Professional Documents
Culture Documents
3, 2014 193
Abdulaziz M. Jarkas*
Projects Development Department,
Al Mazaya Holding Co., KSCP (Holding),
P.O. Box 3546, Safat 13036, Kuwait
Email: jarkas@mazayarealestate.com
*Corresponding author
Sasa Marenjak
Faculty of Civil Engineering,
University of Osijek and Zagreb,
P.O. Box 716, HR-3000, Osijek, Croatia
Email: sasa.marenjak@zg.htnet.hr.com
1 Introduction
While cost performance remains among the most important success measures of
construction enterprises (Chan and Chan, 2004), cost overrun continues to be a major
problem within the industry, where projects are rarely completed within budgeted costs
(Chimwaso, 2001; Azhar et al., 2008; Abdul Rahman et al., 2013). This chronic dilemma,
moreover, exists both, in developed and developing countries, and is associated with
almost all types and scales of projects (Reina and Angelo, 2002; Koushki et al., 2005; Ali
and Kamaruzzaman, 2010; Abdulazis et al., 2013).
Flyvbjerg et al. (2003), in one of the most elaborate studies aimed at exploring the
global problem of cost performance in transport construction projects, investigated
258 projects located in 20 developed and developing nations worth approximately
US$90 billion, and found that cost overrun was evident in nine out of ten projects, with
an average increase of 28%, in comparison with budgeted costs. The study concluded, on
the one hand, that the average cost overruns were 25.7% in Europe, 23.6% in
North America, and 64.6% in other geographical areas, and that cost performance has not
improved over the past 70 years, on the other. This phenomenon, therefore, has become
the rule rather than the exception in the construction industry (Baloi and Price, 2003;
Flyvbjerg et al., 2003).
Several definitions of cost overrun, also referred to as budget overrun or cost
increase, are encountered in the literature (e.g., Avotos, 1983; Dlakwa and Cuplin, 1990;
Iyer and Jha, 2005; Azhar et al., 2008; Enshassi et al., 2009; Durdyev et al., 2012;
Kasimu, 2012; Sweis et al., 2013). Nonetheless, they can all be practically considered as
synonyms to: “the additional expenditure or cost incurred in excess of the original
budgeted amount, at the time of a project completion.”
Construction cost overrun can occur due to many reasons. However, it is crucial to
distinguish between the following two quite different issues, which are frequently, yet
Significant contributors to construction cost overruns 195
information about construction cost underestimation and cost overrun, the reader is
referred to Ahiaga-Dagbui and Smith (2014).
There are many challenges facing the construction industry in the State of Kuwait, but
as the case with other countries, cost overruns in projects is among the most pressing. In
spite of all the technological advancements, abundance of construction equipment, tools,
and financial means available to local contractors, most construction projects are
significantly overrunning their budgeted costs (Jarkas and Bitar, 2012).
The primary objective of this research, therefore, is to identify and rank, based on the
perception of ‘general contractors’ operating in the state, the relative importance of
factors instigating cost overruns in projects, so that the findings can be used by
academics, local and international contractors, in addition to clients, consultants, and
policy makers, to develop a wider and deeper perspective of the significant factors
determined, which can lead to the development of reasonable control measures thereto,
not only during the construction stages, but also along the evolution of the design phases
of projects, and further assist in achieving an acceptable level of competitiveness and cost
effective operation.
This paper starts with a literature review of previous related studies, presents the
research method and data analysis, provides a discussion of the results obtained, and
concludes, based on the results emerged from this investigation, with practical
recommendations geared toward alleviating the adverse influence of the critical factors
discerned on the cost performance of construction projects in Kuwait.
2 Literature review
Construction cost overrun has been the subject of numerous research studies. Arditi et al.
(1985) carried out a survey to identify the main causes for construction cost overruns in
Turkish public projects, which were constructed between the 1970s and 1980s, and
reported the following critical factors:
a increase in material prices
b inflation
c difficulties in producing products at official prices due to the fast growth of inflation
d frequent changes in design and specifications
e inaccurate estimates at the time of creating the budget of the project.
Okpala and Aniekwu (1988) examined the factors instigating construction cost overrun in
Nigeria, and discerned:
1 shortage of materials
2 finance and payment of completed works
3 poor contract management, as most important.
Kaming et al. (1997), on the other hand, investigated the causes of cost overruns in the
Indonesian construction industry, and recognised the following factors as most
influential:
Significant contributors to construction cost overruns 197
a client
b consultant
c contractor
d external, under which the various causes explored by this research study shall be
allocated.
