Professional Documents
Culture Documents
hbreavis
On
08/06/2021
Maintenance Audits
BG 24/2012
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
ACKNOWLEDGEMENTS
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system,
or transmitted in any form or by any means electronic or mechanical including photocopying,
recording or otherwise without prior written permission of the publisher.
© BSRIA BG 24/2012
PREFACE
The issue of effective audits was raised by John Armstrong the author of
AG 13/2000 Toolkit for Building Operation Audits in a recent CIBSE
maintenance task group meeting. We are very pleased to be able to
update this guide and make the toolkit available to the industry.
original checksheet into a useful toolkit. We have been using the toolkit
in earnest for two years, as has Ashley. It has been developed over the last
5 years on PFI projects within Interserve and trialled in the banking, arts
and printing sectors.
Between us we have now produced this guidance and toolkit that is easy
to use, streamlines the audit process and allows you to track progress and
capture the results effortlessly.
Jo Harris
July 2012
© BSRIA BG 24/2012
CONTENTS
© BSRIA BG 24/2012
CONTENTS
FIGURES
Figure 1 : Continuous Improvement 2
Figure 2 : Two levels of Audit 4
TABLES
Table 1 : Optional audit front sheet 20
Table 2 : Property Information 21
Table 3 : Housekeeping checklist 46
Table 4 : Plant condition checklist 46
REFERENCES 51
© BSRIA BG 24/2012
INTRODUCTION 1
corrections. An audit does not have room for apportioning blame for
problems.
The audit process and its outcome is broken down to the following key
stages:
process review
correcting problems
preventing problems
dynamic improvements.
The audit process provided in this guide will support the implementation
[1].
of good practice asset management as outlined in PAS 55-1 To assist
this we have annotated the elements in section 8 of this guide,
[2]
highlighting the relevant section in relation to clause 4 of PAS 55-2 .
The main purposes of the audit are to highlight deviations from plans or
expectations, to evaluate the need for improvement and to take
corrective action.
occupant expectations.
Audit
purpose
What do
Re-assess
we know?
Opportunities Is this
for improvement happening?
Notes and
actions
1.2 PURPOSE OF Operation and maintenance audits are carried out for a number of
AUDITS reasons including:
© BSRIA BG 24/2012
INTRODUCTION 1
1.3 BUSINESS The costs to undertake an audit can be prohibitive if the organisation’s
SUCCESS CRITERIA core priorities are not taken into consideration. The audit will need to
reflect the organisation’s priorities otherwise it will not give the value
intended.
This guide identifies areas that reflect how well a building is being
operated and maintained and how well it is supporting the organisation.
These areas are known as business success criteria. Each business success
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
Throughout this guide the term “client” is used to denote the person,
persons or organisation to whom operation and maintenance
management services are provided. The client could be internal or
external.
2 AUDITS
2.1 LEVEL OF AUDITS An audit can be conducted at two levels - strategic or operational as
illustrated in Figure 2.
STRATEGIC AUDITS
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
OUTPUTS INPUTS
Planned
Arrangements
Productivity Resources
Operation
Customer and Knowledge
Satisfaction Quality Maintenance
Process Supervision
Time
planning and
Control
OPERATIONAL AUDITS
Strategic audits
Strategic requirements for operation and maintenance match
organisational objectives and are determined at management level. The
strategic audit examines the status and effectiveness of the organisation’s
operation and maintenance system. It determines whether the overall
maintenance strategy, maintenance priorities and resourcing are suitable
to achieve the objectives of the organisation. The strategic audit also
enables management to continually review and re-focus maintenance
strategies and action plans to meet those objectives.
For example; the organisation may require some building services plant
to operate at a higher level of operational availability. Changing the
requirements and setting different targets are strategic decisions. The
method of achieving these targets and the deployment of resources,
within the budget, are operational level decisions.
