Professional Documents
Culture Documents
BG 50/2013
1
Acknowledgements
The steering group was chaired by Alan Edwards representing the Water
Management Society, and the editor for the publication was Reginald Brown
of BSRIA. Design and production was carried out by Joanna Smith of BSRIA.
BSRIA wishes to thank all the members of the steering group for their
contributions:
Every opportunity was taken to incorporate the views of the steering group,
however final editorial control of the publication rested with BSRIA.
The guidance given in this publication is correct to the best of BSRIA’s knowledge. However BSRIA
cannot guarantee that it is free of errors. Material in this publication does not constitute any warranty,
endorsement or guarantee by BSRIA. Risk associated with the use of material from this publication is
assumed entirely by the user.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or
transmitted in any form or by any means electronic or mechanical including photocopying, recording or
otherwise without prior written permission of the publisher.
© BSRIA October 2013 ISBN 978-0-86022-724-3 Printed by Charlesworth Press
In particular the guide will help facilities managers and others to engage in
constructive discussion with water treatment professionals and choose the
most appropriate water treatment programme for their systems.
The guide partially replaces BSRIA AG 2/93 Water treatment for building
services systems in respect of closed system applications. The guidance is
consistent with BSRIA BG 29/2012 Pre-commission cleaning of pipework
systems, BS 8552:2012 Sampling and monitoring of water from building
services closed systems. Code of practice and the European Biocidal products
Regulation (528/2012, commonly known as BPR).
1 INTRODUCTION 1
3 CORROSION PROCESSES 21
3.1 Chemical corrosion processes 21
3.2 Microbially influenced corrosion (MIC) 31
7 REGULATIONS 78
7.1 Health and safety 78
7.2 Other regulations 79
GLOSSARY 101
1 INTRODUCTION
The scope of this guide is water treatment for the control of corrosion
and maintenance of water quality in closed heating and cooling systems in
buildings other than individual dwellings. This includes low temperature
hot water heating systems, heat pump and chilled water systems and
condenser water circuits. It is also relevant to community heating and
cooling networks operating at temperatures below 110°C.
The scope does not include the specific requirements for water treatment
for medium and high temperature heating systems, for which reference
should be made to BS 2486[3].
This scope does not include water treatment for open systems such as
cooling towers and steam boilers or for domestic hot and cold water
services.
Various technical issues are discussed in detail in the appendices and there
is a glossary and bibliography at the end of this guide.
¢ Testing ¢ Troubleshooting
¢ Modelling ¢ Information
¢ Research ¢ Training
¢ Consultancy ¢ Publications
Pre-commission Cleaning of
Pipework Systems
Re
up vise
da d a BG 29/2012
20 ted nd
12 for
ACKNOWLEDGEMENTS
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system,
or transmitted in any form or by any means electronic or mechanical including photocopying,
recording or otherwise without prior written permission of the publisher.
© BSRIA BG 29/2012
PREFACE
© BSRIA BG 29/2012
PREFACE
BG 29/2012
The purpose of the 2012 update is to reflect new British and European
standards, correct some minor errors in the 2011 edition, and to clarify
certain points that have been raised in the past year. Changes are as
follows:
Reginald Brown
2012
© BSRIA BG 29/2012
CONTENTS
1 INTRODUCTION 1
2 DESIGN CONSIDERATIONS 3
2.1 introduction 3
2.1.1 General 3
2.1.2 Responsibilities 3
2.1.3 When to chemically clean 3
2.1.4 Specification for system cleaning 4
2.2 system chemistry 6
2.2.1 System contaminants 6
2.2.2 Choice of chemicals 8
2.2.3 Typical stages of a clean 9
2.3 pipework system design 10
2.3.1 General provisions 10
2.3.2 Large bore pipework 15
2.3.3 Plastic pipework 15
2.3.4 Stainless steel 16
2.3.5 System facilities 16
2.3.6 System schematic 17
2.3.7 Systems with two-port control valves 25
3 INSPECTION AND WITNESSING 30
3.1 timetable 30
3.2 monitoring to practical completion 33
4 INSTALLATION CONSIDERATIONS 42
4.1 management 42
4.1.1 Management 42
4.1.2 Organisation and planning 42
4.1.3 Record keeping 43
4.1.4 Choice of chemicals 43
4.1.5 COSHH Regulations 44
4.1.6 Other risks 45
4.1.7 Consequential damage 45
4.2 pipework installation 45
4.2.1 Materials storage 45
4.2.2 Good installation practice 46
4.3 preparation for flushing and cleaning 46
4.3.1 Method statements and risk assessments 46
4.3.2 Installation checks 46
4.3.3 Drainage 47
4.3.4 Water supply 47
4.4 procedure for filling and pressure testing 48
4.4.1 System filling 48
4.4.2 System pressure testing 48
4.4.3 Basic procedure for pressure testing 49
5 SYSTEM DYNAMIC FLUSHING 54
5.1 flushing objectives 54
5.1.1 Importance of water velocity 54
5.2 dynamic flushing procedure 55
5.2.1 General considerations 55
© BSRIA BG 29/2012
CONTENTS
© BSRIA BG 29/2012
TABLES
FIGURES
© BSRIA BG 29/2012
LIST OF SYMBOLS
TP Test point
Gas-fired boiler
STR
Strainer
MV
Motorised four-port
valve M Water meter
MV
Motorised three-port AAV Automatic air vent
valve
MAV
MV
Motorised two-port Manual air vent
valve
FC Flexible coupling
hose connection
SV
Safety valve FP Fill point
© BSRIA BG 29/2012
INTRODUCTION 1
1 INTRODUCTION
Pre-commission cleaning, as it is applied to heating, cooling and other
closed pipework systems, is the process of bringing the system to a
satisfactory state for commissioning and on-going maintenance of water
quality. This means that:
This guide is not concerned with the cleaning of domestic hot and cold
water services systems in buildings.
© BSRIA BG 29/2012
Pre comm green cover_D3-2010 Legislation cover.qxd 05/10/2012 11:03 Page 2
Testing Troubleshooting
Modelling Information
Research Training
Consultancy Publications