You are on page 1of 9

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 25 (2007) 485–493
www.elsevier.com/locate/ijproman

Modelling risk allocation decision in construction contracts


K.C. Lam *, D. Wang, Patricia T.K. Lee, Y.T. Tsang
Construction Management Research Group, Department of Building and Construction, City University of Hong Kong, 83 Tat Chee Avenue,
Kowloon Tong, Hong Kong, PR China

Abstract

The allocation of risk among the contracting parties in a construction contract is an important decision leading to the project success.
The decision-making process, based on the established risk allocation principles expressed in linguistic terms, requires qualitative judge-
ment and experiential knowledge of the construction experts. However, it is subjective and implicit. This paper presents a decision model
which transforms the linguistic principles and experiential expert knowledge into a more usable and systematic quantitative-based anal-
ysis by using the fuzzy logic. Seven risk allocation criteria and a set of knowledge-based fuzzy inference rules are established according to
the expert knowledge. Risk events are assessed on each criterion and the relevant rules. The corresponding risk allocation decisions
between the owner and contractor are then suggested by the model. A practical case to illustrate how the model works is presented.
 2006 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Construction contract; Risk allocation; Fuzzy logic; Modelling; Expert system

1. Introduction Risk allocation, the definition and division of responsi-


bility associated with a possible future loss or gain, seeks
No construction project is risk-free. Risk is manageable, to assign responsibility for a variety of hypothetical cir-
diminishable, transferable or acceptable but not ignorable cumstances should a project not proceed as planned [5].
[1]. Rahman and Kumaraswamy [2] identified 41 risks in As a part of a risk management strategy, it is commonly
construction projects. Risk management is thus an impor- defined through the contractual documents. Usually, a ten-
tant tool to cope with such substantial risks in construction der document of a construction project is prepared by the
industry by: (a) assessing and ascertaining project viability; contracting party, i.e. the owner, who initiates the project.
(b) analyzing and controlling the risks in order to minimize It is common that the owner tends to contractually pass the
loss; (c) alleviating risks by proper planning; and (d) avoid- responsibility for most of the risks to the contractor under
ing dissatisfactory projects and thus enhancing profit mar- traditional procurement processes [7]. A contract can thus
gins [3,4]. A risk management process typically comprises be considered as a trade-off between the contractor’s price
establishment of context, risk identification, risk analysis, for undertaking the work and his willingness to accept both
risk evaluation and risk response [3,5,6]. A risk can be the controllable and uncontrollable risks [8]. Whether the
characterized by the risk event, its probability of occur- party is willing and aware to bear the risk will affect its
rence and the amount of potential loss or gain. All factors response to risk [9]. The cost of improper risk allocation
comprising a risk are to be identified, analysed and evalu- could be seen from the response from contractors such as
ated so that response can then be given. Risk response is adding a high contingency (premium) to the bid price or
a process of formulation of a management strategy leading delivering low quality work. During the project, the owner
to identifying action owners and the risk management plan. might spend more management resources for the increased
work disputes. Upon completion of the works, litigation of
*
Corresponding author. Tel.: +852 2788 7238; fax: +852 2788 7612. contractual claims might come after. In the worst case, the
E-mail address: bckclam@cityu.edu.hk (K.C. Lam). owner pays for the risks twice including one in bidding con-

0263-7863/$30.00  2006 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2006.11.005
486 K.C. Lam et al. / International Journal of Project Management 25 (2007) 485–493