© BSRIA BG 24/2012
AUDITS 2
Operational audits
Watchpoint Operational audits test compliance with the on-going day-to-day
Some organisations use activities based on the operation and maintenance requirements and
operational audits to
ensure that the right
whether these arrangements yield the anticipated results. This requires a
activities are being clear statement of the maintenance activities and a method of measuring
undertaken in compliance the outputs.
with the three Es:
Outputs are sometimes expressed as benchmarks, Key Performance
Effectiveness:
Indicators (KPIs) or Service Level Agreements (SLAs). They may be
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
Organisations are likely to carry out a second party asset management and
maintenance audit on a number of occasions during the building’s life
cycle:
when a new appointee is added to a list of approved suppliers
when it is necessary to ensure that an existing supplier conforms to
stated requirements
When an asset portfolio is handed back to a client, to assist in the
assessment of dilapidation.
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
2.3 THE AUDIT PLAN It is often difficult to carry out formal audits on all activities of the
operation and maintenance organisation as some aspects may have to be
audited more rigorously than others. This may add to the overall cost of
the audit if not planned early in the audit process.
© BSRIA BG 24/2012
AUDITS 2
For example, public organisations place a high emphasis on auditing
value issues whereas a contracting organisation will place more
importance on customer satisfaction. It also follows that some plant and
processes are more critical to the business success than others and should
be given a higher priority in the audit plan.
2.4 THE AUDIT The audit process begins with a definition of the need and an agreement
PROCESS of business success criteria that should be included.
2.5 THE ROLE OF THE The role of the auditor can vary from assessments of their own work to
AUDITOR auditing other people, functions and organisations. There is no absolute
requirement for auditors to have formal qualifications or experience.
However, consideration should be given to the purpose of the audit, the
function being audited, and the level at which the audit is being carried
out when making decisions about the knowledge, skill and experience
required.
Inputs Outputs
At Interserve, we’re re-imagining Interserve approaches every part of Interserve is proud to have supported
support services and facilities property and estates management BSRIA in developing the toolkit for
management, to redefine what it can with intelligence. We put your business asset management and maintenance
do for you. needs at the heart of everything we do. audits. This tool will help you improve
That way, we develop tailored solutions and enhance your organisation’s
Every organisation needs a partner
that mitigate risk, respond to your
that has the expertise to enhance its performance. That’s intelligence.
challenges and protect your brand.
business performance and its brand. A
partner that focuses on service, cost
and efficiency.
www.interserve.com/support
Did you know that the major causes of Public health risk control and increasing
management system failures are poor quality regulatory vigilance mean that water
information and inadequate data analysis? quality management needs to receive rigorous
That’s why we combine scientific expertise audit attention. So we go beyond a simple
and engineering experience to provide a fully Quality Assurance or Health and Safety audit.
independent Third Party auditing service. As scientists, our knowledge and know-how
goes deeper than in-house training to ensure
With over 20 years’ experience in compliance with maintenance and monitoring
managing water quality in the building objectives for water quality management.
services environment, we understand Without this understanding, corrosion of
that the inspection regime for a hospital the system or dangerous outbreaks of
differs from that of an office building. microbiological problems such as legionella
and/or pseudomonas could occur. Legal :
As with any audit the
Our strategic and operational findings are based on the
audits are tailored specifically How do we audit each information available and
www.marquisandlord.com
The time needed by all on-site staff to support an audit should neither be
underestimated nor considered as non-productive time. Taking an active
part in the audit should be seen by management as an important part of
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
3.2 TERMS OF The organisation’s management should define the objectives, procedures
REFERENCE and standards by which the work of the operation and maintenance
function is to be carried out. In addition there need to be benchmarks
and performance targets to measure the output. These become the terms
of reference for the audit.
Some organisations may not have their own procedures or standards for
carrying out the operation and maintenance function. In this case the
audit process should provide an external window to compare
performance against industry-accepted standards and targets drawn from
contemporary samples taken from peer groups. Guidance is provided in
part 2 of this guide.
3.3 OVERLAP OF A task for those commissioning the audit is to avoid repetition and co-
AUDIT ACTIVITIES ordinate audit activities that can overlap.
© BSRIA BG 24/2012
MANAGEMENT APPROACH TO AUDITING 3
method of financing
procurement criteria
maintenance organisation and resourcing
technical standards and competence
planned maintenance policy.
