REPORTS
SUBMITTED BY –
MANSI MOKASHI
5TH YEAR B ARCH SEC –B
ROLL NO- 170066
S B PATIL COLLEGE OF
ARCHITECTURE AND DESIGN
SITE VISIT-1
DATE : 05.08.2021
WORK PROGRESS :
• SAMPLE FLAT CONSTRUCTION PART WAS COMPLETED .
• WORKING WAS ON INTERNAL FITTINGS & TILING .
SITE CONDITION :
• MOSTLY IN GOOD CONFITION .
• THERE WAS SOME ISSUES AND MESSINESS .
OBSERVATIONS :
THERE WAS ISSUE REGARDING THE TOILET LAYOUT AND
SANITARY FITTINGS AND ELECTRIAL FITTINGS WHICH WE SOLVED
SITE VISIT-2
WORK PROGRESS :
CONSTRUCTION PROCESS OF 2ND SLAB WAS GOING ON.
SITE CONDITION :
• MOSTLY IN GOOD CONDITION .
• THERE WAS SOME ISSUES REGARDING PODIUM FLOOR.
SITE VISIT - 3
WORK PROGRESS :
CONSTRUCTION PROCESS OF 3RD SLAB WAS GOING ON.
SITE CONDITION :
• MOSTLY IN GOOD CONDITION .
SITE VISIT - 4
WORK PROGRESS :
COLUMNS WERE MARKED.
SITE CONDITION :
• MOSTLY IN GOOD CONDITION .