tingencies and the other one in court [10]. The allocation of intrinsic to human cognitive processes. Since then, it has
risk is thus one of the important decision-making processes been adopted to tackle ill-defined and complex real-world
leading to project success. problems due to partial and imprecise information. It is
Optimally, the goal of risk management should be to particularly suitable for uncertain or approximate reason-
minimize the total cost of risk to a project, not necessarily ing that involve human intuitive thinking. Fuzzy set theory
the costs to each contracting party separately [11]. The uses linguistic variables and membership functions with
most challenging of the task is to decide what the equitable varying grades to model uncertainty inherent in natural
risk allocation is such that the goal is effectively accom- language [19].
plished. While model or standard sets of general conditions In classical (crisp) set theory, each single element x in a
of contract are available, it is argued that the principles universal set X can either belong to or not belong to a sub-
behind the allocations in these documents have not been set A, A ˝ X. The member elements can be defined by using
clearly stated [12]. Problems can arise using any of them a characteristic function. It assigns a binary value (either 1
if additional clauses affecting risk are applied to them. or 0) to each element x 2 X , in which 1 indicates member-
Moreover, the nature and extent of risks tend to be pro- ship and 0 non-membership. In fuzzy set theory, the char-
ject-specific in today’s high-risk scenarios and multiparty acteristic function allows various degrees of membership
complex projects that adoption of tailor-made contract for the elements. Larger values denote higher degrees or
strategies is more desirable [2]. grades of set membership. Such a generalized function is
Various risk allocation principles had been suggested by called a membership function, l(x), in fuzzy set theory with
a number of researchers such as Casey [13], Kuesel [14], a range of values within an unit interval [0, 1]. Then a fuzzy
Barnes [15], Abrahamson [16] and Thompson and Perry subset A e in a universal set X is a set of ordered pairs
[12]. Adopting these principles as the basis for allocating denoted by
risks is useful in reaching an equitable decision. It would e ¼ fðx; lA~ ðxÞÞ j x 2 X g
A
be ultimately beneficial to both owners and contractors
[17]. Like most of the management doctrines, all these risk Fuzzy set theory allows the use of linguistic variables
allocation principles commonly use natural language in the whose values are not numbers but words or sentences in
expression, which are nevertheless ambiguous in actual a natural or artificial language which are less specific than
application. For example, one of the principles mentioned numerical ones [20].
by Abrahamson [16] states that ‘a party should bear a con- For example, let X be a linguistic variable with the label
struction risk where it is in his control’. The term ‘‘in his ‘‘Age’’ with U = [0, 100]. The linguistic values called terms
control’’ is difficult to be precisely interpreted as the ‘‘con- of this variable could be called ‘‘old’’, ‘‘young’’, ‘‘very old’’
trol’’ by a contracting party on a real situation could be and so on. T(X) will define the term set,
‘partial’. The application of those principles to final deci-
T ðageÞ ¼ fvery old; old; not so old; more or less young;
sion making thus heavily relies on the qualitative judgment
and experiential knowledge of construction experts. The quite young; very youngg
problem of this kind of decision making process is its If a base variable u is equal to the age in years of life, then a
implicitness. Too often it is difficult to be analyzed and fuzzy subset Ne ðX Þ and its membership function of the term
retrieved by others. Human factors such as the attitude ‘‘old’’ can be [21]:
of the parties [15] and bias in personal judgments may
e ðoldÞ ¼ fðu; lold ðuÞÞ j u 2 ½1; 100g
N
impose significant variation on the decision outcome. Rah- (
man and Kumaraswamy [2] had shown that there was a 0 u 2 ½0; 50
divergence of perception on risk allocation in construction where lold ðuÞ ¼ 2 1
ð1 þ ðu50
5
Þ Þ u 2 ½50; 100
contracts among different groups. It is not surprising that
improper risk allocation in construction contracts remains Based on fuzzy set theory, the fuzzy reasoning technique is
a concern in the construction industry in Hong Kong [18]. close to the approach to inference from commonsense
The purpose of this paper is to provide a prototypic knowledge [22,23]. The fuzzy inference rules can be built
quantitative model for risk allocation process. It aims to to represent the knowledge and heuristic rules of experi-
support the decision making in risk management such that enced personnel (i.e. experts in the area). They are usually
the concerns of improper risk allocation can be addressed. in the form: ‘‘IF a set of conditions/premises is satisfied,
As linguistic principles and qualitative expert knowledge THEN a set of consequences can be produced’’. It could
are the essential ingredients of the risk allocation process, be applied to establish a fuzzy inference engine of a deci-
the fuzzy set theory which relates to quantification and rea- sion supporting system with imprecise and uncertain
soning of natural language is utilized in the model building. information.

2. Fuzzy set theory 3. Proposed risk allocation decision model

Fuzzy set theory is a branch of modern mathematics for- This study currently focuses on the main contract and its
mulated by L.A. Zadeh in the 1960s to model vagueness risk allocation between owners and contractors. A mathe-
K.C. Lam et al. / International Journal of Project Management 25 (2007) 485–493 487