Even though it may be criticised on the grounds of causal explanation (Ackroyd and
Hughes, 1981), this research study is inherently quantitative, where the results are mainly
used to underpin the qualitative interpretations, and thus, is not in conflict with the
phenomenological paradigm.
The related data to this investigation were collected by a structured – close-ended –
questionnaire survey. The logic underlying the selection of such a data collection method
is four-fold:
1 compared to telephone or face-to-face interviews, it is less intrusive and cost
effective, which is particularly advantageous for collecting large sample sizes
2 the familiarity of the questionnaire survey concept to most potential respondents
3 the practicality and relative simplicity, with which the sets returned can be analysed
4 in comparison with telephone and interviews methods, it assists in alleviating the
bias that may be introduced by researchers’ verbal and visual clues, respectively.
Based on previous reviewed studies on causes of cost overruns in the construction
industry, but most importantly, their applicability and relevance to local construction
projects, as recognised by industry practitioners and experts in the state, 45 causes were
identified and shortlisted as being potentially significant, or among the relatively
influential contributors to construction cost overruns in Kuwait. Table 1 presents the
causes surveyed, and the associated four major groups under which categorised.
Table 1 Contributors to construction cost overruns in Kuwait and related groups
Table 1 Contributors to construction cost overruns in Kuwait and related groups (continued)
The target population included classified construction firms by the ‘Central Tenders
Committee’ (CTC) of the state. The classification criteria for Kuwaiti construction
contractors are based on:
a the credentials of the technical and administrative staff employed
b equipment and tools available
c the financial position and strength
d previous experience.
As a result, a total number of 400 organisations, classified under the first, second, and
third categories, were identified (CTC, 2013).
In order to obtain a statistically representative sample of the population, the formula
shown in equation (1) was used (Hogg and Tannis, 2009).
m
n= (1)
⎛ m −1 ⎞
1+ ⎜ ⎟
⎝ N ⎠
where n, m and N represent the sample size of the limited, unlimited, and available
population, respectively. On the other hand, m is estimated by equation (2).
z 2 * p *(1 − p )
m= (2)
ε2
where z is the statistic value for the confidence level used, i.e., 2.575, 1.96, and 1.645, for
99%, 95%, and 90% confidence levels, respectively; p is the value of the population
proportion which is being estimated; and ε is the sampling error of the point estimate.
Since the value of p is unknown, Sincich et al. (2002) suggest a conservative value of
0.50 be used so that a sample size that is at least as large as required be obtained. Using a
95% confidence level, i.e., 5% significance level, the unlimited sample size of the
population, m, is quantified by equation (2), as follows:
(1.96) 2 *0.50*(1 − 0.50)
m= = 385
(0.05) 2
Therefore, for the total number of 400 classified contractors, i.e., N, the representative
sample size of the population required is determined by equation (1), as shown below:
385
n= = 196
⎛ 385 − 1 ⎞
1+ ⎜ ⎟
⎝ 400 ⎠
The questionnaire comprised an ordinal measurement scale ranking the effect level of
each factor surveyed in an ascending order from 1 to 5. Nonetheless, it is important to
note that the numbers assigned to the scale do not indicate equal intervals or absolute
quantities, rather, the effect degree of each factor, from the respondents’ perception.
To establish a reasonable validity of the results obtained, and assess the reliability of
the questionnaire, a pilot test was conducted on samples of the prospective respondents.
The questionnaire, thus, was distributed to 22 contractors, who have expressed genuine
Significant contributors to construction cost overruns 207
interest in providing objective assessment and feedback on the research data collection
instrument. The aim of this test was four-fold:
1 to assess the clarity, comprehensibility, interpretation, and appropriateness of the
questions provided in capturing the causes of cost overruns in construction projects
in Kuwait
2 to test the range adequacy of response choices
3 to assess the internal consistency of the questionnaire
4 to determine the efficiency, with which the respondents complete the questionnaires.
Apart from minor comments, which were related to some contextual interpretations of
few questions, the respondents’ feedback was positive. Therefore, the authors
rearticulated such questions using simpler expressions and incontrovertible background
to avoid any future confounding of the framework, within which the response of the
participants is sought.
The internal consistency of the questionnaire was tested by computing the
‘Cronbach’s alpha’ of the sets returned. The alpha coefficient ranges in value from 0 to 1,
and is used to describe the reliability of factors extracted from dichotomous, multi-point
formatted, or ordinal rating scale questionnaires. Cronbach’s alpha (α) is calculated by
equation (3) (Howitt and Cramer, 2008).