Details of all planned tasks and targets for their accomplishment may not
necessarily be written down. An early task of the auditor is to establish
these through discussion with management personnel.
4.2 PERFORMANCE Published performance indicators provide industry standards and targets
INDICATORS for comparison that can be used to demonstrate how an audited site
performs in relation to a peer group or good practice.
Watchpoint
Through the use of the Cost based measures can be obtained relatively easily and provide a useful
toolkit provided in Part 2 reference tool. Performance indicators can include unit costs (for
of this guide it is possible example costs per square metre - £/m²) for each of the following:
to benchmark the results
against the present planned maintenance
industry best practice. If
you submit your results reactive maintenance
to BSRIA, over time we maintenance labour
will build up a database of
results that will spares and materials.
benchmark similar
properties or sectors to
In addition, other indicators include:
enable peer group
comparisons. comparison of actual expenditure against budget
condition of the assets
building occupant satisfaction
health and safety incident statistics
number of breakdowns on critical plant
comparison of planned and breakdown costs.
© BSRIA BG 24/2012
THE AUDIT FUNCTION 4
4.3 GATHERING It is important for the auditor to develop a clear picture of the on-site
INFORMATION operation and maintenance regime and to compare it with planned tasks
and expectations. The success of the audit depends on the quality of the
information collected and the ability of this information to withstand
comparison with performance standards.
The operation and maintenance audit may draw information from many
sources. These include:
management system documentation, for example procedures,
instructions, rules and policies
contract documentation, for example drawings, specifications,
work instructions, tenders and contracts
finance and accounts documents, for example budgets, allocation
of funds, expenditure records, invoice payments and timesheets
personnel and training records, for example competency,
assessments, appraisals, training requirements and training history
operation and maintenance records, for example plant log
books, computer based maintenance records, complaint logs, BMS
logs and condition monitoring records
other maintenance records, for example asset registers, asset
management systems, health and safety file and feedback records
This list is not definitive. Where priorities are agreed other stages may be
added and some removed.
© BSRIA BG 24/2012
THE AUDIT FUNCTION 4
diagnostic questionnaires
site inspections
The analysis should look for problems underlying the failure to meet the
organisation’s procedures. Particular attention should be given to those
that may cause a domino effect. A number of smaller problems may give
rise to a much larger problem in another area. Such problems may
require further audits or opening up another audit trail.
5 THE AUDITOR
5.1 GENERAL The auditor’s job is to provide independent assurance that an
organisation’s operation and maintenance management and control are
operating effectively and assessing whether the expected results have
been achieved or not.
[4]
5.2 AUDITOR BS EN ISO 19011-2 is the international standard for the qualification
TRAINING AND of quality auditors. There are also schemes for the registration of
EXPERIENCE
auditors, for example, the International Register of Certificated Auditors
(IRCA) and European Organisation for Quality (EOQ) which has a scheme
across Europe to strengthen training and qualification of auditors.
© BSRIA BG 24/2012
THE AUDITOR 5
maintenance process
experience in a similar sector (in terms of size, complexity and type
of business)
management experience.
5.3 SELECTION OF AN As there are no schemes to formally recognise auditors who perform
AUDITOR asset management and maintenance audits, those who are
commissioning such work need to evaluate the competency, knowledge
and experience of persons carrying out this work. Sections 5.1 and 5.2
provide a basis for such assessment.
6 REPORTING
6.1 FORMAT AND There is no specific format for reporting the results of an audit.
CONTENTS
The basic requirements are:
a comprehensive introductory section or preamble
a summary of non-conformities and recommendations
an audit summary, including photographic evidence
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
a completed toolkit.
Note that the auditor may not be an expert in the particular area of non-
conformity and the recommendation may be to obtain specialist advice.
© BSRIA BG 24/2012
REPORTING 6
6.4 THE AUDIT The audit summary should make recommendations for improvement that
SUMMARY are separate from the non-conformity, for example introduction of
condition monitoring, improvement of communications with the
organisation, capital expenditure planning and management of additional
works and contractors.