matical model based on the fuzzy set theory is developed to 1. Whether the party is able to foresee the risk. A risk
support the decision making of risk allocation. receiving party can take appropriate measures to man-
The model mainly consists of three parts, namely: fuzz- age a risk only if the party can reasonably foresee the
ification, inference engine and defuzzification. Fuzzifica- risk he may encounter [14].
tion is a procedure that converts raw data from the 2. Whether the party is able to assess the possible magnitude
practical world into membership values of corresponding of consequences of the risk. If the risk receiving party is
fuzzy subsets. The transformed data are then fed into not able to assess the possible magnitude of consequence
the inference engine containing a rule base. The fuzzy of the risk, he may underestimate the outcome and make
mathematic operations are implemented, producing mem- inadequate allowance at the time of tendering to cover
bership values belonging to the output variables. Defuzz- his obligation [13].
ification is followed to convert the fuzzy inferences from 3. Whether the party is able to control the risk chance of
the engine to a single output action giving a clear indica- occurring. A party should bear the risk that he can exer-
tion to the human user. The model is illustrated by Fig. 1. cise best control on minimizing or avoiding the materi-
alization of the risk [12,14–16].
3.1. Input variables for risk allocation decision 4. Whether the party is able to manage the risk in case of
occurring. Risk should be allocated to the party who is
An expert team is organized in the process of formu- best able to manage it in order to minimize the severity,
lation of the model. The team involves a deputy director, extra cost and delay once the risk occurs [12].
a cost and quantity manger, a contracts manager, a 5. Whether the party is able to sustain the consequences if
senior manager, two quantity surveyors and a cost con- the risk occurs. [12]. Chapman and Ward [24] pointed
trol administrator from various organizations including out that the party able to manage a risk may not be
owners, consultants and contractors. They all have over the party best able to bear the consequences of that risk.
15-year experience in the construction industry and are 6. Whether the party will benefit from bearing the risk. Risk-
at the managerial level. Based on the previous works bearing can be beneficial to a receiving party such as the
of risk allocation [12–16] and through discussions with enhancement of credibility, reputation and efficiency in
the team members, risk allocation criteria were identified planning and innovation [16].
as follows: 7. Whether the premium charged by the risk receiving party
is considered reasonable and acceptable for the owner.
When an owner intends to transfer a risk to a contrac-
tor, he needs to consider whether the contractor will
charge a high price for taking the risk or he should
Identify input variables Establish risk
and linguistic terms allocation criteria
assume the risk himself so that a more realistic and rea-
sonable tender price will be finally obtained [12].

Conduct fuzzification – As the model considers the risk allocation between the
convert linguistic terms owner and contractor of a traditional contract arrange-
into membership functions ment, seven linguistic input variables, denoted by IV1–
IV7, are subsequently derived based on the risk allocation
criteria. To evaluate a risk event, the percentage is used
Examine the relevant base Build up base rules to indicate the likelihood of the risk being foreseeable,
rules in the Inference by pooling expert’s
Engine knowledge assessable, controllable, manageable, sustainable by or
beneficial to the contractor, which forms the base variable
of the IV1–IV6. The percentage of premium in relation to
Apply fuzzy mathematic estimated cost of risk transfer is used for IV7. All base vari-
operations to obtain the ables range from 0% to 100%.
membership values of Based on the fuzzy set theory, the linguistic values, i.e. terms
inferences (TIV), are defined to describe the input variables to facilitate
the building of fuzzy inference rules in the next stage. For
Apply center-of-sum
IV1–IV6 the finalized term set is {very unlikely, unlikely, mod-
method to calculate the erate, likely, very likely} and for IV7 the term set is {acceptable,
overall value of the output moderate, unfavourable} through discussion with the expert
variable team. All details are listed in Table 1.

3.2. Fuzzification of the input variables


Determine final risk
allocation decision
The procedure for transforming input data such that
Fig. 1. Risk allocation decision model. they belong to a particular fuzzy subset is known as fuzzifi-
488 K.C. Lam et al. / International Journal of Project Management 25 (2007) 485–493