α=
n ⎛⎜
1−
∑ Vi ⎞
⎟ (3)
n −1 ⎜ Vtest ⎟
⎝ ⎠
where n is the number of questions; Vi is the variance of scores on each question; and Vtest
is the total variance of the overall scores. The higher the alpha coefficient score, the more
reliable the generated scale is. Nunnaly (1978) indicated that a value of 0.700 is an
acceptable reliability coefficient; however, lower thresholds are commonly encountered
in the literature.
Cronbach’s alpha for the sample group of contractors was computed by the Statistical
Package for the Social Sciences (SPSS V18) software, where a coefficient value of 0.782
was obtained, which indicates an acceptable measure of questionnaire reliability by all
respondents. Therefore, a total of 250 randomly chosen firms from the CTC list of
classified contractors were approached to participate in the survey, and followed up,
when possible, by phone calls, direct contacts, and frequent reminders.
The data collection phase spanned approximately ten months, after which, a total of
174 questionnaires were received, of which, 162 were deemed acceptable, representing
approximately 83% of the required sample size; however, suggests reasonable reliability,
validity, and robustness of the findings. The respondents are considered senior ranking
officials within their organisations, mainly comprising technical directors, contracts
managers, and construction project managers, with a minimum of 20 years of practical
experience in the local construction industry. Such a background of respondents lends
further credibility to the results obtained, the authors append.
The data collected were subsequently analysed using the ‘relative importance index’
(RII) technique (Fugar and Agyakwah-Baah, 2010; Jarkas and Bitar, 2012; Jarkas et al.,
2012). The RII for each cause surveyed was quantified by the formula shown in
equation (4).
208 A.M. Jarkas and S. Marenjak
where n1; n2; n3; n4; and n5, are the number of respondents who selected: 1, for no
effect; 2, for little effect; 3, for moderate effect; 4, for strong effect; and 5, for very strong
effect, respectively.
The RII, which value ranges from 0 (not inclusive) to 1, was used to determine the
rank of each cause explored; the higher the RII value, the stronger the perceived
influence of the factor causing cost overrun within construction projects in the State.
On the other hand, the rank for each of the four main groups, as perceived by
contractors, was determined by quantifying the average value of the RIIs for all causes of
cost overruns allocated under; the higher the average value, the stronger the collective
effect of the related group (Sambasivan and Soon, 2007).
Table 2 Overall relative importance indices, related groups, and ranks of contributors surveyed
(continued)
a
Contributor RII Related group Rank
Underestimation of construction cost 0.698 Contractor 17
Inadequate construction methods 0.693 Contractor 18
Low labour productivity 0.690 Contractor 19
Inclement weather 0.687 External 20
Delay in review and approval of materials submission by 0.681 Consultant 21
the engineer
Contract procurement method 0.677 Client 22
Difficulties in financing the project by client 0.673 Client 23
Design complexity level 0.671 Consultant 24
Lack or limited authority granted to client representatives 0.667 Client 25
Poor estimation of construction budget 0.662 Client 26
Delay in responding to requests for information (RFI) 0.659 Consultant 27
Shortage in skilled labour and technical staff 0.653 External 28
Rework due to errors and faulty work 0.648 Contractor 29
Inadequate qualifications and experience of contractor 0.639 Contractor 30
Lack or improper selection of suitable tools and equipment 0.633 Contractor 31
Consultant’s poor communication with contractor 0.624 Consultant 32
Delay in payment review and certification by the engineer 0.607 Consultant 33
Employment of unqualified and inexperienced contractor’s 0.602 Contractor 34
site management personnel
Lack of construction knowledge and experience of client 0.593 Client 35
representatives
Delay in shop drawings review and approval by the 0.589 Consultant 36
engineer
Stringent inspection procedures applied by the engineer 0.581 Consultant 37
Client’s poor communication and coordination with 0.578 Client 38
consultant
Poor communication between site management and labour 0.567 Contractor 39
force
Site layout 0.564 Contractor 40
Cost escalation due to inflation 0.558 External 41
Accidents resulting from poor safety programme applied on 0.552 Contractor 42
site
Delay in subcontracting work packages 0.548 Contractor 43
Frequent changes in statutory regulations 0.535 External 44
Delay in performing inspections and certifications by 0.511 External 45
statutory authorities
Note: aRelative importance index
210 A.M. Jarkas and S. Marenjak
According to the overall perceived importance of factors surveyed, the results obtained
show that the ten top contributors to construction cost overruns in the State are the
following:
Since some of the significant causes distinguished share common characteristics and
dependencies, to avoid redundancy, the discussion of such causes is carried out
collectively, irrespective of the rank order determined.
