Professional Documents
Culture Documents
Pac-Sdl: Types of Discounting
Pac-Sdl: Types of Discounting
of Discounting:
There are different types of discounting with reference to cash flows;
1. Discounting a single sum.
2. Discounting annuity (for constant annual cash flows for a number of years)
3. Discounting Perpetuity
Annuity Discounting – Normal
PV = Annual Cash flow x 1 – (1+i)^-n
i
L
Project A Project B Discounting PV of PV of Project
Year ,000 ,000 @ 10% Project A B
1 25 7 0.909 23 6
D
2 25 7 0.826 21 6
a 25 7 0.751 19 5
4 25 7 0.683 17 5
-S
5 25 7 0.621 16 4
3.791 95 27
PV of Project A 25 x 3.791 95
PV of Project B 7 x 3.791 27
C
Annuity is series of cash flows having Perpetuity is series of cash flows having
following 3 characteristics following 3 characteristics
• Equal cash flows • Equal cash flows
PA
L
PV = Annual Cash flows x annuity factor
D
PV = 1,000 X 3.791 3,791
Advanced Annuity
-S
0 1 2 3 4 5
1,000 1,000
1,000 1,000 1,000
C
1,000
PV = 4,170
Delayed Annuity
0 1 2 3 4 5 6 7
1,000 1,000 1,000 1,000 1,000
L
discounting formula.
Calulate Present Value of perpetuity of Rs1,000/- pa starting;
a) 1 year from now
D
b) Immediately
c) in 3 Years from now
cost of capital is 10% pa
-S
Normal Perpetuity
0 1 2 3 4
1,000 1,000 1,000 1,000 onward
PV = 1,000 / 0.10 10,000
C
Advanced Perpetuity
0 1 2 3 4
onward
PA
1,000 / 0.10
10,000
1,000
PV = 11,000
Delayed Perpetuity
0 1 2 3 4
onward
1,000 1,000
L
Now the question is what is the rate at which our NPV will become 0?
• IRR is the rate at which NPV of the project’s cash flows will become 0.
D
• It can be calculated by hit and trial method
• By testing different rates and
• Identifying a rate where NPV = 0.
-S
But in exam we don’t have time so we can calculate it with following steps.
1. Estimate cash flows of the project (initial investment and future benefits)
2. Select any two discount rates
3. Calculate two NPVs with these two rates.
C
4. Use following interpolation formula to estimate IRR
IRR = L + [ ___NL x (H –L)]
PA
NL-NH
L = lower discount rate
H = higher discount rate
NL = NPV with lower rate
NH = NPV with higher rate
Conclusion: if IRR > Co. Rate of Return = Accept the Project
if IRR < Co. Rate of Return = Reject the Project
Year (a) Discounting @ 15% Present Value Discounting @ 20% Present Value
0 (90) 1.000 (90) 1.000 (90)
1 40 0.870 35 0.833 33
2 30 0.756 23 0.694 21
3 20 0.658 13 0.579 12
4 20 0.572 11 0.482 10
5 24 0.497 12 0.402 10
4 (5)
Using interpolation formula
15% + 4 x 5.00%
9
15% + 2% = 17.23%
Year (a) 17% PV
0 (90) 1.000 (90)
1 40 0.853 34
2 30 0.728 22
3 20 0.621 12
4 20 0.530 11
L
5 24 0.452 11
(0)
D
Advantages:
1. Consider time value of money
2. Based on cash flows
-S
3. Consider whole life of the project
4. Percentage terms; easy to understand
5. Cost of capital is not required to be known for its calculation
C
Disadvantages:
1. Not absolute measure
2. Interpolation just provides estimates
3. Complicated to calculate
PA