The audit summary report should cover at least the following areas:
information and observations highlighting the salient information
received and other observations made during the audit process, the
sources of the information and their limitations (for example sample
size)
details of any tests, measurements and, where necessary conditions
under which they were carried out. Information may be organised
on the basis of functions, departments or jobs audited or in any
format the client requires.
attribution of non-conformities or recommendations to a particular
requirement of the contract, statutory requirement, procedure,
standard or performance target. Although non-conformity is
normally attributed to the organisation’s procedures and
requirements, where possible the auditor should use external
benchmarks for comparison.
6.5 COMPLETED The toolkit described in Part 2 of this guide should be completed and
TOOLKIT made available as a record of the audit. It can be converted to a locked
pdf or similar format to prevent unauthorised changes. This will provide
the detail for each section of the report to refer back to if needed.
Importantly management action can be tracked against the completed
toolkit.
ASSET MANAGEMENT
Property being audited:
Postcode:
Property operator: (if not shown above)
Postcode:
Maintenance contractor:
Contact
Company:
name:
Address: Postcode:
COPIES OF AUDIT TO BE ISSUED TO:
CLIENT
PROPERTY OPERATOR
MAINTENANCE CONTRACTOR
OTHER
© BSRIA BG 24/2012
REPORTING 6
Table 2 : Property Information
PROPERTY INFORMATION
What is the function of the property being audited?
Manufacturing /
Offices Health
Process industry
Media /
Financial Hotel
Communications
Planned maintenance
Measured
only
Inclusive of specialist
Other
services
w w w. a j b h i g h t e ch.com
Certifications
since 1983
&
Memberships
ajb
145 Employees
ajb
Presence in 11 Countries
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
ajb
Projects in 4 Continents, 38 Countries
Building Services
● Building Services
ajb
Commissioning Management
ajb
LEED Commissioning (CxA)
ajb
Building Services Commissioning
NEBB Certified
ajb
Testing & Balancing (TAB)
NEBB Certified
ajb
BMS / Automation Wall to Wall Services
ajb
O&M and Training Manuals
Including E-Manuals
ajb
Services for the Facility Management
Regional Presence:
Greece, Lebanon, Jordan, Qatar, Saudi Arabia, Iraq, Syria, Libya, United Arab Emirates, Palestine, Armenia
Services for
Facility Management
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
ajb
Retro Commissioning
ajb
Infrared Thermal Imaging
ajb
BMS & Controls Service Contracts
ajb
Indoor Air Quality (IAQ) Test
ajb
Building Envelope Test
ajb
Room Integrity Test (RIT)
ajb
Rebalancing of HVAC Systems
ajb
Smoke Evacuation Test
ajb
Smoke Drain Test
ajb
Upgrade O&M Documentation
ajb
O&M Training of your Staff
ajb
Yearly Tests for Hospitals / Pharmaceuticals:
- HEPA Filter DOP Test
- Clean Room Test
- Biological Safety Cabinets
- Laminar Flow Cabinets
completed toolkit can be sent by the auditor to the client, who will be
able to use the electronic information as appropriate.
Guide
This provides instructions to users of the toolkit
Schedule
This worksheet is used to record information such as the building address
and contact details of the auditor.
Preparation
This allows the auditor to plan the audit by assigning questions to specific
people within the organisation. This will give everyone the opportunity
to be suitably mindful of what is expected of them in the audit process.
Audit Analysis
This worksheet indicates the progress of the audit, within each group, at
any stage of the audit, and gives a graphical image of the audit results.
Action Output
This pulls through the results of the audit schedule to allow the non-
conformities to be reviewed. The priority level against each of the
answers is used and each can be selected as necessary.
Audit Schedule
This is the most important element of the audit process, in which the
auditor provides scores and remarks against each question.
© BSRIA BG 24/2012
HOW TO USE THE TOOLKIT 7
Auditor Profile
This is a graph that shows how the auditor has scored the audit. It can be
used as a benchmark for other auditors carrying out the same or similar
audits, or a check for the same auditor undertaking the same audit some
years down the line. It is a check and can indicate an auditor's bias that
may need to be reviewed.