Table 1
Input variables and terms
Foreseeable by the contractor, IV1 Range of % of likelihood
TIV11 Very unlikely 0–25
TIV12 Unlikely 0–50
TIV13 Moderate 25–75
TIV14 Likely 50–100
TIV15 Very likely 75–100
Assessable by the contractor, IV2 Range of % of likelihood
TIV21 Very unlikely 0–25
TIV22 Unlikely 0–50
TIV23 Moderate 25–75
TIV24 Likely 50–100
TIV25 Very likely 75–100
Controllable by the contractor, IV3 Range of % of likelihood
Fig. 2. Fuzzification functions for ‘‘foreseeable by the contractor’’.
TIV31 Very unlikely 0–25
TIV32 Unlikely 0–50
TIV33 Moderate 25–75
They are adopted to represent the membership functions of
TIV34 Likely 50–100
TIV35 Very likely 75–100 the terms of input variables in the model. The ranges of
each TIV covering are defined by the expert team as listed
Manageable by the contractor, IV4 Range of % of likelihood
in Table 1. Fig. 2 illustrates the fuzzification functions for
TIV41 Very unlikely 0–25
TIV42 Unlikely 0–50 IV1,‘‘foreseeable by the contractor’’, in which S function
TIV43 Moderate 25–75 or p functions are used alternatively for the term set. The
TIV44 Likely 50–100 fuzzification functions for IV2 to IV6 are same as the IV1.
TIV45 Very likely 75–100 For the term set of IV7, the fuzzification functions are
Sustainable by the contractor, IV5 Range of % of likelihood shown in Fig. 3. As such each value of IVs is associated
TIV51 Very unlikely 0–25 with the membership values belonging to different TIVs
TIV52 Unlikely 0–50 within a unit interval.
TIV53 Moderate 25–75
TIV54 Likely 50–100
TIV55 Very likely 75–100 3.3. Output variable – risk allocation decision
Beneficial to the contractor, IV6 Range of % of likelihood
TIV61 Very unlikely 0–25 The output variable of the model is the risk allocation
TIV62 Unlikely 0–50 decision which is defined on the basis of the risk allocation
TIV63 Moderate 25–75 scale adopted by Hartman et al. [25] with modification by
TIV64 Likely 50–100 the expert team. The allocation scale proposes a range of
TIV65 Very likely 75–100
risk apportionment from fully bearing by the owner,
Premium of transfer, IV7 Range of % of premium in through a continuum to fully bearing by the contractor.
related to estimated cost Three values of output variable (OV) are identified: own-
TIV71 Premium charged by the 0–40
contractor is unfavourable
er’s risk (=1); shared risk (=2); and contractor’s risk
TIV72 Premium charged by the 0–80 (=3). The S and p functions are adopted again to trans-
contractor is moderate form the scale to the corresponding fuzzy subsets as shown
TIV73 Premium charged by the 40–100 in Fig. 4.
contractor is acceptable
3.4. The rule base
cation. The most popular fuzzification functions are either
the S function or p function. They are defined as follows By utilizing the fuzzy reasoning technique, a rule base is
[20]: built in the inference engine of the model based on the expe-
8
>
> 0 for m 6 a
>
>  2
>
> ma
< 2 ca for a 6 m 6 b
Sðm; a; b; cÞ ¼  2
>
> mc
>
> 1  2 ca for b 6 m 6 c
>
>
:
1 for m P c
( b
Sðm; c  b; c  2 ; cÞ for m 6 c
pðm; b; cÞ ¼ b
1  Sðm; c; c þ 2 ; c þ bÞ for m P c
ð a þ cÞ
with b ¼ and m; a; b; c are real numbers:
2 Fig. 3. Fuzzification functions for ‘‘premium of transfer’’.
K.C. Lam et al. / International Journal of Project Management 25 (2007) 485–493 489

i.e. the OV having the highest membership grade of


d(OV) will be chosen (max[l(OVj)] where j 2 {1, . . . , M}).
It gives a clear linguistic indication to the human user of
overall decision of risk allocation.

