Log of Sh

Date: 2022-01-29

U1 Running
Unit Status
U2 Running

EQP FDF PAF IDF CEP

U1 AB AB AB A

U2 AB AB AB A

Unit 1:

20:00 Measure the motor insulation of unit-1 10KV secti

Unit 2:

Event record
23:00 Measure the motor insulation of unit-2 10KV secti

Common:
Log of Shift Leader(middle shift)
Shift: middle shift Shift leader:

Outgoing Lahore Running


Line Sahiwal Running

APH CWP OCCWP CCCWP VAC P LUB P

AB B A B AC B

AB A B B AB A

tion of unit-1 10KV section B CW pump B ,it is qualified.

tion of unit-2 10KV section B CW pump B ,it is qualified.


Shift leader: Chen Han

U1 Running
FGD
U2 Running

SEL P EHP BFPT GSC P Mill

B B AB A ABCDE

A B AB A ABCDE
Keep load at 1243.517MW
20:10 Terminated and reserviced work ticket "Check the
Maintenance personnel replied that spring dislocati
which has been recovered now/Start the #5A belt c

1. No.1 steam turbine #3, #6 and #7 bearing have vibr


Main defect
2. No.2 steam turbine #1 bearing have vibration high alar

Existing Work
ticket
d work ticket "Check the power breaker and control circuit of #5A belt conveyor m
eplied that spring dislocation of the internal mechanical device of the power breaker
d now/Start the #5A belt conveyor it running normally

and #7 bearing have vibration high alarm.


g have vibration high alarm at low load.
A belt conveyor motor".
the power breaker occurred