8 TOOLKIT GUIDE
The purpose of this section is to act as a guide on the key functions of an operation
and maintenance regime and to identify the main activities in each area that may
need to be audited. It also provides a brief commentary on the operation and
maintenance procedures that should be in place and identifies some of the items
that should be considered and about which questions should be asked during an
audit process. It may be modified and developed by individual organisations as a
template for their own audit.
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
The numbers in the right hand column of each of the tables in this
section refer to the questions in the toolkit.
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
Is there an ongoing training programme? 8.1.2i
Are adequate budget funds allocated for staff training 8.1.2j
and development?
Critical Is there a procedure for assessing and ensuring that the 8.1.2a
staff are competent to do their jobs?
Is this procedure adequate to satisfy legislative 8.1.2b
requirements such as the management of Health And
Safety at Work Regulations and the requirements of the
business?
Are there adequate arrangements to refresh training on 8.1.2c
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
INFORMATION TECHNOLOGY
PAS 55-2
Clause 4: Sections The use of computer-based information systems for the management of
4.4.6 the operation and maintenance function is becoming more prevalent.
4.4.5 This includes computer-based maintenance management systems,
4.6.4 building management systems and computer-based information
management systems such as electronic operation and maintenance
manuals.
The extent and level to which IT systems are used varies from one
organisation to another. The purpose of this section is to prompt the
audit process to examine whether the organisation uses the technology
available to its full potential and whether or not staff and managers use
this resource effectively as intended.
Minor How well does the IT system compare to the industry 8.1.3b
norms?
Is the information on the system secure? 8.1.3g
STAFF MOTIVATION
Staff motivation is important to the success of any organisation, leads
towards the retention of good staff and reduces the requirement and cost
to train new staff. It helps to maintain a team environment where
management can install and inspire changes in practice to improve
service.
There are legal requirements such as the Management of Health and Safety
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
8.2 PLANNING AND The purpose of this section is to identify those management functions related to
MANAGEMENT OF the operation and maintenance programme and to focus on key tasks under each
THE
MAINTENANCE function that need to be audited.
ACTIVITY
MAINTENANCE MANAGEMENT (GENERAL)
PAS 55-2
Clause 4: Sections The operation and maintenance function can be separated into
4.3.2 programmed or non-programmed activities. Planned maintenance,
4.3.3 statutory examinations, condition surveys and new build and
4.6.4 refurbishment works come under programmed work. Reactive
maintenance, unforeseen breakdowns, emergency maintenance and
disaster recovery can be considered non-programmed.
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
STORES MANAGEMENT
PAS 55-2
Clause 4: Sections Stores items are either consumable or non-consumable. Consumables are
4.5.2 those items used in maintenance, repairs and replacements, for example:
4.6.4 filters, lubricants, cable, fuses and pipe lengths. Non-consumable items
include items that aid the workforce, such as hand tools, equipment used
in testing and measurements, safety equipment, protective clothing and
those items with a capital rather than maintenance cost.
ISSUING STOCK
The auditor should assess the following:
STOCK TRANSPORTATION
The auditor should assess the following:
Moderate
Critical
STATUTORY EXAMINATIONS
PAS 55-2
Clause 4: Sections Certain building services plant and equipment are subject to periodic
4.4.8 statutory inspections. These inspections may reveal the need for
4.6.4 corrective action that may need to be completed within a given time
period. Examples of documentation and the legislation requiring these
can be found in Appendix C.
Minor
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
The maintenance plan must take into consideration all the requirements
of the Health and Safety at Work act and other legislation, along with
those planned maintenance tasks that are intended to reduce the
incidence of plant and system failure to the detriment of the core
business.
Minor Are funds available to carry out the additional works? 8.2.8b
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
NON-PROGRAMMED WORK
PAS 55-2
Clause 4: Sections The need for non-programmed work may arise out of unforeseen or
4.4.6 unplanned circumstances such as breakdowns, power failures and adverse
4.6.2 weather. The operation and maintenance organisation should have
4.6.4 procedures to cope with these so that any consequential effects can be
minimised.