4. Evaluation of the model

A railway company supported by the Hong Kong Gov-


ernment has been proceeding with the design, construction,
Fig. 4. Fuzzification functions for ‘‘risk allocation’’.
financing and operation of the railway network in Hong
Kong. To manage a latest large-scale railway construction
rience and knowledge of the expert team. The production composed of 15 civil engineering contracts of awarded sum
rules in IF–THEN format are used to represent the expert ranging from HK$118 million to HK$2238 million, the
knowledge, i.e. ‘‘if a set of conditions/premises is satisfied, company specifically developed a set of conditions of con-
then a set of consequences can be produced.’’ The inference tract entitled as ‘‘Railway General Conditions of Contract
engine is a mechanism for manipulating the encoded for Civil Engineering and Building Works’’ (RGCC).
knowledge and to form inferences and draw conclusion 16 risk events are identified from the RGCC as listed in
[21]. A typical mathematical format for N number of input Table 2. Based on the Casey’s categorization [13], they are
variable (IV), S number of terms (TIV) associated with categorized into five groups for clarity, namely, capability
each IV, and M number of output variable (OV) is [26]: related risks, contractual and legal risks, economic risks,
IF fIVi is TIVik g and . . . and fIVu is TIVuv g THEN OVj physical risks and political and societal risks.
where i 2 f1; . . . ; N g; k 2 f1; . . . ; S i g; u 2 f1; . . . ; N g; The participants of the expert team are again asked to
assess each risk events against each risk allocation criterion
v 2 f1; . . . ; Su g; j 2 f1; . . . ; Mg and u 6¼ i
in terms of the percentage of likelihood for IV1–IV6 or pre-
mium in relation to estimated cost for IV7. Each partici-
Theoretically, the total number of possible fuzzy inference
pant works independently based on his/her experience
rules would be SN rules, which can be enormous. The
and professional judgment to determine the value of each
advantage of fuzzy reasoning is that even when all the rules
input variable. As this study focuses on the building of a
are not present we can still get reasonable and usable re-
prototypic quantitative model based on fuzzy reasoning
sults. The larger the rule base is, the better the result can
techniques, the arithmetic mean of all participants’ value
be [26,27].
is taken for simplicity. It is then used to derive the member-
Since the membership function of TIVik is given by lik
ship values of the seven input variables for each risk event
and so on, the membership function of the output variable
using Figs. 2 and 3. The outcome is listed in Table 2. In
ðOVpj Þ of the pth rule is given by using the ‘‘minimum’’
case participants have clear differences in estimating the
operation of the fuzzy set theory:
value in actual applications, these differences should be
lðOVpj Þ ¼ lpik ^    ^ lpuv ¼ min½lpik ; . . . ; lpuv  explicitly discussed, e.g., through the approach of the Kei-
zer, Halman and Song’s work [29], before feeding into the
model.
3.5. Defuzzification and decision for risk allocation
The fuzzified data are then fed into the inference engine
in which the relevant base rules are examined for each risk
When a case is evaluated, it will be examined by each
event. Total 128 (=27) base rules has been examined for
rule in turn. Defuzzification is followed to convert each
each case. To demonstrate how the model works, one of
conclusion expressed in terms of a fuzzy set obtained by
the risk events, ‘‘Third Party Delay’’, is taken as an exam-
the inference engine to a single output action. The center-
ple. For IV1, the mean percentage of likelihood of Third
of-sum method is used to determine the overall level of risk
Party Delay foreseeable by the contractor assessed by the
allocation of all examined rules. It is a popular defuzzifica-
expert team is 38%. It is fuzzified into the fuzzy subsets
tion method in most fuzzy control algorithms and tools
of the Terms TIV12 ‘‘Unlikely’’ and TIV13 ‘‘Moderate’’
[21]. The idea of this method is to aggregate the informa-
with membership grade of 0.43 and 0.57, respectively, using
tion about possible control actions that are represented
Fig. 2. All other values of the input variables for this risk
by the membership functions so as to reach a compromise
event are similarly transformed.
solution. If total T rules are examined, the numerical
In the inference engine, for instances, the first relevant
defuzzified value, d(OV), is computed as
base rule established is:
XT   X T  
dðOV Þ ¼ ðOVpj Þ  l OVpj = l OVpj IF Third Party Delay is unlikely foreseeable by the con-
p¼1 p¼1
tractor: IV1 = TIV12
If d(OV) lies between two values of the set of OV, the final and it is unlikely assessable by the contractor:
decision is made by choosing the value of closet to it [28], IV2 = TIV22
490
Table 2
16 Risk events and the corresponding membership values of input variables
IV1, Foreseeable by IV2, Assessable by IV3, Controllable IV4, Manageable by IV5, Sustainable by IV6, Beneficial by IV7, Premium of
the contractor the contractor by the contractor the contractor the contractor the contractor transfer
Capability
Contractor’s design TIV14 TIV15 TIV24 TIV25 TIV34 TIV35 TIV44 TIV45 TIV54 TIV55 TIV64 TIV65 TIV72 TIV73
0.07 0.93 0.09 0.91 0.08 0.92 0.21 0.79 0.17 0.83 0.08 0.92 0.86 0.14
Subcontractor failure TIV13 TIV14 TIV23 TIV24 TIV33 TIV34 TIV44 TIV45 TIV54 TIV55 TIV63 TIV64 TIV72 TIV73