In comparison with the 45 causes surveyed, ‘frequent change orders issued by client
during construction’, with an RII of 0.886, is perceived as the salient contributor to
construction cost overruns in the state. This finding agrees with the results obtained by
Koushki et al. (2005), Oladapo (2007), Kaliba et al. (2009), Osman et al. (2009), Turkey
(2011), and Alinaitwe et al. (2013), whose investigations have asserted the adverse effect
of clients’ change requests on cost performance of construction projects in Kuwait,
South Africa, Zambia, Malaysia, Ethiopia, and Uganda, respectively.
According to Parker (2002), a change order is defined as “works, processes, or
methods that deviate from original plans and specifications.” Frequent disruptions and
redirection of works associated with change orders can, not only result in prolongation in
construction schedules, but also in labour productivity degradation, demolition and
rework, additional procurement activities, and possibly, disputes and litigations, all of
which can translate into significant construction cost overruns in projects under
development.
This outcome may be largely attributed, individually or collectively, to the following
three reasons:
1 clients’ little involvement, in particular those belonging to the private sector, in the
various design phases of projects
2 the lack of foreign designers’ experience in the social, cultural, and physical
environment of the state
3 simply due to clients’ ‘change of heart’, particularly to plans (i.e., architectural
layouts and circulations), fixtures, ornamental features, and finishes.
Significant contributors to construction cost overruns 211
Consequently, changes are often requested after contractual agreements have been
executed; at times, even after physical erections of major parts of projects have taken
place.
With quantified RIIs of 0.841, 0.833, 0.825, 0.802, 0.778, and 0.761, ‘errors and
omissions in design drawings’, ‘incomplete design details at the tendering stage’, ‘design
changes during construction’, ‘discrepancy in contract documents’, ‘clarity of technical
specifications’, and ‘contractual clauses and specifications interpretation’, rank 2nd, 3rd,
4th, 6th, 9th, and 10th, respectively.
Noting that 60% of the discerned critical causes instigating cost overruns are related
to the consultants’ outputs, further corroborate the results obtained by Jarkas and Bitar
(2012), whose research study has identified ‘constructability’ as the most prominent
concept affecting the performance of construction projects in Kuwait.
Constructability, commonly referred to as ‘buildability’ in Europe, as defined by the
Construction Industry Institute (CII) (1986), is “the optimum use of construction
knowledge and experience in planning, design, procurement, and field operations to
achieve overall project objectives”. On the other hand, the Construction Industry
Research and Information Association (CIRIA) (1983), describes buildability as “the
extent to which the design of a building facilitates ease of construction, subject to the
overall requirements for the completed building”. Although both expressions target
similar issues, the term constructability covers wider range of disciplines including
conceptual planning, design, procurement, and construction.
Nevertheless, an early attempt to address this concept can be credited to
Sir Harold Emmerson (1962), when he suggested a new form of relationship between
designers and contractors. The point of concern was the lack of cohesion between the two
parties and their inability to see the whole construction process through each other’s eyes.
Errors and omissions in design drawings, incomplete details, discrepancy in contract
documents, unclear technical specifications, and ambiguous contractual clauses, require
continuous requests for information, clarifications, and interpretations, and thus,
consecutive disruptions and interruptions to work progress. Furthermore, numerous
changes or substantial alterations to design documents during construction, may lead to
complete halt of related activities, productivity degradation, possible demolition and
rework, schedule slippage, and ultimately, cost overruns (Jarkas, 2013; Subramanyan
et al., 2012).
The perceived effects of such constructability factors on construction cost overruns
can be ascribed, in whole or in part, to the following primary causes:
1 the insufficient durations and tight schedules imposed upon consultants to develop
and review design alternatives, related details, specifications, and contract
documents, and therefore, contract documents are often unclear, incomplete, and
contain serious discrepancies, errors, and omissions among the various disciplines
involved
2 the shortfall in applying constructability principles among several consultants
operating in the state, which may further suggest a lack of awareness on their part of
the importance of this concept to the successful progress of the construction
operation
3 the deficiency of some consultants in providing ‘quality’ work and effective
professional services.
212 A.M. Jarkas and S. Marenjak
Supporting the findings of Odeh and Battaineh (2002), Iyer and Jha (2005), Faridi and
El-Sayegh (2006), Tumi et al. (2009), and Alhomidan (2013), whose research studies
have determined the detrimental impact of clients’ inefficiency in decision-making on
construction cost performance in Jordan, India, UAE, Libya, and Saudi Arabia,
respectively, ‘slow decision-making process by client’, with an RII of 0.819, ranks 5th, in
comparison with the 45 causes surveyed.