Minor Has the organisation carried out an energy survey on the 8.3.1c
building?
Is there an energy champion for the building? 8.3.1d
WASTE MANAGEMENT
The auditor should assess the following:
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
Critical Is there a Health and Safety at work policy for operation 8.4.1a
and maintenance?
Does the policy and related organisational procedures 8.4.1b
adequately cover health and safety requirements relating to
maintenance, e.g. permit to work, method statements, risk
assessments, emergency procedures, access control, manual
handling, electrical safe
Is clear and adequate information, and where necessary, 8.4.1c
training, provided to staff and contractors?
Do staff understand their obligations? 8.4.1d
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
RISK ASSESSMENTS
PAS 55-2
Clause 4: Sections The auditor should verify that risk assessments are carried out in
4.4.3 accordance with the Management of Health and Safety at Work regulations
4.4.7 1989 and cover both generic and specific maintenance tasks, and that
4.6.4 they are reviewed periodically and revised as required. For example; are
they signed by the maintainer? When the task is finished is the
maintainer asked to comment on the adequacy and accuracy of the risk
assessment?
Minor
Moderate State who developed the Risk Assessment procedure. Are 8.4.2b
the risk assessments carried out adequate to cover both
generic and specific risks associated with the maintenance
operations?
Where necessary, are the risk assessments recorded? 8.4.2c
Is work covered by risk assessments monitored to ensure 8.4.2d
that the assessment requirements have been implemented
and that they are effective?
Are the assessments of risks and precautions taken 8.4.2e
reviewed periodically and revised as appropriate?
Critical Are risk assessments carried out in accordance with the 8.4.2a
requirements of Health & Safety at Work Legislation?
Minor
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
ACCESS CONTROL
PAS 55-2
Clause 4: Sections The auditor should comment on the access control procedures and their
4.4.3 relationship with the Permit to Work system and its implementation.
4.4.7
4.6.4 The auditor should assess the following:
Minor
Moderate Does the access control procedure cover all areas which 8.4.5b
should only be accessed by authorised or competent
persons?
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
Minor Have there ever been any reportable incidents on site? 8.4.7h
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
FINANCIAL CONTROL
PAS 55-2
Clause 4: Sections In order to achieve value for money and to ensure that the funds are
4.3.2 deployed correctly and honestly, organisations need to set out authorities
4.6.4 and delegations for spending. These may include procedures for
authorisations, individual expenditure limits, single order expenditure
limits and so on.
Minor Are there controls over sending out quotations for extra 8.5.2e
works?
Moderate Are the imposed financial limits adequate for efficient 8.5.2a
control of the funds and to avoid fraud?
Are there procedures if invoice costs exceed order costs? 8.5.2c
Critical Are the financial limits and controls adhered to (e.g. staying 8.5.2b
within limits, necessary authorization, written estimates,
etc.)?
Is the formal financial control system being bypassed? 8.5.2d
maintenance’ recorded?
Is full use made of current technology (e.g. mobile phones, 8.6.1f
cameras, computer-based systems, etc.)?
Moderate Are the procedures for communicating maintenance 8.6.1a
requirements satisfactory (e.g. reporting method, help desk,
routine meetings)? Give details of procedures
Is the procedure for tracking work in progress (WIP) 8.6.1b
satisfactory?
Critical Are clients kept informed of delays in attending to requests? 8.6.1e
8.7 RECORDS AND Holding records and keeping documentation is an important and
DOCUMENTATION integral part of the operation and maintenance process. There are legal
requirements as well as organisational needs for maintaining a good
PAS 55-2
quality system of record and documents relating to operation and
Clause 4: Sections
maintenance, for example cost management, risk assessments, review of
4.4.5
processes and avoiding fraud.
4.4.6
4.6.4
The purpose of this section is to focus on issues relating to the
management of a system of operation and maintenance documentation
with particular reference to its comprehensiveness, storage, archiving and
security.