K.C. Lam et al. / International Journal of Project Management 25 (2007) 485–493


0.23 0.77 0.11 0.89 0.28 0.72 0.12 0.88 0.21 0.79 0.33 0.67 0.31 0.69
Quality of work TIV13 TIV14 TIV24 TIV25 TIV34 TIV35 TIV44 TIV45 TIV53 TIV54 TIV63 TIV64 TIV72 TIV73
0.13 0.87 0.29 0.71 0.21 0.79 0.21 0.79 0.30 0.70 0.11 0.89 0.22 0.78
Safety at site TIV13 TIV14 TIV23 TIV24 TIV34 TIV35 TIV44 TIV45 TIV53 TIV54 TIV63 TIV64 TIV72 TIV73
0.15 0.85 0.29 0.71 0.79 0.21 0.90 0.10 0.35 0.65 0.45 0.55 0.34 0.66
Obtaining approval or consent TIV13 TIV14 TIV23 TIV24 TIV33 TIV34 TIV44 TIV45 TIV52 TIV53 TIV63 TIV64 TIV72 TIV73
from relevant authority 0.33 0.67 0.35 0.65 0.41 0.59 0.45 0.55 0.11 0.89 0.34 0.66 0.67 0.33
Contractual and legal
Conflicts in documents TIV11 TIV12 TIV21 TIV22 TIV31 TIV32 TIV42 TIV43 TIV51 TIV52 TIV61 TIV62 TIV71 TIV72
0.21 0.79 0.21 0.79 0.95 0.05 0.63 0.37 0.17 0.83 0.83 0.17 0.93 0.07
Third party delay TIV12 TIV13 TIV22 TIV23 TIV32 TIV33 TIV42 TIV43 TIV51 TIV52 TIV61 TIV62 TIV71 TIV72
0.43 0.57 0.46 0.54 0.82 0.18 0.45 0.55 0.31 0.69 0.21 0.79 0.81 0.19
Economic
Inflation TIV12 TIV13 TIV23 TIV24 TIV31 TIV32 TIV43 TIV44 TIV53 TIV54 TIV62 TIV63 TIV72 TIV73
0.79 0.21 0.83 0.17 0.99 0.01 0.88 0.12 0.67 0.33 0.78 0.22 0.21 0.79
Availability of labour and TIV13 TIV14 TIV23 TIV24 TIV34 TIV35 TIV44 TIV45 TIV53 TIV54 TIV63 TIV64 TIV72 TIV73
equipment 0.17 0.83 0.19 0.81 0.82 0.18 0.79 0.21 0.21 0.79 0.23 0..77 0.21 0.79
Physical
Ground conditions TIV12 TIV13 TIV22 TIV23 TIV31 TIV32 TIV43 TIV44 TIV52 TIV53 TIV62 TIV63 TIV71 TIV72
0.67 0.33 0.63 0.37 0.32 0.68 0.39 0.61 0.67 0.33 0.57 0.43 0.78 0.22
Rights of access to site TIV11 TIV12 TIV22 TIV23 TIV32 TIV33 TIV42 TIV43 TIV52 TIV53 TIV62 TIV63 TIV71 TIV72
0.21 0.79 0.59 0.41 0.89 0.11 0.77 0.23 0.88 0.12 0.87 0.13 0.93 0.07
Quantity variations TIV13 TIV14 TIV23 TIV24 TIV33 TIV34 TIV43 TIV44 TIV53 TIV54 TIV63 TIV64 TIV72 TIV73
0.21 0.79 0.21 0.79 0.34 0.66 0.32 0.68 0.18 0.82 0.82 0.18 0.68 0.32
Inclement weather TIV13 TIV14 TIV23 TIV24 TIV31 TIV32 TIV43 TIV44 TIV53 TIV54 TIV62 TIV63 TIV72 TIV73
0.19 0.81 0.21 0.79 0.45 0.55 0.17 0.83 0.24 0.79 0.32 0.68 0.31 0.69
Political and societal
Changes in laws and regulations TIV12 TIV13 TIV22 TIV23 TIV31 TIV32 TIV43 TIV44 TIV53 TIV54 TIV61 TIV62 TIV72 TIV73
0.29 0.71 0.27 0.73 0.15 0.85 0.16 0.84 0.37 0.63 0.16 0.84 0.58 0.42
Public disorder TIV11 TIV12 TIV21 TIV22 TIV31 TIV32 TIV41 TIV42 TIV51 TIV52 TIV61 TIV62 TIV71 TIV72
0.19 0.81 0.24 0.76 0.12 0.88 0.22 0.78 0.23 0.77 0.15 0.85 0.26 0.74
Labour disputes and strikes TIV13 TIV14 TIV23 TIV24 TIV33 TIV34 TIV44 TIV45 TIV53 TIV54 TIV63 TIV64 TIV72 TIV73
0.21 0.79 0.19 0.81 0.16 0.84 0.12 0.88 0.27 0.73 0.23 0.77 0.64 0.36
K.C. Lam et al. / International Journal of Project Management 25 (2007) 485–493 491

and it is unlikely controllable by the contractor: dðOVÞ ¼ ½1  0:21ð1stÞ þ 1  0:19ð2ndÞ þ    þ 2


