Professional Documents
Culture Documents
eni.com
WORKSHOP OUTLINE
2
Eni Worlwide Lifting Operation Model
Operative Personnel:
Responsible for conducting lifting
operations safely, efficiently and in strict
compliance with the company
requirements
3
Lifting Procedure Development Process
Eni Indonesia
Lifting Management Operation
Procedure
4
The Aspects of Lifting Management System
5
Lifting Functional Organization Scheme
The functional organization scheme presented in this chapter aims at identify the reference
roles that need to be covered either by internal or external (Contractors) personnel to
control and coordinate lifting activities.
The Lifting
Operation Team
shall be clearly
stated in every
Area /
Department.
6
Roles & Responsibility
7
Roles & Responsibility
8
Roles & Responsibility
Site Manager:
He has the overall responsibility for the site and for applying the HSE
integrated management system including the execution of safe lifting and
hoisting operations.
For the project site the site manager is a construction leader, for the drilling site
the site manager is company man, for the logistic shore base the site manager
is a logistic superintendent and for ORF site the site manager is operation
superintenndent and for FPU the site manager is OIM.
9
Roles & Responsibility
Lifting Engineer:
Lifting Engineer shall be activated by PIC inside LTA in case of lifting
requiring engineering studies.
Lifting Engineer shall be involved in the preparation stage of all lifting
operations which deserve an engineering activity.
10
Personnel Competence & Qualification
Person In Chrage (PIC) LOLER Appointed Person for Lifting or In-house course that are equivalent.
LOLER & PUWER Awareness Course or In-house course that are equivalent as per
approval by LTA.
In-situ Planning & Risk Assessment
Offshore Crane LOLER& PUWER Awarness Course or In-house course that are equivalent as per
Operator approval by LTA.
In-situ Planning & Risk Assessment.
Offshore crane operator stage 3
Banksman LOLER & PUWER Awarness Course or In-house course that are equivalent as per
approval by LTA.
In-situ Planning & Risk Assessment.
OPITO Stage 3 Banksman/slinger or MIGAS certificate.
11
Personnel Competence & Qualification
Slinger / Rigger LOLER & PUWER Awarness Course or In-house course that are equivalent as per
approval by LTA.
In-situ Planning & Risk Assessment.
OPITO Stage 3 Rigger or MIGAS certificate.
Forklift Operator LOLER & PUWER Awarness Course or In-house course that are equivalent as per
approval by LTA.
In-situ Planning & Risk Assessment.
OSHA or MIGAS or Equivalent Forklift Operator.
Onshore Mobile Crane LOLER & PUWER Awarness Course or In-house course that are equivalent as per
Operator approval by LTA.
In-situ Planning & Risk Assessment.
Migas Crane Operator
Gantry Crane or OHC LOLER & PUWER Awarness Course or In-house course that are equivalent as per
Operator approval by LTA.
In-situ Planning & Risk Assessment.
Migas Crane Operator
Powered Lifting LOLER & PUWER Awarness Course or In-house course that are equivalent as per
Equipment Operator approval by LTA.
In-situ Planning & Risk Assessment.
(Winches, MEWP etc).
Equipment familiarisation / induction / assessment from manufacturer
12
Operational Flowchart & Task Ownership
13
Lifting Categorization
14
Lifting Categorization Management Flowchart
15
Lifting Categorization Requirement
16
Lifting Equipment
No lifting equipment shall be used without the safe working load being
clearly marked.
No lifting equipment should be used without valid report of thorough
examination
All safety devices fitted to lifting equipment shall be fully operational.
A colour code system shall be used
If the safe working load is dependent upon the configuration of the lifting
equipment, then the safe working load for each configuration shall be either
marked on the equipment for each configuration or information kept with
the equipment where it is readily available to the operator ((e.g.) load radius
charts in the crane cab)
The hoisting mechanism of a crane shall not be used for any other purpose
other than raising or lowering a load vertically.
17
Lifting Equipment
18
Portable Lifting Equipment
Movable lifting appliances and accessories for general use on site. ((e.g.), includes
shackles, slings, chain hoists, lever hoists).
Be Stored and issued from a rigging loft.
Shall be inspected, maintained and recertified six (6) monthly.
Shall be miantained in accordance with manufacturer’s recommendations / instructions.
Shall be marked with a unique identification number and the SWL or WLL.