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
may be small and involve simple work instructions and planning. The
audit checks given below apply to small additional works that are asked
of the maintenance team, either to directly deliver or manage the
delivery of. They do not apply to management of large and complex
projects.
The audit process should check whether these instructions are clear and
concise and whether they provide adequate information to the
workforce, that they are technically correct and reflect the standards
required by the organisation.
SUPPLIER SELECTION
PAS 55-2
Clause 4: Sections It may be necessary for an organisation to outsource some of its operation
4.4.2 and maintenance activities. These may include maintenance
4.4.4 management activities such as the review of planned maintenance system
4.4.9 and condition surveys, design activities and the physical operation and
4.6.4 maintenance work that would otherwise be carried out by the direct
employed labour force. There may also be a need to employ external
organisations to do specialist tests, inspections and calibrations.
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
ORDERING / PROCUREMENT
PAS 55-2
Clause 4: Sections The organisation should regularly re-assess its subcontractors and obtain
4.4.2 alternative quotes. These should be assessed for value, not just cost. For
4.6.4 example, environmental factors such as distance travelled during delivery
could be taken into account. Procuring services according to value will
also avoid accusations of favouritism.
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
WORKFORCE
This section includes audit checks that should be carried out to check the
workforce process for other work.
Moderate Are the plant, equipment and work tools adequate and of 8.8.7c
sufficient quality?
Are the communication arrangements adequate? 8.8.7d
Critical Are the skills and competence of the selected workforce 8.8.7a
adequate for the job?
WORKS MANAGEMENT
PAS 55-2
Clause 4: Sections The auditor should assess the following:
4.4.1
4.4.3 Minor
4.6.4 Moderate Is the method of monitoring site performance adequate? 8.8.8a
Are there normally significant delays, disruptions or 8.8.8b
additional costs associated with ‘Additional work’?
Critical Are there any variations to the contract after the work has 8.8.8c
been started?
8.9 CLIENT As mentioned in section 1.3, the client may be internal or external.
SATISFACTION
Gauging client satisfaction involves both measurable and subjective
observations. Often, the client’s perception of the success of the services
provided and their relative importance is different from that of the
operation and maintenance organisation. Therefore, the auditor should
carefully evaluate the client perception of the services provided, their
relative importance and the success. This information will be invaluable
to the operation and maintenance regime to re-orient itself to better
serve the client needs.
Minor Are the service levels appropriate for the needs of the 8.9.2j
client organisation?
Are response times to client requests in accordance with 8.9.2k
the service level agreement?
Are priorities allocated to client requests? 8.9.2l
Do the staff have the necessary technical and diplomatic 8.9.2p
skills for these meetings?
Are reporting procedures adequate 8.9.2q
Are any informal means of communicating utilized (e.g. 8.9.2r
personal contacts)?
Is the client regularly informed about guidance on other 8.9.3e
issues (e.g. site surveys by third parties)?
Moderate Are the requirements and constraints of the contract clear 8.9.1a
to the client and the O&M service provider?
Are repairs carried out in accordance with contractual 8.9.2i
agreements?
Is there compliance with:
Number of staff on site? 8.9.2a
Staff competence? 8.9.2b
Attendance? 8.9.2c
Plant performance criteria? 8.9.2d
Response times? 8.9.2e
Priorities for response? 8.9.2f
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
Reporting procedures 8.9.2g
After hours service? 8.92h
Are minutes taken at these client meetings and action 8.9.2n
points raised?
Are the existing interface methods between the client and 8.9.2o
the O&M service provider adequate?
Critical Are regular client meetings held? 8.9.2m
Is the client regularly informed on:
Condition of the estate? 8.9.3a
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
DISPUTES
Minor
Moderate Is there any history of disputes between the client and the 8.9.4a
O&M organisation?
Have any recommendations been made for improvements 8.9.4b
(e.g. procedural changes, communications improvements or
re-negotiation of contracts)?