IV3 = TIV32
 0:19ð10thÞ þ 1  0:31ð11thÞ þ    þ 1
and it is unlikely manageable by the contractor:
IV4 = TIV42  0:18ð127thÞ þ 2  0:18ð128thÞ=½0:21ð1stÞ
and it is very unlikely sustainable by the contractor: þ 0:19ð2ndÞ þ    þ 0:19ð10thÞ þ 0:31ð11thÞ
IV5 = TIV51
and it is very unlikely beneficial by the contractor: þ    þ 0:18ð127thÞ þ 0:18ð128thÞ
IV6 = TIV61 ¼ 35:86=17:06 ¼ 1:33
and the premium of transfer is unfavourable:
IV7 = TIV71 With reference to Fig. 4, the d(OV) for ‘‘Third Party De-
THEN the risk should be allocated to the owner: lay’’ lies between the owner’s risk and shared risk with
OV1 = 1 membership grade of 0.77 and 0.23, respectively. To con-
solidate a final decision, the output variable with the high-
From Table 2, the value of membership function of each est membership value is chosen. Accordingly, the final risk
input variable devised for this risk event regarding this rule is: allocation decision for ‘‘Third Party Delay’’ is the owner’s
risk. The result calculated and recommendations from the
TIV12 (unlikely) = 0.43 model for all risk events are presented in Table 3.
TIV22 (unlikely) = 0.46
TIV32 (unlikely) = 0.82 4.1. Analysis of the results
TIV42 (unlikely) = 0.45
TIV51 (very unlikely) = 0.31 The actual risk allocation stipulated in the RGCC for the
TIV61 (very unlikely) = 0.21 16 risk events is also listed in Table 3. Comparing the two
TIV71 (unfavourable) = 0.81 patterns, the final decision obtained from the model basi-
cally ties in with those in RGCC. The major deviation is
The membership value of output variable is thus found in the risk events ‘‘Inflation’’ and ‘‘Inclement
obtained by the ‘‘min’’ operation: weather’’. The model suggests that these two risks shall be
shared by both parties while the RGCC allocates them to
lðOV1 Þ ¼ min½0:43; 0:46; 0:82; 0:45; 0:31; 0:21; 0:81 ¼ 0:21 the contractor. Actually the recommendation from the
model is more consistent with the usual contracting practice
The overall level of risk allocation after examining by all as ‘‘Inflation’’ and ‘‘Inclement weather’’ are commonly trea-
base rules is determined by applying the center-of-sum ted as shared risk in most contract arrangements. A possible
method: reason for this alternative arrangement in RGCC is the

Table 3
Comparison of risk allocation decision between the model and RGCC
Events Numerical results Final risk allocation Risk allocation in
obtained from the model decision from the model RGCC
Capability
Contractor’s design 3.0 Contractor Contractor
Subcontractor failure 2.99 Contractor Contractor
Quality of work 2.99 Contractor Contractor
Safety at site 2.99 Contractor Contractor
Obtaining approval or consent from 2.75 Contractor Contractor
relevant authority
Contractual and legal
Conflicts in documents 1.02 Owner Owner
Third party delay 1.33 Owner Owner
Economic
Inflation 2.33 Share Contractor
Availability of labour and equipment 3 Contractor Contractor
Physical
Ground conditions 1.39 Owner Owner
Rights of access to site 1.27 Owner Owner
Quantity variations 2.69 Contractor Contractor
Inclement weather 2.43 Share Contractor
Political and societal
Changes in laws and regulations 2.27 Share Share
Public disorder 1.0 Owner Owner
Labour disputes and strikes 2.83 Contractor Contractor
492 K.C. Lam et al. / International Journal of Project Management 25 (2007) 485–493

