100 kW Cummins (2850 RH)
Capacity:

Date Started: November 28, 2021

Reason: Genset High Voltage

Action Plans: Outsource spare parts and troubleshoot the problem.

Original Target Date of


December 31, 2021
Restoration:

The original and damaged AVR (STAMFORD AS440) was


Activities / Actions
replaced by the ordered same part no. (AS440) AVR in
Taken (for the period):
online shop.

Actual Status /
100%, problem rectified. Restored on January 13, 2022.
Accomplishment:
Problems Encountered,
None
if any:

Remarks: The unit no. 2 is operational

Prepared by: Reviewed by:

1|Page
RON CEDRIC B. GARCIA ALFREDO R. ZABALA
Engineer II, Mangsee DPP PEC, POD

Approved by:

ROMEO S. ANDRIANO EDWIN T. TATEL


OIC, POD Acting Manager, LOD