In accordance with local industry practice, important decisions are most often
required by clients both, before and during the physical developments of construction
projects. For instance, the formal approval of shortlisted subcontractors, suppliers,
mechanical, electrical and plumbing (MEP) equipment and fixtures models (including
trade-marks and country of origin), architectural facades, finishes and colour samples of
materials, hard and soft landscape features, revised plans, in addition to technical
specifications for alternatives and substitutions, must be obtained from clients prior to
materials procurement and commencement of related activities.
‘Delay in payment process by client’, a finding which is directly related to clients’
inefficiency in decision-making, and in further agreement with the results obtained by
Olawale and Sun (2010), Abdul Rahman et al. (2013), Alhomidan (2013), and Alinaitwe
et al. (2013), whose studies have identified this factor among the major causes of
construction cost overruns in the UK, Malaysia, Saudi Arabia, and Uganda, respectively,
with an RII of 0.767, ranks 9th among the causes examined.
However, in order to position this factor within the framework of the study, it is
important not to confuse this cause with ‘clients’ financial difficulties’, the importance
level of which is elicited separately, on a justifiable ground that prolonging payments
process due to clients’ pure inefficiency or sheer reluctance in decision-making, and/or
unnecessarily bureaucratic procedures, should be distinguished from constraining
financial circumstances, which can, on the one hand, be related to unexpected and
unforeseen events, and thus are beyond the control of clients, or may simply be linked to
clients’ mismanagement of financial resources, on the other.
Irrespectively, excessive delays in processing contractors’ due payments can
create financial overburdens on contractors to meet their obligations toward their
subcontractors, suppliers, site technical staff, and direct labourers, and hence, this may
lead to a serious ‘knock-on’ cash flow problem, where the financial stability of the whole
chain may be severely impacted.
In view of the preceding discussion, the inefficiency in clients’ decision-making
process can be attributed, in whole or in part, to the following reasons:
a the clients’ bureaucratic chain of approvals, most noticeably in public projects
b the limited authority vested in clients’ staff, especially those at the supervisory
levels, to render timely decision on submitted samples of proposed materials,
specifications of alternatives or substitutions, and payment applications received
c the cultural perception, as the case with most developing countries, of possible
contractors’ favouritism in the case of prompt evaluation and acceptance of
submissions, including positive recommendation for payments processing
(Al-Tabtabai, 2002), encourages clients’ representatives to either prolong the
decision-making process, or simply shift such a responsibility toward the higher or
top clients’ administrative staff, where the decision could be significantly delayed.
Significant contributors to construction cost overruns 213
Juxtaposing all of the aforementioned required decisions with the frequent changes
requested by clients along the course of the construction operation, in addition to the
financial difficulties encountered by contractors as a result of payments stagnation, and
the pernicious effect of clients’ inefficiency in decision-making on construction cost
performance of projects becomes palpable.
With an RII of 0.797, ‘unavailability or shortage of specified materials’, ranks 7th
among the 45 causes of cost overruns explored. This outcome substantiates the findings
of Okpala and Aniekwu (1988), and Koushki and Kartam (2004), whose investigations
have recognised the inimical impact of this factor on cost performance of construction
projects in Nigeria and Kuwait, respectively.
Although it can be reasonably argued that this finding is connected with foreign
consultants’ lack of knowledge of the local availability of specified construction
materials, the outcome may be further ascribed to the current ‘supply-demand’ curve,
where the demand for some materials, in relation to its local availability, could be much
higher, and thus creating a major shortage of supply to projects underway. It could also
be referred, according to the results obtained by Bubshait and Al-Juwait (2002), and
Enshassi et al. (2010), to local suppliers’ manipulation and market monopoly, in order to
induce an ‘artificial’ inflation of prices.
The result is conceivable as materials are essential to the construction process, and
hence, work cannot be accomplished without them. Consequently, unavailability,
shortage, or interrupted supply of materials to jobsites leads to disruption of the
workforce momentum and progress of activities, which may necessitate, at times,
procuring at higher than contractual prices, otherwise resort to change orders for
substitutions or alternatives, and subsequently undergo through the wasteful approval
cycle process, as previously highlighted. Nonetheless, either route entails a construction
cost overrun, the findings suggest.
Table 3, on the other hand, presents the overall ranking of the four major groups,
under which the factors investigated are categorised.