political consideration that maximizing the certainty of the Kong Special Administrative Region, China [Project No.
price and progress of the proposed project is more impor- CityU 1293/04E].
tant than seeking the minimum cost of risks of the whole
project. It is, however, out of the scope of the risk allocation
criteria adopted in the model. The model also gives signals References
for some risk events to which special attention should be
paid. The numerical results of the risk events ‘‘Obtaining [1] Latham M. Constructing the team: joint review of procurement and
approval or consent from relevant authority’’, ‘‘Third party contractual arrangements in the United Kingdom construction
industry. London: HMSO; 1994.
delay’’, ‘‘Ground condition’’, ‘‘Right of access to site’’, [2] Rahman MM, Kumaraswamy MM. Risk management trends in the
‘‘Quantity variations’’ and ‘‘Change in laws and regula- construction industry: moving towards joint risk management. Eng
tions’’ lie somewhere between 2 risk allocation choices. Construct Archit Manage 2002;9(2):131–51.
While the algorithm finalizes the decision by choosing the [3] Edwards PJ, Bowen PA. Risk and risk management in construction: a
one with the highest membership value, the users can focus review and future directions for research. Eng Construct Archit
Manage 1998;5(4):339–49.
the resources to proceed further examination on these risks [4] Waring AI, Glendon AI. Managing risk. London: International
where necessary. After reconciliation, the expert team Thomson Business Press; 1998.
agreed to the result obtained from the model and recognised [5] Uff J. Risk, management and procurement in construction. London:
that the model had enabled them to consider all those risk Centre of Construction Law and Management; 1995.
allocation criteria in reaching the final decision. [6] Lyons T. Project risk management in the construction industry: a
review. Australia: The Australian Institute of Quantity Surveyor; 2003.
[7] Rutgers JA, Haley HD. Project risks and risk allocation. Cost Eng
5. Conclusions AACE Trans 1996;38(9):27–30.
[8] Flanagan R, Norman G. Risk management and construction.
New and project-specific risks emerged in today’s multi- Oxford: Blackwell Scientific Publications; 1993.
party complex construction projects that a tailor-made con- [9] Ward SC, Chapman CB, Curtis B. On the allocation of risk in
construction projects. Int J Project Manage 1991;9(3):140–7.
tract strategy allocating risks among the contracting parties [10] Fisk ER. Construction project administration. New Jersey: Prentice-
based on the accepted allocation principles is more desirable. Hall; 2000.
The prototypic decision model proposed in this paper dem- [11] CII (Construction Industry Institute). Allocation of insurance related
onstrates the extraction and transformation of these impre- risks and costs on construction projects. University of Texas at
cise linguistic principles and experiential expert knowledge Austin, Austin; 1993.
[12] Thompson P, Perry J. Engineering construction risks: a guide to
into a more usable quantitative-based analysis by using the project risk analysis and risk management. London: Thomas Telford
fuzzy set theory. It has several advantages. It provides an Ltd; 1992.
explicit and systematic framework in risk allocation practice [13] Casey JJ. Identification and nature of risks in construction project: a
rather than a subjective and untraceable approach based on contractor’s perspective. In: Proceedings: construction risk and
individual’s professional judgement. It examines the alloca- liability sharing conference. Scottsdale (USA): American Society of
Civil Engineers; 1979. p. 17–24.
tion of risks more fundamentally based on accepted risk allo- [14] Kuesel TR. Allocation of risks. In: Proceedings: construction risk and
cation principles rather than simply using standard clauses liability sharing conference. Scottsdale (USA): American Society of
from typical conditions of contract without appreciating Civil Engineers; 1979. p. 51–60.
the rationale behind. The outcome of the model can be in [15] Barnes M. How to allocate risks in construction contracts. Int J
numerical or linguistic indication which provides appropri- Project Manage 1983;1(1):24–8.
[16] Abrahamson MW. Risk management. Int Construct Law Rev
ate signals to different users. As a decision support tool, it 1984;1(3):241–64.
provides a ground for the users in reaching a final decision. [17] Grove JB. Consultant’s report on review of general conditions of
Through the model building involving different experts from contract for construction works for the government of the Hong Kong
the owners, consultants and contractors in the early stage of special administrative region. New York: Thelen Reid & Priest Lip; 1998.
the risk allocation decision, the final outcome will be more [18] CIRC (Construction Industry Review Committee). Construct for
excellence: report of the Construction Industry Review Committee.
agreeable by different contracting parties. Currently, the HK SAR Government, HK; 2001.
scope of the proposed model is limited to risk allocation [19] Baloi D, Price ADF. Modelling global risk factors affecting
between the owner and the contractor in a traditional con- construction cost performance. Int J Project Manage 2003;21:261–9.
tract arrangement. There is room for upgrading when more [20] Zadeh LA. The concept of a linguistic variable and its application to
information and expert knowledge can be pooled. It can be approximate reasoning. Inform Sci 1975;8:199–249.
[21] Zimmermann HJ. Fuzzy set theory and its applications. third ed.
modified to suit a specific context or project strategy by USA: Kluwer Academic Publishers; 1996.
adjusting or expanding the risk allocation criteria, the mem- [22] Zadeh LA. Commonsense reasoning based on fuzzy logic. In: Proceed-
bership functions of the variables and the inference rules. ings of the 1986 winter simulation conference. Washington: IEEE; 1986.
[23] Tanaka K. An Introduction to fuzzy logic for practical applications.
New York: Springer-Verlag Inc; 1997.
[24] Chapman C, Ward S. Project risk management: processes, techniques
Acknowledgement and insights. Chichester: John Wiley and Sons; 1997.
[25] Hartman F, Snelgrove P, Ashraft R. Effective wording to improve
The work described in this paper was fully supported by risk allocation in lump sum contracts. J Construct Eng Manage
a grant from the Research Grants Council of the Hong 1997;123(4):379–87.
K.C. Lam et al. / International Journal of Project Management 25 (2007) 485–493 493

[26] Wong KC, So ATP. A fuzzy expert system for contract decision [28] Klir GJ, Yuan B. Fuzzy sets and fuzzy logic – theory and
making. Construct Manage Econ 1995;13:95–103. applications. New Jersey: Prentice Hall; 1995.
[27] Lam KC, So ATP, Hu T, Ng T, Yuen RKK, Lo SM, Cheung SO, [29] Keizer JA, Halman JIM, Song M. From experience: applying the
Yang H. An integration of the fuzzy reasoning technique and the risk diagnosing methodology. J Prod Innov Manage 2002;19(3):
fuzzy optimization method in construction project management 213–32.
decision-making. Construct Manage Econ 2001;19:63–76.

You might also like