Shall be visually examined prior to use.
The valid colour codes shall be clearly displayed at all sites in prominent locations.
Soft slings shall be colour coded by a method which does not cause damage or introduce
sharp edges
19
Fixed Lifting Equipment
Permanently installed at the site, ((e.g.), overhead cranes, pedestal cranes, runway /
monorail beams, hoists, trolley beams, suspension pad eyes, certified steel work, davits,
man riding winches, utility winches).
Inspected, maintained and recertified every 12 months.
For personnel lifting shall be examined every six months.
Have a unique visible identification number
The safe working load(s) shall be clearly visible to the user
Fixed lifting equipment approved for personnel transfer shall be marked as “Suitable for
Personnel Transfer.”
Fixed lifting equipment used for man riding shall be marked as “Suitable for Man
Riding.”
Any pedestal cranes or winches (eg. located on the drill floor) that could be used in error
for lifting personnel shall be marked “not for lifting personnel”.
All overhead gantry cranes should have their full travel path, marked on the floor using
painted lines and this area shall be kept clear of obstructions at all times.
20
Transit Equipment & Sling
21
CCU & ISO Container
CCUs are defined as portable units with a dedicated sling set for repeated use in the
transportation of goods or equivalent, handled in open seas. Examples of certified
CCU’s are containers, lifting baskets, mud boxes, tanks and waste skips.
CCUs shall be designed to an applicable standard found acceptable to the Eni
Indonesia Lifting Authority ((e.g.) BS EN 12079, DNV 2.7-1 for:
1. manufacture
2. inspection
3. testing
4. thorough examination and recertification
ISO / Conex style containers are not designed to be lifted with multi-leg sling sets and
shackles. They are not designed to accommodate the dynamic factors that are present
during the transportation of goods to and from offshore sites and therefore shall not be
used as CCU.
22
CCU & ISO Container
23
Mobile Lifting Equipment
24
Defective Equipment
Prior to issue from a rigging loft, portable lifting equipment shall be visually inspected by
the Rigging loft controller, any item found to be unfit for service will be removed from
service and quarantined immediately.
During normal operations, portable lifting equipment found to be unfit for service shall
be removed from service and quarantined immediately.
Unfit for service equipment shall be stored in a secure quarantine area until the defected
equipment has been:
1. recertified by a competent person
2. removed from the site
Unfit for service equipment shall be reported to and recorded by the Person – In –
Charge.
A report on unfit for service equipment that presents an existing or imminent risk of
serious personal injury shall be sent to the LTA.
25
Rigging Loaf Management
26
Rigging Loaf Management
27
Lifting Operation Plan
28
Lifting Operation Plan
29
Lifting Operation Plan
30
Lifting Operation Plan
31
TRA & Tool Box Talk
32
Lifting Over or in Close Proximity to Live Plant
33
Lifting Over or in Close Proximity to Live Plant
34
Uncertified Steel Works & Lifting Point
35
Ground Condition
36
Hand Safe Lifting & Tag Lines
37
Handling of Tubular Goods
38
Lifting Personnel
39
Lifting Personnel
40
Lifting Personnel
41
Monitor, Learn & Take Corrective Action
Each Site PIC shall monitor compliance with this Procedure, local
legislation, through a systematic assessment program.
All lifting related internal and external incident / accident reports and safety
alerts, supplied to Lifting Technical Advisor shall be forwarded to ENI HQ
Lifting Specialist for central review and distributed with the appropriate
action
Everyone involved in the execution of lifting operation shall have the
opportunity to discuss and record applicable improvements on the lift plan.
Any learning points recorded on the lift plan shall be reviewed by the PIC
and where appropriate, actions taken and communicated to all relevant
personnel and the lift plan revised.
42
Internal Lifting Assessment
43
Lifting Contract Qualification Requirements
Any Lifting Services Provider before being invited to tender, for the delivery
of lifting services on behalf of the Company, shall be qualified for the type of
operations required, in accordance with LOGIS-DG-2636-0-2016 “Lifting
Operative Tool”.
The qualification stage includes, but is not limited to, assessment of the
Provider organizational structure, lifting operations and maintenance
organization, safety performance, appliances and accessories condition and
certifications, lifting crew and engineering training and standards etc.
During the qualification process, the documentation and information to be
submitted are contained in the Appendix 10
44
THANKS
45