Table 3 Groups average RIIs and ranks
With an average RII of 0.714, ‘consultant’ related causes rank 1st in their collective
influence, and hence, are perceived as the most significant contributors to construction
cost overruns in the State of Kuwait. Causes partitioned under the ‘client’ group, with an
average RII of 0.702, rank 2nd over the ‘contractor’ and ‘external’ group factors, which
come in 3rd and 4th in ranks, with average RIIs of 0.649 and 0.637, respectively.
It is worth noting that equal basis comparison of group rankings necessitates similar
taxonomies. Contrasting the pattern established by this study to those determined by
previous investigations is, therefore, inapplicable.
The pattern depicted, in view of the critical causes determined, is justified, where out
of the top 10 factors, 6 and 3 (i.e., 90%) belong to the consultant and client groups,
respectively. The outcomes further reveal an interesting trend. By inspection, it can be
214 A.M. Jarkas and S. Marenjak
realised that the ‘mean values’ of the RIIs of the groups make modicum distinctions
between the collective effects of causes belonging to the ‘consultant and client groups’
(0.714 vs. 0.702), on the one hand, and those related to the ‘contractor and external
groups’ (0.649 vs. 0.637), on the other, a pattern which may be expected, noting that the
respondents belong to the ‘contractor’ group, and thus may suggest some sort of a ‘bias’
on the respondents’ side, as a result of an anecdotal ‘blaming’ attitude.
However, upon further examination of the RIIs values of the causes allocated under
the contractors’ category – although none is identified within the significant contributors
established – coupled with a perfunctory comparison between the mean RII value of the
contractors’ group and the average RII values of the other groups, the overall pattern
emerged reasonably negates such a plausible inclination. Simply put, the quantified RIIs
reveal tenuous differences between the effects of causes associated with the ‘contractor’
group, and those linked to other groups, both separately and cumulatively, suggesting,
therefore, reasonable impartiality, objectivity, and credibility of the results obtained.
1 client
2 consultant
3 contractor
4 external.
Based on the overall perceived importance of the factors surveyed, the findings reveal
that the most significant contributors to construction cost overruns in the state, in a
descending order, are the following:
Additionally, the quantified average RIIs of the four major groups, under which the
causes explored are categorised, recognise the factors associated with the ‘consultant’
group as most influential, followed by the ‘client’, ‘contractor’, and ‘external’
group-factors, respectively. Nonetheless, the modicum differences among the perceived
relative importance of the major groups, and the causes investigated, suggest that the
collective impact of each group factors, in addition to most of the individual causes, are
fairly comparable with those belonging to other groups, on the one hand, and among one
another, on the other.
Even though such a pattern renders further validity to the causes shortlisted, and
subsequently surveyed, distinguishing one cause from another is rather impractical.
Consequently, what is suggested to guide the problem solution is to consider most of the
causes surveyed, with special emphasis, however, being placed on the prominent factors
identified.
It is a common objective among clients, consultants, contractors, and policy makers
in Kuwait to enhance the cost performance of construction projects, which can be
augmented if original contracts flow with minimum or controlled variability, the findings
indicate.
The adverse effect of frequent change orders on construction cost overruns can be
moderated by clients’ direct involvement in the design phase of projects through
authorised representatives, who can effectively review, evaluate, scrutinise, and render
timely feedback on the compatibility level of the various options and specifications
proposed by consultants with local traditions and environmental conditions, prior to
commencement of construction activities.
This cause may be further developed by appointing, in the first instance, consultants
who possess sufficient expertise in the local culture, physical environment characteristics,
web of suppliers, and availability of construction materials, so that, with limited
intervention from clients, can largely achieve projects’ objectives. Therefore, minor
changes to drawings or specifications, should they become necessary along the course of
the construction operation, can be implemented with minimum cost impacts.
Clients, moreover, can reasonably restrain cost overruns by devising a ‘modus
operandi’ for efficient decision-making, including timely actions on contractors due
payments, which may be achieved by:
References
Abdul Rahman, I., Memon, A. and Abd Karim, A. (2013) ‘Significant factors causing cost overruns
in large construction projects in Malaysia’, Journal of Applied Sciences, Vol. 13, No. 2,
pp.286–293.
Abdulazis, A., Memon, A., Abdul Rahman, I. and Abd Karim, A. (2013) ‘Controlling cost overrun
factors in construction projects in Malaysia’, Research Journal of Applied Sciences,
Engineering and Technology, Vol. 5, No. 8, pp.2621–2629.
Ackroyd, S. and Hughes, J. (1981) Data Collection in Context, Longman, London, UK.
