Interface Schedule Package 1 and Package 2
Interface Schedule Package 1 and Package 2
Interface Schedule
0 General
Confirmation to Package 1 Contractor of loads and
0.1 dimensions of overall hydromechanical gates and other Package 2 90 743
components by Package 2 Contractor
1 Radial gates, stoplogs and operating equipment etc. for main dam spillway
Section Completion Date 5.4 – Completion of Main Dam
concrete placement and other civil works necessary to
1.1 allow Package 2 Contractor to have access to, and Package 1 1295 1948
commence erection of, the spillway gates and to cast
the associated concrete encasement
Spillway Bay N°1 gate installation completed and
1.2 Package 2 1386 2039
released to Package 1 Contractor
Spillway Bay N°2 released to Package 2 Contractor for
1.3 Package 1 1414 2067
gate installation
Spillway Bay N°2 gate installation completed and
1.4 Package 2 1505 2158
released to Package 1 Contractor
Spillway Bay N°3 released to Package 2 Contractor for
1.5 Package 1 1449 2102
gate installation
Spillway Bay N°3 gate installation completed and
1.6 Package 2 1540 2193
released to Package 1 Contractor
Spillway Bay N°4 released to Package 2 Contractor for
1.7 Package 1 1449 2102
gate installation
Spillway Bay N°4 gate installation completed and
1.8 Package 2 1540 2193
released to Package 1 Contractor
Block C released to Package 2 Contractor for spillway
1.9 Package 1 1435 2088
stoplogs storage works
Stoplog spillway storage bay works completed and
1.10 Package 2 1533 2186
released to Package 1 Contractor
Spillway gates and stoplogs detailed layout and shape
1.11 Package 2 224 877
design by Package 2 Contractor
Detailed design (calculations & drawings) of all spillway
1.12 and dam crest hydromechanical components by Package 2 630 1283
Package 2 Contractor
Provision of drawings and supply of first stage
1.13 embedded steel parts to the Package 1 Contractor in Package 2 945 1598
accordance with the Contract
Provision of requirements for grounding system to the
1.14 Package 2 120 773
Package 1 Contractor in accordance with the Contract
1.15 Design, supply and installation of grounding system Package 1 700 1353
Tanahu Hydropower Project: Package 1 Head Works (Re-bid II) Bidding Document Volume V
9-12 Section 9 – Contract Forms
Package 1
Preparation and provision of drawings necessary for the as as
1.16 and
above works at the main dam required required
Package 2
Gates and operating equipment etc. and steel liners for water level lowering outlets in
2
main dam
Section Completion Date 5.2 – Completion of the main
dam concrete placement necessary to allow the Package 2
2.1 Contractor to have access and commence installation of Package 1 1176 1829
the hydromechanical equipment and associated
concrete encasement of the water level lowering outlets
Left water level lowering gates area handed over to
2.2 Package 2 1239 1892
Package 1 Contractor
Right water level lowering area handed over to Package 1
2.3 Package 2 1239 1892
Contractor
Completion of installation and dry testing of all
hydromechanical equipment related to the water level
2.4 lowering outlets in the Main Dam ready for reservoir Package 2 1498 2151
impoundment above elevation 336.00 masl
[Package 2 Section Completion Date 3.2]
Provision of preliminary design information to the
2.5 Package 1 Contractor related to the water level lowering Package 2 90 743
outlets equipment in accordance with the Contract
Provision of final design information to the Package 1
2.6 Contractor related to the water level lowering outlets Package 2 270 923
equipment in accordance with the Contract
Design of the concrete structures including block-outs
2.7 Package 1 364 1017
for gate installation and access ladders or steps.
Provision of drawings and supply of first stage
2.8 embedded steel parts to Package 1 Contractor in Package 2 896 1549
accordance with the Contract
Provision of requirements of operation rooms of water
2.9 level lowering equipment to the Package 1 Contractor in Package 2 90 743
accordance with the Contract
Package 1
Preparation and provision of drawings necessary for the as as
2.10 and
above works required required
Package 2
Gates and operating equipment etc. and steel liners for sediment flushing outlets in
3
main dam
Section Completion Date 5.1 – Completion of the main
dam concrete placement necessary to allow the Package 2
3.1 Contractor to have access and commence installation of Package 1 1050 1703
the hydromechanical equipment and associated
concrete encasement of the sediment flushing outlets
Sediment sluice area handed over to Package 1
3.2 Package 2 1215 1868
Contractor
Tanahu Hydropower Project: Package 1 Head Works (Re-bid II) Bidding Document Volume V
Section 9 – Contract Forms 9-13
Tanahu Hydropower Project: Package 1 Head Works (Re-bid II) Bidding Document Volume V
9-14 Section 9 – Contract Forms
Tanahu Hydropower Project: Package 1 Head Works (Re-bid II) Bidding Document Volume V
Section 9 – Contract Forms 9-15
Package 1
Preparation and provision of drawings necessary for the as as
7.3 and
above works. required required
Package 2
8 Maintenance of access roads constructed by the Employer
Maintenance of the existing road from the conjunction of throughout
8.1 the national highway H04 to the end point in Beni Patan Package 1 contract –
improved by the Employer period
Maintenance of the section from the start point (the end
throughout
of the existing road) in Beni Patan to the branch point of
8.2 Package 1 contract –
upstream and downstream areas of the access road on
period
the right bank via the access bridge
Maintenance of the section from the above branch point throughout
8.3 to upstream end point of the access road on the dam Package 1 contract –
right bank period
throughout
Maintenance of the surface of the access bridge across
8.4 Package 1 contract –
the Seti River
period
throughout
Maintenance of the access road from the end of the
8.5 Package 1 contract –
existing road to the end point on the dam left bank
period
Maintenance of the section from the branch point of throughout
8.6 upstream and downstream areas to end point in vicinity Package 2 – contract
of the Employer’s camp on the dam right bank period
9 Package 2 main power intake structure
Completion of all works required for the construction of
the intake structure including trashrack, gates and all
9.1 associated equipment, and closure of stoplog ready for Package 2 429 1082
reservoir impoundment above elevation 360.00 masl
[Package 2 Section Completion Date 3.3]
Tanahu Hydropower Project: Package 1 Head Works (Re-bid II) Bidding Document Volume V