Critical
Watchpoint Minor Are the areas unduly used for storage? 8.10.1f
If the checklists in tables Moderate Are these areas clean and tidy? 8.10.1a
3 and 4 are augmented
with photographic Are there any broken gauges? 8.10.1c
evidence, such survey and Are there any leaking glands? 8.10.1d
condition appraisal
Is there any damaged insulation? 8.10.1e
information could
contribute positively to Critical Are there any health and safety hazards? 8.10.1g
regular workplace risk Is the general condition of the plant satisfactory? 8.10.1b
assessments. See BSRIA
[9]
Guide BG 35/2012 for
further information on Checklists that can help to evaluate the basic site quality quickly are
Condition Surveys and Asset given in tables 3 and 4.
Data Capture.
The purpose of these checks is to raise warning signs and hence identify
the need for further probing. A competent site observer could develop
this into an objective scoring scheme for purposes of benchmarking and
prioritising actions.
Is there flammable material that has been unduly left that 8.11.1 c
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
Are facilities such as lifting gear available for this work? 8.11.3g
Are any extension cables, hose pipes etc. lying about that 8.11.3j
could cause tripping hazards?
Are tripping hazards that cannot be eliminated clearly 8.11.3k
marked?
Are hazards due to lack of head room clearly marked? 8.11.3l
Are there any other hazardous areas, (e.g. holes, trenches, 8.11.3m
etc.)?
Are they fenced as appropriate and marked with hazard 8.11.3n
warning signs?
Are the appropriate guards and barriers separating persons 8.11.3o
from hazards in place and secured?
© BSRIA BG 24/2012
TOOLKIT GUIDE 8
deterioration of plant?
Are there any water leaks from pump and valve glands, pipe 8.11.2j
joints or valves?
Are air inlets and exhausts free from obstruction? For 8.11.2m
example leaves on the ventilation grilles to boiler houses,
blocked or damaged exhaust pipes from generators
DOCUMENTATION
The auditor should check the following:
Minor
Critical
WORK PERSONS
The auditor should observe the following:
Minor
Critical
The authors have sought to incorporate the views of the steering group
but final editorial control of this document rests with BSRIA.
© BSRIA BG 24/2012
TRAINING AND COMPETENCE LEVELS B
The law requires employers to provide safe systems of work for their
employees. Any safe system of work is reliant on the competence of each
member of staff in their ability to carry out their duties correctly and
safely. This includes any supervisory duties that are required.
legal requirements for such competence, for example; Gas Safe Register
is the official gas registration body for the United Kingdom, Isle of Man
and Guernsey, appointed by the relevant Health and Safety Authority for
each area. By law all gas engineers must be on the Gas Safe Register.
Gas Safe Register replaced CORGI as the gas registration body in Great
Britain and Isle of Man on 1 April 2009 and Northern Ireland and
Guernsey on 1 April 2010.
The following lists the documentation and records that the auditor
should expect to find in an organisation that helps to demonstrate good
operation and management of assets and enables the building occupier to
demonstrate compliance with legislation.
This list has been generated as a minimum to expect although some may
not be relevant for smaller buildings and there may be others required for
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
© BSRIA BG 24/2012
REFERENCES
REFERENCES
1 PAS 55-1:2008 Asset management. Specification for the optimized management of physical assets.
ISBN:978 0 580 50975 9
2 PAS 55-2:2008 Asset management. Guidelines for the application of PAS 55-1. ISBN:978 0 580
50976 6
Licensed copy from CIS: hbreavis, H B REAVIS UK LIMITED, 08/06/2021, Uncontrolled Copy.
3 BS EN ISO 9000:2005 Quality Management Systems. Fundamentals and Vocabulary. ISBN:0 580
46751 1
4 BS EN ISO 19011-2:2011 Guidelines for auditing management systems. ISBN:978 0 580 77524 6
5 B&ES Formerly HVCA) SFG20 Standard Maintenance Specifications for Building Services (Web
Application www.sfg20.com)
7 BSRIA BG 35/2012 Condition Surveys and Asset Data Capture. ISBN:978 0 860 27069
¢ Testing ¢ Troubleshooting
¢ Modelling ¢ Information
¢ Research ¢ Training
¢ Consultancy ¢ Publications