Ahiaga-Dagbui, D. and Smith, D. (2014) ‘Rethinking construction cost overruns: cognition,
learning and estimation’, Journal of Financial Management of Property and Construction,
Vol. 19, No. 1, pp.38–54.
Alhomidan, A. (2013) ‘Factors affecting cost overrun in road construction projects in
Saudi Arabia’, International Journal of Civil & Environmental Engineering, Vol. 13, No. 3,
pp.1–4.
Ali, A. and Kamaruzzaman, S. (2010) ‘Cost performance for building construction projects in
Klang Valley’, Journal of Building Performance, Vol. 1, No. 1, pp.110–118.
Alinaitwe, H., Apolot, R. and Tindiwensi, D. (2013) ‘Investigation into the causes of delays and
cost overruns in Uganda’s public sector construction projects’, Journal of Construction in
Developing Countries, Vol. 18, No. 2, pp.33–47.
Al-Tabtabai, H. (2002) ‘Causes for delays in construction projects in Kuwait’, Engineering Journal
of Qatar University, Vol. 15, pp.19–37.
Arcila, S. (2012) Avoiding Cost Overruns in Construction Projects in the United Kingdom, MS
Dissertation, Programme and Project Management, Warwick Manufacturing Group, The
University of Warwick, Coventry, UK.
Arditi, D., Akan, G. and Gurdamar, S. (1985) ‘Cost overruns in public projects’, International
Journal of Project Management, Vol. 3, No. 4, pp.218–224.
Avotos, I. (1983) ‘Cost-relevance analysis for overrun control’, International Journal of Project
Management, Vol. 1, No. 3, pp.142–148.
Azhar, N., Farooqui, R. and Ahmed, S. (2008) ‘Cost overrun factors in construction industry of
Pakistan’, First International Conference on Construction in Developing Countries
(ICCIDC-1), Advancing and Integrating Construction Education, Research & Practice,
Karachi, Pakistan, 4–5 August, pp.499–508.
Baloi, D. and Price, A. (2003) ‘Modelling global risk factors affecting construction cost
performance’, International Journal of Project Management, Vol. 21, No. 4, pp.261–269.
Baloyi, L. and Bekker, M. (2011) ‘Causes of construction cost and time overruns: the 2010 FIFA
World Cup Stadia in South Africa’, Acta Structilia: Journal for the Physical and Development
Sciences, Vol. 18, No. 1, pp.51–67.
Bubshait, A. and Al-Juwait, Y. (2002) ‘Factors contributing to construction costs in Saudi Arabia’,
Cost Engineering, Vol. 44, No. 5, pp.30–34.
Central Tenders Committee (CTC) (2013) Council of Ministers, Classified Companies, State of
Kuwait [online] http://www.ctc.gov.kw (accessed 5 January 2013).
Chan, A. and Chan A. (2004) ‘Key performance indicators for measuring construction success’,
Benchmarking: An International Journal, Vol. 11, No. 2, pp.203–221.
Chimwaso, K. (2001) ‘An evaluation of cost performance of public projects; Case of Botswana’,
Proceedings of the 2nd International Conference of the CIB [online]
http://buildnet.csir.co.za/cdcproc/docs/2nd/chimwaso_dk.pdf (accessed 28 November 2012).
Construction Industry Research and Information Association (CIRIA) (1983) Buildability: An
Assessment, Construction Industry Research and Information Association, Special Publication
No. 26, London, UK.
218 A.M. Jarkas and S. Marenjak
Kaming, P., Olomolaiye, P., Holt, G. and Harris, F. (1997) ‘Factors influencing construction time
and cost overruns on high-rise projects in Indonesia’, Construction Management and
Economics, Vol. 15, No. 1, pp.83–94.
Kasimu, M. (2012) ‘Significant factors that cause cost overruns in building construction projects in
Nigeria’, Interdisciplinary Journal of Contemporary Research in Business, Vol. 3, No. 11,
pp.775–780.
Koushki, P. and Kartam, N. (2004) ‘Impact of construction materials on project time and cost in
Kuwait’, Engineering, Construction and Architectural Management, Vol. 11, No. 2,
pp.126–132.
Koushki, P., Al-Rashid, K. and Kartam, N. (2005) ‘Delays and cost increases in the construction of
private residential projects in Kuwait’, Construction Management and Economics, Vol. 23,
No. 3, pp.285–294.
Kruger, J. and Dunning, D. (1999) ‘Unskilled and unaware of it: how difficulties in recognizing
one’s own incompetence lead to inflated self-assessments’, Journal of Personality and Social
Psychology, Vol. 77, No. 6, pp.1121–1134.
