Drying machine-1 Haroon Print (Rotary joints status report)

Date of checking status 2/2/2022

Installation Component
Location Installation date Current status Detail
detail
Rotary joint leaked-New joint is 27/09/2021 old rotary joint is
1 intalled-Left rack 2nd column 2nd repaired-new carbon is
from top installed

Rotary joint leaked-Carbon seal Same rotary joint is


2 undergo wear and tear-Left rack 28/09/2021 repaired -new Carbon seal
2nd column 3rd from top is installed

Repaired rotary joint is installed old rotary joint is


3 on Drying machine-1-1st stack repaired-new carbon is
2nd column 2nd from top 10/11/2021 installed
Drying machine-2 Lahore Print (Rotary joints status report)

Date of checking status 2/2/2022

Installation Component Current


Location Installation date Detail
detail status

rotary joint leaked-Carbon seal undergo wear 29/09/2021 repaired joint is installed
and tear and spring broke- 1st stack 1st
1 column 2nd from top

Two joints leak- one on the 2nd rack 2nd 2/10/2021 One new joint and other old
2 column top one and the 2nd from the top joint is repaired and installed

Two rotary joints are leak on drying-2- one


two old repaired joints are
on2nd rack 1st column and top most and 13/10/2021 Installed
other one from left rack 2nd column top most
3

One rotary joint- 2nd rack 1st column 4th


14/10/2022 new gasket is placed in
from top is leak- gasket is damaged
4 rotary joint and installed
Repired rotary joint (of D1) is installed on
drying machine-2- 1st stack 1st column 3rd
5 from top 22/11/2021 old rotary joint is repaired
Repaired joint is installed on D2- 1st stack 1st 25/11/2021
6 column 3rd one from top-
On Drying machine-2 rotary joint installed on 16/12/2021 repaired joint is installed-
7 1st stack 1st column 3rd one from top only carbon seal changed
Drying machine-1 Haroon Print (Rotary joints status report)
Date of checking status 2/2/2022

Location Installation date Installation Current status Detail


Component detail
Rotary joint of 1st stack 2nd 20/09/2021 repaired rotary
column top most is leaked joint is installed

1
23/11/2021 repaired rotary
joint is installed
Repaired rotary joint is installed
- 2nd stack 1st column bottom
one- 2 new flexible pipes are
2 also installed
27/1/2022 repaired rotary
joint is installed
Soaper-1 2 rotary joints installed
on drying machine- 1st stack
2nd column 3rd from
top(counter threads) and 4th
3 one from top
4
Drying machine-1 Haroon Print (Rotary joints status report)
Date of checking status 2/2/2022

Location Installation date Installation Current status Detail


Component
detail

3
4