Professional Documents
Culture Documents
Grime - @00230419
2 Comparitor
Scheme 1; DB-001 Scheme 2; KP-001 Scheme 3; CG-001
3 (Weight)
End bearing CFA piles, at columns Standard sections used for steel frame. The overhanging roof structure and glazed
4
positions only; material and instalation Large excavation for mass concrete piles panels are a preimum product which may
5 relatively inexpensize. Steel frame for builidng perimeter. Large mass of overlook any saving in the comparatively
structure repetitive; reduced design and concrete used. Fabrication of large shallow simple structural frame.
6
fabrication cost. Truss roof, high WPG to cover large 24m span with thick
Cost
30%
7 fabrication cost, crane installation, poss components would cost time and money.
8 temporary support req'd; increased cost.
Offset columns; maintain clear space. for the operations floor and studio. The requirements. Allowances have been
12 Floor depth, wall thickness, roof insulation structure is 5m from dock wall. Slim floor made for soundproofing within the depth of
provision made for min. sound deck between studio and operation floor the trusses, and a separate lobby further
13
transmission. Secondary steel provided for would require additional sound proofing as supports the disconnect for sound
20%
14 services/light rigging within roof structure. deck is only 150mm thick. transmission to the offices
15
16 Mark Weighted Mark Mark Weighted Mark Mark Weighted Mark
17 10 / 10 2 8 / 10 1.6 8 / 10 1.6
Vertical tubular K-bracing in two directions, Two stability systems. Overall stability Concrete foundations and walls have been
18
horizontal tubular bracing in roof. 1st floor obtained via vertical bracing system. E-W chosen to deal with the large compressive
19 slab diaphragm action. Vertical brace has hybrid of rolled steel (N) and cable forces. Above the first floor, steel has been
positions reduce possible window system (S) due to glass clad. Portalisation chosen to provide a lightweight solution for
Stability
20
obstructions. CFA embedment to provide for WPG spanning over the studio. the nominal forces
15%
26 dewatering of high W.T. Slab & Ring Beam construct in braced bay/module first. Use building for the erection of the trusses.
above W.T lvl. Steelwork off site of WPG could be problematic due to long Large scale dewatering is required for
27
fabrication, long lead/fab time, quick onsite length and heavy section. Large crane installation of the foundations
15%
28 erection. VB allows modular erection. required to lift heavy WPG at long lever
29 Truss poss. req large crane. arm.
corrosion resistance treatment (Galv). spans across the interruptable studio floor. chosen to deal with the large compressive
33 CFA's and slab rebar cover to rebar to be Heavy galv required due to high corrosion forces. Above the first floor, steel has been
increased. Steel superstruture enabes classification with the structure being next chosen to provide a lightweight solution for
34
long open spans for studio. 1st floor conc to a dock. Glass, brick and clad panel for the nominal forces.
15%
Possible material delivery/removal via materials,extent of recycled use is structural materials can be reusued or
41
docks. Recycled aggregrates within slabs. uncertain. Bespoke WPG would require recycled.
5%
48
49 Therefore, adopt scheme DB-001 for the next stage of the design process.
50 Excellent. Have all five marks