Le-Hoai, L., Lee, Y. and Lee, J. (2008) ‘Delays and cost overruns in Vietnam large construction
projects: a comparison with other selected countries’, KSCE Journal of Civil Engineering,
Vol. 12, No. 6, pp.367–377.
Lovallo, D. and Kahneman, D. (2003) ‘Delusions of success: how optimism undermines
executives’ decisions’, Harvard Business Review, July, Vol. 81, No. 7, pp.56–63.
Love, P., Edwards, D. and Irani, Z. (2011) ‘Moving beyond optimism bias and strategic
misrepresentation: an explanation for social infrastructure project cost overruns’, IEEE
Transactions on Engineering Management, Vol. 59, No. 4, pp.560–571.
Mahamid, I. and Burland, A. (2011) ‘Cost overrun causes in road construction projects:
consultants’ perspective’, Proceedings of the 2nd International Conference on Construction
and Project Management, IPEDR, IACSIT Press, Singapore, Vol. 15.
Mahamid, I. and Dmaidi, N. (2013) ‘Risks leading to cost overrun in building construction from
consultants’ perspective, organization’, Technology and Management in Construction: An
International Journal, Vol. 5, No. 2, pp.860–873.
Nunnaly, J. (1978) Psychometric Theory, McGraw-Hill, NY, USA.
Odeh, A. and Battaineh, H. (2002) ‘Causes of construction delay: traditional contracts’,
International Journal of Project Management, Vol. 20, No. 1, pp.67–73.
Ogunlana, S., Promkuntong, K. and Jearkjirm, V. (1996) ‘Construction delays in fast-growing
economy: comparing Thailand with other economies’, International Journal of Project
Management, Vol. 14, No. 1, pp.37–45.
Okpala, D. and Aniekwu, A. (1988) ‘Causes of high costs of construction in Nigeria’, Journal of
Construction Engineering and Management, ASCE, Vol. 114, No. 2, pp.233–244.
Oladapo, A. (2007) ‘A quantitative assessment of the cost and time impact of variation orders on
construction projects’, Journal of Engineering, Design and Technology, Vol. 5, No. 1,
pp.35–48.
Olawale, Y. and Sun, M. (2010) ‘Cost and time control of construction projects: inhibiting factors
and mitigating measures in practice’, Construction Management and Economics, Vol. 28,
No. 5, pp.509–526.
Osman, Z., Omran, A. and Foo, C. (2009) ‘The potential effects of variations orders in construction
projects’, Annals of Faculty of Engineering Hunedoara – Journal of Engineering, Vol. 7,
No. 2, pp.141–152.
Parker, M. (2002) ‘Dynamics change for fast-tracking construction project’, Proceedings of the
19th ISARC, International Association for Automation and Robotics in Construction,
Washington, USA, pp.81–89.
220 A.M. Jarkas and S. Marenjak
Reina, P. and Angelo, W. (2002) Megaprojects Need More Study Up Front to Avoid Construction
Overruns, Engineering News-Record (ENR), Business and Labor, 15 July [online]
http://enr.construction.com/news/bizlabor/archives/020715.asp (accessed 10 December 2012).
Sambasivan, M. and Soon, Y. (2007) ‘Causes and effects of delays in Malaysian construction
industry’, International Journal of Project Management, Vol. 25, No. 5, pp.517–526.
Sincich, T., Levine, D. and Stephan, D. (2002) Practical Statistics by Example using Microsoft®
Excel and Minitab®, 2nd ed., Prentice Hall, Upper Saddle River, NJ, USA.
Subramanyan, H., Sawant, P. and Bhatt, V. (2012) ‘Construction project risk assessment:
development of model based on investigation of opinion of construction project experts from
India’, Journal of Construction Engineering and Management, ASCE, Vol. 138, No. 3,
pp.409–421.
Sweis, G., Sweis, R., Abu Rumman, M., Abu Hussein, R. and Dahiyat, S. (2013) ‘Cost overruns in
public construction projects: the case of Jordan’, Journal of American Science, Vol. 9, No. 7s,
pp.134–141.
Tumi, S., Omran, A. and Pakir, A. (2009) ‘Causes of delay in construction industry in Libya’, The
International Conference on Economics and Administration, Faculty of Administration and
Business, University of Bucharest, Bucharest, Romania, 14–15 November, pp.265–272.
Turkey, W. (2011) Risk Factors Leading to Cost Overrun in Ethiopian Federal Road Construction
Projects and its Consequences, MS dissertation, Addis Ababa University, Addis Ababa,
Ethiopia.